1446-1448 W 37TH ST 90018

Certificate Information: 1446-1448 W 37TH ST 90018

Application / Permit
20010-10000-02607
Plan Check / Job No.
B20LA13817
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) DUPLEX W/ATT GARAGE
Permit Issued
Issued on 7/21/2021
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 LAMAR DAVIS
Corrections Issued 9/14/2020 LAMAR DAVIS
Quality Review Completed 9/25/2020 TU HUA
Building Plans Picked Up 9/29/2020 APPLICANT
Green Plans Picked Up 9/29/2020 APPLICANT
Plan Check Approved 7/2/2021 LAMAR DAVIS
Issued 7/21/2021 APPLICANT
CofO in Progress 11/3/2022 SABAS ALONSO
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/2/2020 JUAN ASHTON
Address approval Cleared 11/5/2020 JUAN ASHTON
Sewer availability Cleared 11/5/2020 JUAN ASHTON
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Low Impact Development Cleared 5/2/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/18/2021 THAN WIN

Contact Information

Contractor Universal Elite Construction Llc; Lic. No.: 1072818-B 34 WILLOWBROOK LN      POMONA, CA 91766
Engineer Jones,, Ryan Keith; Lic. No.: GE2852 1253 W MASLINE ST      COVINA, CA 91722
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/26/2021 Partial Approval SABAS ALONSO
Underground Mechanical 8/26/2021 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 8/31/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 8/31/2021 Approved SABAS ALONSO
METHANE-Barrier 8/31/2021 Approved SABAS ALONSO
METHANE-Subgrade 8/31/2021 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval SABAS ALONSO
Green Building Rough 9/22/2021 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 9/22/2021 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 9/22/2021 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/8/2021 Not Ready for Inspection SABAS ALONSO
Green Building Rough 11/8/2021 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 11/8/2021 Approved SABAS ALONSO
Verify Sprinkler Sign Off 11/8/2021 Not Ready for Inspection SABAS ALONSO
Wood Frame 11/8/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/3/2021 Partial Approval SABAS ALONSO
HVAC-Rough 12/3/2021 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 12/9/2021 Not Ready for Inspection SABAS ALONSO
Green Building Rough 12/9/2021 Not Ready for Inspection SABAS ALONSO
Rough-Elec/Plmb/HVAC 12/9/2021 Partial Inspection SABAS ALONSO
Verify Sprinkler Sign Off 12/9/2021 Corrections Issued SABAS ALONSO
Wood Frame 12/14/2021 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/15/2021 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/15/2021 Partial Approval SABAS ALONSO
Green Building Rough 12/15/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 12/15/2021 Partial Approval SABAS ALONSO
Verify Sprinkler Sign Off 12/15/2021 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/21/2021 Partial Approval SABAS ALONSO
HVAC-Rough 12/21/2021 Approved SABAS ALONSO
PLUMBING-Rough 12/21/2021 Not Ready for Inspection SABAS ALONSO
Wood Frame 12/21/2021 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 12/22/2021 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/27/2021 Approved SABAS ALONSO
Insulation 12/27/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 12/27/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 12/29/2021 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 1/3/2022 Conditional Approval SABAS ALONSO
Green Building Rough 1/3/2022 Approved SABAS ALONSO
Insulation 1/4/2022 Partial Approval HORACE FULTZ
Interior/Exterior Lathing 1/5/2022 Not Ready for Inspection HORACE FULTZ
Insulation 1/13/2022 Approved HORACE FULTZ
Sewer 1/13/2022 Approved HORACE FULTZ
Drywall Nailing 1/18/2022 Partial Approval SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Not Ready ANTHONY EGSON
Drywall Nailing 1/31/2022 Corrections Issued JOAQUIN GREENOUGH
Drywall Nailing 2/2/2022 Approved SABAS ALONSO
Service/Power Release 4/26/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 6/14/2022 Conditional Approval SABAS ALONSO
Final 6/14/2022 Corrections Issued SABAS ALONSO
Green Building Final 6/14/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 6/14/2022 Partial Approval SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 6/14/2022 Partial Approval SABAS ALONSO
Verify Sprinkler Sign Off 6/14/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 6/22/2022 Not Ready for Inspection SABAS ALONSO
Final 6/22/2022 Not Ready for Inspection SABAS ALONSO
Service/Power Release 6/22/2022 Approved SABAS ALONSO
Smoke Detectors 6/22/2022 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 6/22/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 7/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/2/2022 Corrections Issued SABAS ALONSO
HVAC-Final 8/2/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 8/2/2022 Approved SABAS ALONSO
ELECTRICAL-Final 8/17/2022 Approved SABAS ALONSO
HVAC-Final 8/17/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/17/2022 Approved SABAS ALONSO
Final 10/17/2022 Corrections Issued SABAS ALONSO
Green Building Final 10/17/2022 Approved SABAS ALONSO
Smoke Detectors 10/17/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 10/17/2022 Approved SABAS ALONSO
Final 11/2/2022 OK to Issue CofO SABAS ALONSO