11705 N WOODLEY AVE 91344
Certificate Information: 11705 N WOODLEY AVE 91344
- Application / Permit
- 20010-10000-02489
- Plan Check / Job No.
- B20LA13057
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 26'X 26' 2 STORY ADU
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 7/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 10/9/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 10/19/2020 | WING SUEN |
| Applicant returned to address corrections | 11/10/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/5/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/6/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/18/2021 | CRYSTEL MAALOUF |
| Issued | 4/20/2022 | APPLICANT |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| CofO in Progress | 6/2/2026 | CHRISTOPHER ROJAS |
| CofO Issued | 7/7/2026 | RUBEN SALAS |
| Permit Finaled | 7/7/2026 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 11/9/2020 | TERRI OSBORNE |
| Address approval | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 3/8/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/2/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/2/2021 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 10/18/2021 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 10/18/2021 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 12/22/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/10/2024 | Partial Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 7/25/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 1/29/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/5/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2025 | No Access for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 2/5/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/9/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 4/21/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 4/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 4/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 4/30/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/5/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 6/11/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 6/11/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 7/16/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 7/16/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 3/20/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 3/20/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 3/20/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 3/20/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/20/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 3/20/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/20/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 4/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 4/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/19/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 5/19/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 6/2/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 6/2/2026 | Approved | CHRISTOPHER ROJAS |