831-831 1/2 W 95TH ST 90044
Certificate Information: 831-831 1/2 W 95TH ST 90044
- Application / Permit
- 20010-10000-02421
- Plan Check / Job No.
- B20LA12641
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 39.5' X 36' 2-STORY DUPLEX W/ATTACHED GARAGE
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Current Status
- CofO Issued on 6/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 8/19/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 9/30/2020 | WING SUEN |
| Plan Check Approved | 5/14/2021 | CRYSTEL MAALOUF |
| Issued | 6/9/2021 | APPLICANT |
| Building Plans Picked Up | 6/14/2021 | APPLICANT |
| CofO in Progress | 6/26/2023 | JAMES CHAVEZ |
| Permit Finaled | 6/26/2023 | ANSON MAGLASANG |
| CofO Issued | 6/26/2023 | ANSON MAGLASANG |
| Permit Finaled | 6/26/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 2/24/2021 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2021 | JEANIE LAM |
| Sewer availability | Cleared | 2/26/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 5/2/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | JEANIE LAM |
| Green Code | Cleared | 5/14/2021 | CRYSTEL MAALOUF |
Contact Information
| Contractor | New World Construction; Lic. No.: 864461-B | 838 E 93RD STREET LOS ANGELES, CA 90002 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/28/2021 | Partial Approval | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 8/26/2021 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/27/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 8/27/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/30/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/30/2021 | Conditional Approval | EUGENE CASSIDY |
| Green Building Rough | 8/30/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/30/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 8/30/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/2/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 9/2/2021 | Approved | JOHN KLARIN |
| Insulation | 9/2/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/2/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/7/2021 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 9/7/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/13/2021 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 11/7/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 4/21/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 4/21/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 4/21/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 4/21/2023 | Corrections Issued | JAMES CHAVEZ |
| HVAC-Final | 4/21/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Final | 4/21/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 4/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 4/21/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 5/1/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 5/1/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Final | 5/1/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 5/1/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Verify Rec and Parks Fee Memo | 5/1/2023 | Approved | JAMES CHAVEZ |
| Final | 6/12/2023 | Corrections Issued | JAMES CHAVEZ |
| Service/Power Release | 6/12/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 6/20/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Service/Power Release | 6/20/2023 | Approved | JAMES CHAVEZ |