5707 S WEST BLVD 90043
Certificate Information: 5707 S WEST BLVD 90043
- Application / Permit
- 20010-10000-02712
- Plan Check / Job No.
- B20LA14444
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- BUILD NEW 2 STORY DETACHED ACCESSORY DWELLING UNIT LOCATED IN REAR SIDE OF PROPERTY. EXPAND EXISTING DRIVEWAY
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 7/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | DANIEL YIP |
| Corrections Issued | 9/8/2020 | DANIEL YIP |
| Quality Review Completed | 10/9/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Plan Check Approved | 4/5/2021 | DANIEL YIP |
| Issued | 4/21/2021 | APPLICANT |
| CofO in Progress | 7/15/2022 | ANTHONY EGSON |
| Permit Finaled | 7/27/2022 | DEROLD HAUFF |
| CofO Issued | 7/27/2022 | DEROLD HAUFF |
| Permit Finaled | 7/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2020 | CECILIO NAVARRO |
| Permit | Cleared | 12/10/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/11/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 2/11/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/18/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Sc Contractors; Lic. No.: 980133-B | 19009 LAUREL ROAD #467 COMPTON, CA 90220 |
| Engineer | Gorgy,, Moheb Shohdy; Lic. No.: C53260 | 1545 VICTORY BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/10/2021 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/25/2021 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/13/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/13/2021 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2021 | Partial Approval | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 9/23/2021 | Approved | DAVID FEILER |
| Sewer | 9/23/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 9/23/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 10/5/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 10/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 10/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 10/7/2021 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 10/20/2021 | Partial Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/6/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 1/6/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 1/6/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/6/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 1/6/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/11/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 1/11/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/20/2022 | Conditional Approval | ANTHONY EGSON |
| Green Building Rough | 1/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 1/20/2022 | No Access for Inspection | ANTHONY EGSON |
| Insulation | 1/27/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/2/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 2/2/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/2/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/11/2022 | Approved | SHAVONNE ESPINOZA |
| Special/Order Compliance | 2/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 4/19/2022 | Approved | ANTHONY EGSON |
| Gas Test | 4/19/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/4/2022 | Partial Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 5/13/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 6/2/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | ANTHONY EGSON |
| Final | 6/6/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/6/2022 | Approved | ANTHONY EGSON |
| Green Building Final | 6/6/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 6/6/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 6/6/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 6/6/2022 | Approved | ANTHONY EGSON |
| Final | 6/13/2022 | No Access for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 6/13/2022 | No Access for Inspection | ANTHONY EGSON |
| Final | 6/15/2022 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | ANTHONY EGSON |
| Final | 6/27/2022 | Conditional Approval | ANTHONY EGSON |
| Service/Power Release | 6/27/2022 | Approved | ANTHONY EGSON |