9107-9109 S ORCHARD AVE 90044

Certificate Information: 9107-9109 S ORCHARD AVE 90044

Application / Permit
20010-10000-02564
Plan Check / Job No.
B20LA13550
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE "COMPLY WITH DEPARTMENT ORDER effective date 05/11/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 1/19/2021
Issuing Office
Current Status
CofO Issued on 6/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 MAHNAZ NOURHASHEMI
Corrections Issued 8/25/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 8/28/2020 TIEN JEN WANG
Applicant returned to address corrections 11/12/2020 MAHNAZ NOURHASHEMI
Plan Check Approved 12/10/2020 MAHNAZ NOURHASHEMI
Issued 1/19/2021 APPLICANT
Building Plans Picked Up 1/21/2021 APPLICANT
CofO in Progress 6/25/2021 ALEJANDRO DE ARTOLA
Permit Finaled 6/30/2021 DEROLD HAUFF
CofO Issued 6/30/2021 DEROLD HAUFF
Permit Finaled 6/30/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/21/2020 RENZ SORIANO
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 10/5/2020 RENZ SORIANO
Low Impact Development Cleared 10/26/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 11/5/2020 CELINA MORENO
Sewer availability Cleared 11/13/2020 RENZ SORIANO
Permit Cleared 11/16/2020 RENZ SORIANO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/11/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 2/23/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 2/24/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 3/16/2021 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 3/23/2021 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/23/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 3/23/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/23/2021 Approved ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 3/23/2021 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 3/23/2021 Approved ALEJANDRO DE ARTOLA
Insulation 3/24/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/24/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/8/2021 Approved SABAS ALONSO
Drywall Nailing 4/8/2021 Approved SABAS ALONSO
Green Building Rough 4/8/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 4/8/2021 Approved SABAS ALONSO
ELECTRICAL-Final 6/4/2021 Approved ALEJANDRO DE ARTOLA
Final 6/4/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 6/4/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 6/4/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/4/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/4/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/4/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 6/4/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 6/4/2021 Approved ALEJANDRO DE ARTOLA
Final 6/25/2021 OK to Issue CofO ALEJANDRO DE ARTOLA