9922 W COVELLO ST 91504
Certificate Information: 9922 W COVELLO ST 91504
- Application / Permit
- 20010-10000-02664
- Plan Check / Job No.
- B20LA14162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1 STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 6/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 9/10/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/22/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 1/28/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/5/2021 | SERGIO GUTIERREZ |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| CofO in Progress | 5/17/2026 | DAVID ANDERSON |
| Permit Finaled | 6/11/2026 | RUBEN SALAS |
| CofO Issued | 6/11/2026 | RUBEN SALAS |
| Permit Finaled | 6/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 10/20/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 10/20/2020 | SARAHI ORTEGA |
| Low Impact Development | Cleared | 1/12/2021 | ANDRES COVARRUBIAS |
| Stormwater Pollution Mitigatn | Cleared | 1/12/2021 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/17/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/24/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 3/29/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2023 | Approved | DAVID ANDERSON |
| Sewer | 11/7/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 11/7/2023 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 12/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 1/2/2024 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 1/26/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/12/2024 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 7/31/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/7/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/7/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 10/7/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 10/7/2024 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 10/7/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 10/7/2024 | Approved | DAVID ANDERSON |
| Insulation | 12/17/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Shower Pan | 12/17/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 2/7/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/7/2025 | Approved | DAVID ANDERSON |
| Underground Mechanical | 9/11/2025 | Partial Approval | DAVID ANDERSON |
| Final | 1/5/2026 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/5/2026 | Approved | DAVID ANDERSON |
| Green Building Final | 1/5/2026 | Approved | DAVID ANDERSON |
| MERV13>=Final | 1/5/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 1/5/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 1/5/2026 | Approved | DAVID ANDERSON |
| Final | 5/15/2026 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 5/15/2026 | Approved | DAVID ANDERSON |