1351-1353 W 58TH ST 90037
Certificate Information: 1351-1353 W 58TH ST 90037
- Application / Permit
- 20010-10000-02574
- Plan Check / Job No.
- B20LA13584
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE COMPLY WITH DEPARTMENT ORDER effective date 01/10/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | CARLOS MONTES |
| Corrections Issued | 8/24/2020 | CARLOS MONTES |
| Quality Review Completed | 10/1/2020 | WING SUEN |
| Applicant returned to address corrections | 2/2/2021 | CARLOS MONTES |
| Plan Check Approved | 2/8/2021 | CARLOS MONTES |
| Building Plans Picked Up | 2/10/2021 | APPLICANT |
| Issued | 2/19/2021 | APPLICANT |
| CofO in Progress | 8/13/2021 | HORACE FULTZ |
| CofO Issued | 8/14/2021 | DEROLD HAUFF |
| Permit Finaled | 8/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2020 | CECILIO NAVARRO |
| Permit | Cleared | 10/15/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/16/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 1/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 1/13/2021 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 1/21/2021 | TERRI OSBORNE |
| Trees in Parkway | Cleared | 1/25/2021 | JOHN KIM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/19/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Partial Approval | ROBERT MCDOWELL |
| Underground Mechanical | 3/26/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Partial Approval | ROBERT MCDOWELL |
| Insulation | 3/30/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/10/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/10/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/10/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 5/10/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/10/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/10/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 5/11/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/28/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/28/2021 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 7/27/2021 | Approved | SABAS ALONSO |
| Final | 7/27/2021 | Partial Approval | SABAS ALONSO |
| Green Building Final | 7/27/2021 | Approved | SABAS ALONSO |
| HVAC-Final | 7/27/2021 | Approved | SABAS ALONSO |
| PLUMBING-Final | 7/27/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 7/27/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 7/27/2021 | Approved | SABAS ALONSO |
| Final | 8/12/2021 | OK to Issue CofO | SABAS ALONSO |