549 W 15TH ST 90731
Certificate Information: 549 W 15TH ST 90731
- Application / Permit
- 20010-10000-02478
- Plan Check / Job No.
- B20LA12990
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED ACCESSORY DWELLING UNIT 1 -STORY PER GCS 65852.2(e)(1)(D)
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 10/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | CARLOS MONTES |
| Corrections Issued | 8/18/2020 | CARLOS MONTES |
| Quality Review Completed | 9/22/2020 | WING SUEN |
| Plan Check Approved | 3/23/2022 | CARLOS MONTES |
| Issued | 4/20/2022 | APPLICANT |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| CofO in Progress | 10/14/2022 | ANSON MAGLASANG |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
| CofO Issued | 10/14/2022 | DEROLD HAUFF |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | CHINH DINH |
| Sewer availability | Cleared | 11/18/2020 | CHINH DINH |
| Hydrant and Access approval | Cleared | 1/30/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 11/3/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/12/2022 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 5/18/2022 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 6/2/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/2/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/8/2022 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 6/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/23/2022 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 6/23/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 6/23/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 6/30/2022 | Corrections Issued | ANSON MAGLASANG |
| Interior/Exterior Lathing | 7/5/2022 | Approved | JOHN KLARIN |
| Insulation | 7/7/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 7/12/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 7/12/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | ANSON MAGLASANG |
| Underground Mechanical | 9/1/2022 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 9/27/2022 | Approved | ANSON MAGLASANG |
| Final | 9/27/2022 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 9/27/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 9/27/2022 | Approved | ANSON MAGLASANG |
| Final | 10/5/2022 | OK to Issue CofO | ANSON MAGLASANG |
| Service/Power Release | 10/5/2022 | Not Required | ANSON MAGLASANG |