763 W 4TH ST 90731
Certificate Information: 763 W 4TH ST 90731
- Application / Permit
- 20010-10000-02599
- Plan Check / Job No.
- B20LA13747
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 2ND STORY ADU AND CARPORT ADDITION TO EXISTING ONE STORY 2 CAR GARAGE (1200 SF MAX PER ORDINANCE, LAMC 12.22(A)33(c)-(d))
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | AUNG SOE |
| Corrections Issued | 8/28/2020 | AUNG SOE |
| Quality Review Completed | 9/16/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 9/17/2020 | APPLICANT |
| Applicant returned to address corrections | 1/12/2021 | AUNG SOE |
| Plan Check Approved | 1/13/2021 | AUNG SOE |
| Issued | 1/21/2021 | APPLICANT |
| CofO in Progress | 5/20/2022 | ANSON MAGLASANG |
| CofO Issued | 6/3/2022 | DEROLD HAUFF |
| Permit Finaled | 6/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | CHINH DINH |
| Sewer availability | Cleared | 10/7/2020 | CHINH DINH |
| Hydrant and Access approval | Cleared | 11/13/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/10/2020 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 1/13/2021 | AUNG SOE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2021 | Approved | JOHN KLARIN |
| Sewer | 3/12/2021 | Approved | JOHN KLARIN |
| Underground Mechanical | 3/12/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/4/2021 | Corrections Issued | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/19/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 5/19/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/23/2021 | Corrections Issued | ANSON MAGLASANG |
| Drywall Nailing | 11/23/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Final | 11/23/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 11/23/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 11/23/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Rough | 11/23/2021 | Corrections Issued | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 11/23/2021 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/14/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Drywall Nailing | 3/14/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 3/14/2022 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 3/14/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 3/14/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Not Ready | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/6/2022 | Approved | EUGENE CASSIDY |
| Final | 4/6/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/6/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 4/6/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Approved | EUGENE CASSIDY |
| Final | 4/13/2022 | Conditional Approval | JOHN KLARIN |
| Green Building Final | 4/13/2022 | Approved | JOHN KLARIN |
| Final | 4/25/2022 | OK to Issue CofO | JOHN KLARIN |