4245 3/4 S OLIVE ST 90037

Certificate Information: 4245 3/4 S OLIVE ST 90037

Application / Permit
20010-10000-02412
Plan Check / Job No.
B20LA12608
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED, TWO-STORY ACCESSORY DWELLING UNIT PROPOSED. EXISTING GARAGE STRUCTURE TO BE REMOVED.
Permit Issued
Issued on 6/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 DANIEL YIP
Corrections Issued 8/14/2020 DANIEL YIP
Quality Review Completed 9/1/2020 HERNAN ARREOLA
Building Plans Picked Up 9/8/2020 APPLICANT
Applicant returned to address corrections 4/7/2021 DANIEL YIP
Plan Check Approved 6/6/2022 DANIEL YIP
Issued 6/8/2022 APPLICANT
CofO in Progress 12/31/2024 ALEJANDRO DE ARTOLA
Permit Finaled 1/9/2025 DEROLD HAUFF
Permit Finaled 1/9/2025 DEROLD HAUFF
CofO Issued 1/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/15/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/23/2021 CELINA MORENO
Sewer availability Cleared 9/23/2021 CELINA MORENO
Low Impact Development Cleared 5/18/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 5/26/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Noe,, Juan Gabriel; Lic. No.: C72822 390 E SAN YSIDRO BLVD PMB 26      SAN YSIDRO, CA 92173

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/21/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 6/13/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 6/26/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 7/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 7/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 7/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 1/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 1/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/5/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/8/2024 Partial Approval ENRIQUE MIRELES
Green Building Rough 1/8/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/11/2024 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/25/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/12/2024 Approved ALEJANDRO DE ARTOLA
Sewer 2/12/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/15/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/28/2024 Approved ALEJANDRO DE ARTOLA
Final 12/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/9/2024 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 12/9/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/10/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/10/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/10/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 12/10/2024 Approved ALEJANDRO DE ARTOLA
Final 12/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 12/20/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/20/2024 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 12/20/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/20/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 12/20/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/30/2024 Approved ALEJANDRO DE ARTOLA
Final 12/30/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved ALEJANDRO DE ARTOLA