3160-3162 W 11TH ST 90006
Certificate Information: 3160-3162 W 11TH ST 90006
- Application / Permit
- 20010-10000-02686
- Plan Check / Job No.
- B20LA14318
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-STORY DUPLEX (6684.0 SF) AND ATTACHED GARAGE (185.0 SF)
- Permit Issued
- Issued on 10/7/2021
- Issuing Office
- Current Status
- CofO Issued on 2/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 10/28/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 11/2/2020 | KESETE HAREGOT |
| Plan Check Approved | 9/9/2021 | SERGIO GUTIERREZ |
| Issued | 10/7/2021 | APPLICANT |
| Building Plans Picked Up | 10/8/2021 | APPLICANT |
| CofO in Progress | 2/5/2025 | WILLIAM SIERRA |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| CofO Issued | 2/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2020 | WALLIE JONG |
| Historic Resource Verification | Cleared | 11/30/2020 | MICAELA TORRES-GIL |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | WALLIE JONG |
| Redevelopment Project Area | Cleared | 12/1/2020 | GRACIELA ACOSTA |
| Sewer availability | Cleared | 12/2/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 2/17/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/17/2021 | JORGE MEJIA LEMUS |
| Stormwater Pollution Mitigatn | Cleared | 5/18/2021 | JORGE MEJIA LEMUS |
| Flood clearance | Cleared | 6/17/2021 | BRYAN GATHUKA |
| Frnt yard landscape/Water mgmt | Cleared | 8/17/2021 | KENTON TRINH |
| Roof/Waste drainage to street | Cleared | 8/23/2021 | WALLIE JONG |
| Highway dedication | Cleared | 8/25/2021 | WALLIE JONG |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 12/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 12/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| FLOOD-Elevation Certificate | 12/9/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 12/20/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| FLOOD-Elevation Certificate | 12/20/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/6/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/11/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2022 | Partial Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 3/8/2022 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 3/15/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 3/15/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 3/15/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/21/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| FLOOD-Proofing Certificate | 3/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 3/21/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 3/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 3/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 3/24/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 3/31/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 4/7/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 4/11/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| FLOOD-Proofing Certificate | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 7/31/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/21/2024 | Approved | ARTHUR NEGRETE |
| FLOOD-Proofing Certificate | 3/21/2024 | Approved | ARTHUR NEGRETE |
| Final | 3/21/2024 | Partial Approval | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 3/21/2024 | Approved | ARTHUR NEGRETE |
| Green Building Final | 3/21/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 3/21/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/21/2024 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 3/21/2024 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 8/20/2024 | Corrections Issued | ARTHUR NEGRETE |
| Final | 2/4/2025 | OK to Issue CofO | WILLIAM SIERRA |