11604 W VANOWEN ST 1-49 91605
Certificate Information: 11604 W VANOWEN ST 1-49 91605
- Application / Permit
- 20010-10000-02527
- Plan Check / Job No.
- B20LA13289
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 3-story factory-built housing, modular apartment building with 49 dwelling units (100% affordable) utilizing TOC Tier 2 incentives.
- Permit Issued
- Issued on 1/27/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 1/26/2021 | RODOLFO ARIAS |
| Issued | 1/27/2021 | APPLICANT |
| TCO Issued (Expire Date: 02-09-2025) | 8/13/2024 | JEFFREY DURAN |
| TCO Issued (Expire Date: 08-02-2025) | 2/3/2025 | JEFFREY DURAN |
| TCO Issued (Expire Date: 01-25-2026) | 7/29/2025 | JEFFREY DURAN |
| Permit Finaled | 12/17/2025 | RICKEY JACKSON |
| CofO Issued | 12/17/2025 | RICKEY JACKSON |
| Permit Finaled | 12/17/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| ZA Case | Cleared | 9/30/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/30/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/30/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/30/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/30/2020 | MAXFIELD VERMY |
| Address approval | Cleared | 10/30/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2020 | ADRIAN CASTRO |
| Permit | Cleared | 11/5/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/5/2020 | ADRIAN CASTRO |
| Highway dedication | Cleared | 11/6/2020 | ABDULLAH SADOZAI |
| Hydrant and Access approval | Cleared | 11/16/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 12/3/2020 | RODOLFO ARIAS |
| Construction near power lines | Cleared | 12/7/2020 | RIDWAN HARDY |
| Density Bonus 12.22.A.31 | Cleared | 12/9/2020 | RICHARD TRUONG |
| Building over 36-ft | Cleared | 12/10/2020 | CALOSHA APPROVED |
| Trees in Parkway | Cleared | 12/16/2020 | JOHN KIM |
| Excavation more than 5-ft deep | Cleared | 1/11/2021 | CALOSHA APPROVED |
| Fire Marshall Fire Life Safety | Cleared | 1/12/2021 | MENOA AGHAJANI |
| Low Impact Development | Cleared | 1/14/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/19/2021 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 1/20/2021 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 1/21/2021 | RODOLFO ARIAS |
| Public Housing | Cleared | 1/21/2021 | RUBEN REYES |
| Frnt yard landscape/Water mgmt | Cleared | 1/22/2021 | MAXFIELD VERMY |
| Opn space landscape/Water mgmt | Cleared | 1/22/2021 | MAXFIELD VERMY |
Contact Information
| Architect | Bohn,, Michael Peter; Lic. No.: C21695 | 287 GRANADA AVENUE LONG BEACH, CA 90803 |
| Contractor | Gundry Partners Lp; Lic. No.: 1006248-B | 3750 LONG BEACH BLVD, STE 200 LONG BEACH, CA 90807 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Larocca,, Francis Joseph; Lic. No.: C75121 | 1821 PACIFIC COAST HWY 38 HERMOSA BEACH, CA 90254 |
| Engineer | Tavares,, Ralph Monteiro; Lic. No.: C60484 | 11590 WEST BERNARDO COURT STE 100 SAN DIEGO, CA 92128 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 10/28/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 11/2/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 11/30/2021 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 12/1/2021 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 12/2/2021 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 12/6/2021 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 12/8/2021 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 12/15/2021 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/21/2021 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 1/21/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 1/28/2022 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 1/28/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 2/2/2022 | Approved | JOHN KITCKO |
| Structural Steel Frame | 2/8/2022 | Partial Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 2/14/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 2/17/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 2/18/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 2/22/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 2/23/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 2/24/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 3/3/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/4/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/10/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 3/11/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 4/7/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/11/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/12/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/15/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/20/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/22/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/26/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 4/27/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/29/2022 | No Access for Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 5/3/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 5/4/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/5/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/6/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/10/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 5/11/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/12/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/13/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/17/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/18/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 5/19/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/20/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/24/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 5/25/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/26/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/27/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/31/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/1/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 6/2/2022 | Approved | KENNETH ROBERTS |
| Deputy Steel/Welding | 6/3/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 6/6/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/7/2022 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 6/7/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/8/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/9/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/10/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/13/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/14/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 6/16/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 6/17/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/24/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/28/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/29/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 6/30/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/1/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/5/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/6/2022 | Approved | JOHN KITCKO |
| Deputy Drilled-In Anchors | 7/7/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/7/2022 | Approved | JOHN KITCKO |
| Deputy Drilled-In Anchors | 7/8/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/8/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/12/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/13/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/14/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/15/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/19/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 7/20/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/20/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/21/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/22/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/25/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/26/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/27/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/28/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/29/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/2/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/3/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 8/4/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 8/5/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/9/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/10/2022 | Approved | JOHN KITCKO |
| Green Building Rough | 8/10/2022 | Partial Approval | JOHN KITCKO |
| Verify Sprinkler Sign Off | 8/10/2022 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 8/10/2022 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 8/11/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 8/12/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 8/16/2022 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 8/17/2022 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 8/17/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/18/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 8/19/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 8/23/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 8/24/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 8/25/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/26/2022 | Approved | JOHN KITCKO |
| Drywall Nailing | 8/26/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/30/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 8/31/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/1/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 9/2/2022 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 9/2/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 9/7/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/8/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/9/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/13/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/14/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/15/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/16/2022 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 9/16/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/20/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/21/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/22/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/23/2022 | Approved | JOHN KITCKO |
| Deputy Drilled-In Anchors | 9/27/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/27/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 9/28/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/29/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 9/30/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/3/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/4/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/5/2022 | Approved | JOHN KITCKO |
| Deputy Drilled-In Anchors | 10/6/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/6/2022 | Approved | JOHN KITCKO |
| Green Building Rough | 10/6/2022 | Not Ready for Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 10/6/2022 | Approved | JOHN KITCKO |
| Wood Frame | 10/6/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/7/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 10/11/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 10/12/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/12/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/13/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/14/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/17/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/18/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/19/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/20/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/21/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/25/2022 | Approved | JOHN KITCKO |
| Drywall Nailing | 10/25/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/26/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/27/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/28/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/31/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 11/1/2022 | Approved | JOHN KITCKO |
| Structural Steel Frame | 11/1/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/2/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/3/2022 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 11/3/2022 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/4/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/7/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 11/8/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 11/9/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 11/10/2022 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 11/14/2022 | Approved | JOHN KITCKO |
| Green Building Rough | 11/16/2022 | Approved | JOHN KITCKO |
| Wood Frame | 11/16/2022 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 11/28/2022 | No Access for Inspection | JOHN KITCKO |
| Structural Steel Frame | 11/28/2022 | Partial Inspection | ROBERT DAVIS |
| Piling/Pier/Caisson | 12/22/2022 | Partial Inspection | JOHN KITCKO |
| Wood Frame | 12/22/2022 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 1/31/2023 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Inspection | JEFFREY FULTON |
| Deputy Steel/Welding | 2/14/2023 | Approved | JOHN KITCKO |
| Special/Order Compliance | 2/14/2023 | Approved | BRIAN KELLY |
| Structural Steel Frame | 2/22/2023 | Partial Approval | DAVID BURKHEAD |
| Structural Steel Frame | 2/23/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 3/16/2023 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 4/10/2023 | Partial Approval | JOHN KITCKO |
| Wood Frame | 4/19/2023 | Partial Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 4/26/2023 | Partial Approval | JOHN KITCKO |
| Special/Order Compliance | 4/26/2023 | Partial Approval | STEVEN LEVITT |
| Deputy Steel/Welding | 7/3/2023 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 7/6/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 8/11/2023 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 9/18/2023 | Partial Approval | JOHN KITCKO |
| Wood Frame | 9/26/2023 | Partial Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 10/17/2023 | Partial Approval | JOHN KITCKO |
| Wood Frame | 10/24/2023 | Partial Approval | JOHN KITCKO |
| Wood Frame | 10/26/2023 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 10/31/2023 | Partial Approval | ROBERT DAVIS |
| Insulation | 11/6/2023 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 11/17/2023 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 11/29/2023 | Partial Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 12/5/2023 | Approved | JOHN KITCKO |
| Insulation | 12/5/2023 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 12/7/2023 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 12/12/2023 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 12/18/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/19/2023 | Conditional Approval | JOHN KITCKO |
| Drywall Nailing | 12/29/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 1/3/2024 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 1/12/2024 | Partial Inspection | JEFFREY FULTON |
| Insulation | 1/12/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 1/16/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 1/30/2024 | Partial Approval | JOHN KITCKO |
| Deputy Drilled-In Anchors | 2/26/2024 | Approved | JOHN KITCKO |
| Deputy Drilled-In Anchors | 2/27/2024 | Approved | JOHN KITCKO |
| Deputy Drilled-In Anchors | 5/9/2024 | Conditional Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 5/9/2024 | Partial Approval | JOHN KITCKO |
| Pre-Inspection | 6/18/2024 | Partial Approval | JOHN KITCKO |
| Light Gage Steel Frame | 6/21/2024 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 7/17/2024 | Partial Approval | ROBERT DAVIS |
| Final | 7/25/2024 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/25/2024 | Approved | JOHN KITCKO |
| Green Building Final | 7/25/2024 | Not Ready for Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 7/25/2024 | Approved | JOHN KITCKO |
| Wood Frame | 7/25/2024 | Approved | JOHN KITCKO |
| Final | 7/30/2024 | OK for TCO | GREGORY POMISH |
| Green Building Final | 7/30/2024 | Approved | GREGORY POMISH |
| Final | 8/8/2024 | Partial Inspection | GREGORY POMISH |
| Special/Order Compliance | 1/14/2025 | Partial Inspection | JOHN KITCKO |
| Special/Order Compliance | 7/8/2025 | Partial Inspection | JOHN KITCKO |