241 W 49TH ST 90037
Certificate Information: 241 W 49TH ST 90037
- Application / Permit
- 20010-10000-02504
- Plan Check / Job No.
- B20LA13173
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER ORDINANCE 186,481
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- CofO Issued on 10/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | SINA KHOSRAVI |
| Corrections Issued | 7/30/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/3/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 2/1/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 2/26/2021 | LUKE GONZALES |
| Plan Check Approved | 3/19/2021 | LUKE GONZALES |
| Issued | 4/15/2021 | APPLICANT |
| Building Plans Picked Up | 4/19/2021 | APPLICANT |
| CofO in Progress | 10/8/2021 | JOAQUIN GREENOUGH |
| Permit Finaled | 10/13/2021 | DEROLD HAUFF |
| Permit Finaled | 10/13/2021 | DEROLD HAUFF |
| CofO Issued | 10/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/18/2020 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | CELINA MORENO |
| Address approval | Cleared | 10/8/2020 | CELINA MORENO |
| Sewer availability | Cleared | 10/13/2020 | CELINA MORENO |
| Construction near power lines | Cleared | 12/6/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/11/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/15/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2021 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 5/6/2021 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/18/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/10/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/22/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/22/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 6/22/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 6/22/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/22/2021 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 6/22/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/1/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/1/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 7/1/2021 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 7/1/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 7/7/2021 | Approved | HORACE FULTZ |
| Drywall Nailing | 7/16/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/16/2021 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 8/16/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Pre-Inspection | 8/17/2021 | Partial Inspection | ALAN MORELOS |
| Shower Pan | 8/17/2021 | Approved | JOAQUIN GREENOUGH |
| Sewer | 9/13/2021 | Approved | WILLIAM WREN |
| Underground Mechanical | 9/20/2021 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 9/29/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 9/29/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 9/29/2021 | Approved | JOAQUIN GREENOUGH |
| MERV13>=Final | 9/29/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/29/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 9/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/29/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 10/7/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 10/7/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 10/7/2021 | Approved | JOAQUIN GREENOUGH |