137 E AVENUE 36 90031
Certificate Information: 137 E AVENUE 36 90031
- Application / Permit
- 20010-10000-02516
- Plan Check / Job No.
- B20LA13222
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SECOND UNIT
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Metro
- Current Status
- Issued on 5/31/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 9/3/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/14/2020 | PRANITA SHAH |
| Building Plans Picked Up | 9/30/2020 | APPLICANT |
| Applicant returned to address corrections | 3/1/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/10/2022 | ARSALAN SHABESTARI |
| Issued | 5/31/2022 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/22/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/1/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 7/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/15/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/12/2021 | ROBERT DUFF |
| Grading Pre-Inspection | Cleared | 9/15/2021 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 2/9/2022 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Advance Remodeling And Property Services; Lic. No.: 1010131-B | 1313 SOUTH POPLAR STREET SANTA ANA, CA 92704 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/5/2022 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 10/25/2022 | Partial Inspection | AMY COLIN |
| Footing/Foundation/Slab | 11/16/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 1/12/2023 | Partial Inspection | AMY COLIN |
| Green Building Rough | 1/12/2023 | Partial Inspection | AMY COLIN |
| MERV13>=Rough | 1/12/2023 | Partial Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 1/12/2023 | Partial Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 1/13/2023 | Partial Inspection | AMY COLIN |
| Green Building Rough | 1/13/2023 | Partial Inspection | AMY COLIN |
| MERV13>=Rough | 1/13/2023 | Approved | AMY COLIN |
| Special/Order Compliance | 1/13/2023 | Partial Inspection | RUBEN SALAS |
| Verify Sprinkler Sign Off | 1/13/2023 | Not Ready for Inspection | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 1/17/2023 | Corrections Issued | AMY COLIN |
| Structural Steel Frame | 2/13/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/4/2023 | No Access for Inspection | AMY COLIN |
| Green Building Rough | 10/4/2023 | No Access for Inspection | AMY COLIN |
| Structural Steel Frame | 10/4/2023 | No Access for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 10/4/2023 | No Access for Inspection | AMY COLIN |
| Light Gage Steel Frame | 10/10/2023 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 10/10/2023 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 10/26/2023 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 10/26/2023 | Not Ready for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 10/26/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 11/18/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 11/18/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 11/18/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Structural Steel Frame | 7/31/2025 | Corrections Issued | LILIANA PORTILLO |
| Pre-Inspection | 11/14/2025 | Partial Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 11/14/2025 | Approved | LILIANA PORTILLO |