671-673 W 62ND ST 90044
Certificate Information: 671-673 W 62ND ST 90044
- Application / Permit
- 20010-10000-02561
- Plan Check / Job No.
- B20LA13539
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 88'X25' 2-STORY DUPLEX WITH FRONT 1-CAR ATTACHED GARAGE AND BACK 2-CAR ATTACHED GARAGE.
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- CofO Issued on 6/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 10/15/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 10/22/2020 | KESETE HAREGOT |
| Plan Check Approved | 12/18/2020 | CHUNG-WEN CHUANG |
| Issued | 1/13/2021 | APPLICANT |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| CofO in Progress | 6/24/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 6/30/2021 | DEROLD HAUFF |
| CofO Issued | 6/30/2021 | DEROLD HAUFF |
| Permit Finaled | 6/30/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/21/2020 | KURT CORRAL |
| Address approval | Cleared | 10/23/2020 | ELAINE LEI |
| Permit | Cleared | 10/23/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2020 | ELAINE LEI |
| Sewer availability | Cleared | 10/26/2020 | ELAINE LEI |
| Low Impact Development | Cleared | 11/18/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/19/2020 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2021 | Approved | DAVID FEILER |
| Deputy Reinf. Concrete | 2/3/2021 | No Access for Inspection | ELMER BLAND |
| Underground Mechanical | 2/10/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 2/11/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 2/11/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 2/12/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2021 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 3/16/2021 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/22/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 3/22/2021 | Approved | DAVID FEILER |
| Green Building Rough | 3/22/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 3/22/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 3/22/2021 | Not Ready for Inspection | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 3/22/2021 | Partial Approval | DAVID FEILER |
| Verify Sprinkler Sign Off | 3/22/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 3/23/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 3/23/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/23/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 3/26/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 3/26/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 3/26/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 3/26/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Special/Order Compliance | 4/8/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 6/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/10/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/10/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/11/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/23/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |