6220 W SELMA AVE 90028

Certificate Information: 6220 W SELMA AVE 90028

Application / Permit
20010-10000-02400
Plan Check / Job No.
B20LA12514
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 8-story , 276-unit, including 13 very low income units and 7 voluntary moderate income units, mixed-use building with 5 levels of Type IIIA residential over 2 levels of Type IA residential over ground level Type IA retail over 4-levels of subterranean parking.
Permit Issued
Issued on 7/22/2021
Issuing Office
Metro
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 EUGENE BARBEAU
Disabled Access Plans Picked Up 8/7/2020 APPLICANT
Corrections Issued 8/25/2020 EUGENE BARBEAU
Quality Review Completed 8/31/2020 ALLEN MANALANSAN
Building Plans Picked Up 9/1/2020 APPLICANT
Applicant returned to address corrections 9/24/2020 EUGENE BARBEAU
Applicant returned to address corrections 11/13/2020 EUGENE BARBEAU
Green Plans Picked Up 3/3/2021 APPLICANT
Plan Check Approved 6/11/2021 EUGENE BARBEAU
Issued 7/22/2021 APPLICANT
TCO Issued (Expire Date: 06-01-2025) 12/3/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 12-09-2025) 6/12/2025 ADAM BURGESS
TCO Issued (Expire Date: 06-03-2026) 12/5/2025 ADAM BURGESS
CofO in Progress 4/7/2026 DAVID BURKHEAD
Permit Finaled 4/7/2026 ERNESTO CORRAL
CofO Issued 4/7/2026 ERNESTO CORRAL
Permit Finaled 4/7/2026 ERNESTO CORRAL

Permit Application Clearance Information

Metro Rail approval Cleared 8/31/2020 EUGENE BARBEAU
Highway dedication Cleared 9/1/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/2/2020 RENZ SORIANO
Address approval Cleared 9/3/2020 RENZ SORIANO
Hydrant and Access approval Cleared 10/13/2020 MATTHEW CRAIG
Fire Marshall Fire Life Safety Cleared 11/5/2020 VIDAL GARCIA
Encroachment in public way Cleared 11/23/2020 ELAINE LEI
Food Service Establishment Cleared 12/15/2020 JASH PATEL
DAS Clearance Cleared 1/11/2021 SHINE LIN
Low Impact Development Cleared 2/10/2021 ORVAL HERNANDEZ-MARCI
Green Code Cleared 3/3/2021 AARON COSTA
Trees in Parkway Cleared 3/3/2021 JOHN KIM
Work Adjacent to Public Way Cleared 3/8/2021 BOK GOH
Driveway location Cleared 3/12/2021 EDUARDO HERMOSO
DCP conditions approval Cleared 3/24/2021 DORIS KWOK
Density Bonus 12.22.A.25 Cleared 3/24/2021 DORIS KWOK
Bicycle Parking Cleared 4/13/2021 ELAINE LEI
Permit Cleared 4/13/2021 ELAINE LEI
Roof/Waste drainage to street Cleared 4/13/2021 ELAINE LEI
Sewer availability Cleared 4/20/2021 ELAINE LEI
"Q" conditions Cleared 5/12/2021 JASON MCCREA
CPC Cleared 5/12/2021 JASON MCCREA
Miscellaneous Cleared 5/12/2021 JASON MCCREA
Opn space landscape/Water mgmt Cleared 5/12/2021 JASON MCCREA
Site Plan review Cleared 5/12/2021 JASON MCCREA
Tract Map conditions Cleared 5/12/2021 JASON MCCREA
ZA Case Cleared 5/12/2021 JASON MCCREA
ZA Case Cleared 5/12/2021 JASON MCCREA
ZI Cleared 5/12/2021 JASON MCCREA
Excavation more than 5-ft deep Cleared 5/14/2021 CALOSHA APPROVED
Redevelopment Project Area Cleared 5/17/2021 GISELLE CORELLA
Historic Resource Verification Cleared 5/18/2021 MICAELA TORRES-GIL
Building over 36-ft Cleared 6/11/2021 CALOSHA APPROVED

Contact Information

Architect Dixon,, James Troy; Lic. No.: C16900 4418 MARIOTA AVE.      TOLUCA LAKE, CA 91602
Contractor M C R T California Construction Lp; Lic. No.: 957117-B 949 SOUTH COAST DRIVE #400      COSTA MESA, CA 92626
Engineer Blunda,, Abraham Matthew; Lic. No.: S6536 1845 W ORANGEWOOD AVE 200      ORANGE, CA 92868

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/27/2021 Approved DAVID BURKHEAD
Pre-Inspection 9/29/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 10/13/2021 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/13/2021 Not Ready for Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 10/14/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 10/14/2021 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 10/15/2021 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/19/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/21/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/22/2021 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/27/2021 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 10/28/2021 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/28/2021 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/29/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 10/29/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/1/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 11/1/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/2/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 11/2/2021 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/2/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 11/3/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 11/3/2021 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/3/2021 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/4/2021 Approved DAVID BURKHEAD
Deputy Shotcrete 11/4/2021 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/4/2021 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/5/2021 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/8/2021 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 11/9/2021 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/10/2021 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 11/12/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/12/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 11/12/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 11/12/2021 Conditional Approval DAVID BURKHEAD
Green Building Rough 11/12/2021 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 11/12/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 11/12/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 11/15/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/15/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 11/15/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 11/15/2021 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 11/16/2021 Approved DAVID BURKHEAD
Deputy Reinf. Concrete 11/16/2021 Approved DAVID BURKHEAD
Deputy Reinf. Masonry 11/16/2021 Approved DAVID BURKHEAD
Deputy Shotcrete 11/16/2021 Approved DAVID BURKHEAD
Green Building Rough 11/16/2021 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 11/16/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 11/16/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 11/17/2021 Approved DAVID BURKHEAD
Deputy Reinf. Concrete 11/17/2021 Approved DAVID BURKHEAD
Deputy Reinf. Masonry 11/17/2021 Approved DAVID BURKHEAD
Deputy Shotcrete 11/17/2021 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/17/2021 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 11/18/2021 Approved DAVID BURKHEAD
Deputy Pre-Stress Concrete 11/18/2021 Approved DAVID BURKHEAD
Deputy Reinf. Concrete 11/18/2021 Approved DAVID BURKHEAD
Deputy Reinf. Masonry 11/18/2021 Approved DAVID BURKHEAD
Deputy Shotcrete 11/18/2021 Approved DAVID BURKHEAD
Reinforced Masonry Frame 11/18/2021 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 11/19/2021 Approved DAVID BURKHEAD
Deputy Pre-Stress Concrete 11/19/2021 Approved DAVID BURKHEAD
Deputy Reinf. Concrete 11/19/2021 Approved DAVID BURKHEAD
Deputy Reinf. Masonry 11/19/2021 Approved DAVID BURKHEAD
Deputy Shotcrete 11/19/2021 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/19/2021 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 11/22/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Pre-Stress Concrete 11/22/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/22/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 11/22/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 11/22/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Drilled-In Anchors 11/23/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Pre-Stress Concrete 11/23/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/23/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 11/23/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 11/23/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Drilled-In Anchors 11/24/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Pre-Stress Concrete 11/24/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/24/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Masonry 11/24/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Shotcrete 11/24/2021 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/30/2021 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 12/1/2021 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 12/3/2021 Approved DAVID BURKHEAD
Footing/Foundation/Slab 12/3/2021 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 12/9/2021 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 12/10/2021 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 12/13/2021 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 1/6/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 1/6/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 1/6/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 1/7/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 1/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 1/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/12/2022 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 1/12/2022 Partial Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 1/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/13/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 1/13/2022 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 1/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/14/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 1/14/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 1/14/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 1/14/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 1/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/18/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/18/2022 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 1/18/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 1/19/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/19/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/19/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/19/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/19/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/19/2022 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 1/20/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/20/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/20/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/20/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/20/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 1/20/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 1/20/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 1/20/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 1/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/21/2022 Conditional Approval DAVID BURKHEAD
Reinforced Masonry Frame 1/21/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 1/24/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/24/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/24/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/24/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/24/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/24/2022 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 1/25/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 1/25/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/25/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 1/25/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/25/2022 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 1/26/2022 Corrections Issued DAVID BURKHEAD
Piling/Pier/Caisson 1/27/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 1/28/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 1/28/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 1/28/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 1/31/2022 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 1/31/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 2/1/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/1/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 2/2/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 2/2/2022 Partial Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/2/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 2/3/2022 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 2/16/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 2/16/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 2/16/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/16/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 3/1/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/1/2022 Partial Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/1/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 3/2/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/2/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 3/2/2022 Not Ready for Inspection DAVID BURKHEAD
Piling/Pier/Caisson 3/4/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 3/7/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/7/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 3/7/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 3/8/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 3/8/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 3/9/2022 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 3/10/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 3/10/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/10/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 3/10/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 3/10/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 3/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 3/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 3/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 3/11/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 3/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 3/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 3/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 3/14/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 3/14/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/14/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 3/14/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 3/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 3/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 3/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 3/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 3/16/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 3/16/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/16/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 3/16/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 3/16/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/17/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/18/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 3/18/2022 Partial Approval DAVID BURKHEAD
Piling/Pier/Caisson 3/21/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 3/22/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/22/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/22/2022 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 3/24/2022 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 3/25/2022 Partial Approval DANIEL MC AULIFFE
Deputy Drilled-In Anchors 3/30/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 3/30/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/30/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 3/30/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 3/30/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 3/31/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 3/31/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/31/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 3/31/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 3/31/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 4/1/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/1/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/1/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/1/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/1/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 4/1/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 4/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/4/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 4/4/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 4/4/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 4/4/2022 Partial Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 4/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/5/2022 Conditional Approval DAVID BURKHEAD
Structural Steel Frame 4/5/2022 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/6/2022 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/7/2022 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 4/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/12/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 4/12/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 4/12/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 4/12/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 4/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/13/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 4/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/14/2022 Approved DAVID BURKHEAD
Deputy Reinf. Masonry 4/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/14/2022 Approved DAVID BURKHEAD
Piling/Pier/Caisson 4/14/2022 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 4/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/15/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 4/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 4/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 5/3/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 5/3/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/3/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 5/3/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 5/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 5/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 5/4/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 5/4/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 5/4/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 5/4/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Drilled-In Anchors 5/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 5/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 5/5/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 5/6/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 5/6/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/6/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 5/6/2022 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 5/9/2022 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 5/9/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/9/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 5/9/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/11/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 5/12/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/13/2022 Conditional Approval DAVID BURKHEAD
Structural Steel Frame 5/17/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/18/2022 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 5/18/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/19/2022 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 5/19/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 5/20/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 5/20/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 5/20/2022 Not Ready for Inspection DAVID BURKHEAD
Piling/Pier/Caisson 5/24/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 6/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 6/1/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 6/2/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/2/2022 Partial Approval RAFAEL ESPINOZA
Piling/Pier/Caisson 6/2/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Pre-Stress Concrete 6/3/2022 Conditional Approval TED RIES
Deputy Shotcrete 6/3/2022 Conditional Approval TED RIES
Piling/Pier/Caisson 6/3/2022 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 6/6/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 6/8/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 6/8/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 6/8/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Shotcrete 6/9/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/9/2022 Partial Approval DAVID BURKHEAD
Piling/Pier/Caisson 6/10/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 6/14/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 6/14/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 6/14/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Shotcrete 6/15/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 6/15/2022 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 6/29/2022 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 7/7/2022 Partial Approval DAVID BURKHEAD
Piling/Pier/Caisson 7/13/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 7/14/2022 Partial Approval DAVID BURKHEAD
Reinforced Masonry Frame 7/14/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 7/15/2022 Conditional Approval DAVID BURKHEAD
Green Building Rough 7/15/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 7/15/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/15/2022 Not Ready for Inspection DAVID BURKHEAD
Piling/Pier/Caisson 7/20/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 7/22/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 7/22/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/22/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 8/12/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 8/12/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 8/12/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 8/15/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/22/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/23/2022 Conditional Approval WINSTON DUNNING
Drywall Nailing 8/24/2022 Partial Approval TED RIES
Wood Frame 9/2/2022 Partial Inspection DAVID BURKHEAD
Masonry Wall/Backfill 9/8/2022 Partial Approval DAVID BURKHEAD
Deputy Steel/Welding 9/14/2022 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/16/2022 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Approval TED RIES
Deputy Wood Construction 10/5/2022 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 10/5/2022 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 10/7/2022 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 11/7/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Not Ready for Inspection TED RIES
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 11/17/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 12/1/2022 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 12/1/2022 Partial Approval DAVID BURKHEAD
Reinforced Concrete Frame 12/1/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 12/1/2022 Corrections Issued DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/2/2022 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 12/7/2022 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 12/8/2022 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 12/19/2022 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 12/21/2022 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 1/3/2023 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 1/4/2023 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 1/5/2023 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 1/6/2023 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 1/9/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 1/13/2023 Partial Inspection DAVID BURKHEAD
Light Gage Steel Frame 1/20/2023 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Partial Approval DAVID BURKHEAD
Wood Frame 1/25/2023 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 1/26/2023 Partial Inspection DAVID BURKHEAD
Light Gage Steel Frame 1/27/2023 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 2/6/2023 Corrections Issued DAVID BURKHEAD
Wood Frame 2/6/2023 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval DAVID BURKHEAD
Structural Steel Frame 2/9/2023 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 3/6/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/6/2023 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 3/6/2023 Partial Inspection DAVID BURKHEAD
Light Gage Steel Frame 3/15/2023 Partial Inspection DAVID BURKHEAD
Wood Frame 4/19/2023 Partial Approval EDWIN GREGORYONA
Pre-Inspection 5/1/2023 Partial Inspection GREGORY POMISH
Structural Steel Frame 5/2/2023 Partial Approval GREGORY POMISH
Drywall Nailing 5/5/2023 Partial Approval GREGORY POMISH
Wood Frame 5/8/2023 Partial Inspection DAVID BURKHEAD
Wood Frame 5/10/2023 Partial Approval DAVID BURKHEAD
Wood Frame 5/15/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 5/16/2023 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/30/2023 Partial Approval DAVID BURKHEAD
Insulation 6/5/2023 Partial Approval TIMOTHY POWELL
Interior/Exterior Lathing 6/6/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval DAVID BURKHEAD
Insulation 6/9/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/9/2023 Partial Approval RAFAEL ESPINOZA
Insulation 6/12/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 6/13/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 6/14/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 6/15/2023 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 6/16/2023 Partial Approval DAVID BURKHEAD
Insulation 6/21/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 6/22/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Partial Approval DAVID BURKHEAD
Insulation 6/30/2023 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 7/11/2023 Partial Approval DAVID BURKHEAD
Wood Frame 7/17/2023 Partial Approval DAVID BURKHEAD
Insulation 7/20/2023 Partial Approval DAVID BURKHEAD
Insulation 7/26/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 7/31/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 8/2/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 8/3/2023 Partial Approval GREGORY POMISH
Drywall Nailing 8/14/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 8/16/2023 Approved EDWIN GREGORYONA
Masonry Wall/Backfill 8/17/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 8/21/2023 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 8/21/2023 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 8/22/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 8/24/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 8/28/2023 Not Ready for Inspection DAVID BURKHEAD
Insulation 8/30/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 9/5/2023 Partial Approval DAVID BURKHEAD
Insulation 9/6/2023 Partial Inspection DAVID BURKHEAD
Pre-Inspection 9/11/2023 Partial Approval DAVID BURKHEAD
Deputy Steel/Welding 9/14/2023 Conditional Approval DAVID BURKHEAD
Light Gage Steel Frame 9/14/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 9/18/2023 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 9/18/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 9/19/2023 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 9/25/2023 Partial Approval DAVID BURKHEAD
Insulation 9/26/2023 Partial Approval DAVID BURKHEAD
Insulation 9/27/2023 Partial Approval DAVID BURKHEAD
Wood Frame 9/28/2023 Partial Approval DAVID BURKHEAD
Wood Frame 10/3/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/5/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 10/6/2023 Partial Approval DAVID BURKHEAD
Wood Frame 10/10/2023 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 10/12/2023 Partial Approval EDWIN GREGORYONA
Pre-Inspection 10/17/2023 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 10/19/2023 Partial Approval RONALD JIMENEZ
Pre-Inspection 10/24/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 10/26/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/30/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/31/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 11/2/2023 Partial Approval DAVID BURKHEAD
Wood Frame 11/6/2023 Partial Inspection DAVID BURKHEAD
Drywall Nailing 11/8/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 11/13/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 11/14/2023 Partial Approval DAVID BURKHEAD
Wood Frame 11/17/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/21/2023 Partial Approval DAVID BURKHEAD
Wood Frame 11/27/2023 Partial Approval DAVID BURKHEAD
Pre-Inspection 11/28/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 12/7/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/12/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 12/13/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/14/2023 Partial Approval GREGORY POMISH
Insulation 12/18/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 12/26/2023 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 1/3/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 1/5/2024 Partial Approval DAVID BURKHEAD
Insulation 1/16/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 1/18/2024 Partial Approval EDWIN GREGORYONA
Insulation 1/18/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/19/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/22/2024 Partial Approval DAVID BURKHEAD
Insulation 1/29/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 2/1/2024 Approved DAVID BURKHEAD
Drywall Nailing 2/6/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/6/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/7/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/9/2024 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 2/12/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/20/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/27/2024 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 3/11/2024 Partial Approval DAVID BURKHEAD
Insulation 3/18/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 4/15/2024 Partial Approval DAVID BURKHEAD
Wood Frame 5/2/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/16/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 5/20/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 5/21/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 6/14/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 6/24/2024 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 7/11/2024 Partial Approval LARRY ARNICK
Pre-Inspection 8/21/2024 Approved EDWIN GREGORYONA
Green Building Final 8/26/2024 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 8/27/2024 Approved DAVID BURKHEAD
Final 9/23/2024 Partial Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV Not Ready DAVID BURKHEAD
Verify Sprinkler Sign Off 9/23/2024 Partial Inspection DAVID BURKHEAD
Final 9/25/2024 Corrections Issued DAVID BURKHEAD
Footing/Foundation/Slab 9/25/2024 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 9/25/2024 SGSOV Not Ready DAVID BURKHEAD
Smoke Detectors 9/25/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/25/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 9/26/2024 Partial Inspection DAVID BURKHEAD
Final 9/30/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 9/30/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 9/30/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 9/30/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 9/30/2024 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready DAVID BURKHEAD
Smoke Detectors 9/30/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/30/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 10/1/2024 Partial Inspection DAVID BURKHEAD
Posting Pre-Inspection 10/2/2024 Partial Inspection DAVID BURKHEAD
Interior/Exterior Lathing 10/3/2024 Not Ready for Inspection DAVID BURKHEAD
Final 10/7/2024 Partial Inspection DAVID BURKHEAD
Green Building Final 10/7/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 10/7/2024 Approved DAVID BURKHEAD
Reinforced Concrete Frame 10/7/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 10/7/2024 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 10/7/2024 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 10/7/2024 Partial Approval DAVID BURKHEAD
Posting Pre-Inspection 10/8/2024 Corrections Issued DAVID BURKHEAD
Pre-Inspection 10/10/2024 Approved DAVID BURKHEAD
Final 10/11/2024 Partial Inspection DAVID BURKHEAD
Green Building Final 10/11/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 10/11/2024 Partial Approval DAVID BURKHEAD
Reinforced Masonry Frame 10/11/2024 Partial Approval DAVID BURKHEAD
Smoke Detectors 10/11/2024 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 10/11/2024 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 10/16/2024 Partial Approval DAVID BURKHEAD
T-Bar Ceiling 10/16/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 10/22/2024 Approved DAVID BURKHEAD
Green Building Final 11/19/2024 Partial Inspection EDWIN GREGORYONA
Final 11/20/2024 Partial Inspection DAVID BURKHEAD
Reinforced Concrete Frame 11/20/2024 Approved DAVID BURKHEAD
Reinforced Masonry Frame 11/20/2024 Approved DAVID BURKHEAD
Smoke Detectors 11/20/2024 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 11/20/2024 Approved DAVID BURKHEAD
Special/Order Compliance 5/6/2025 Approved DAVID BURKHEAD
Final 5/21/2025 Partial Inspection DAVID BURKHEAD
Green Building Final 5/21/2025 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 11/12/2025 Approved DAVID BURKHEAD
Final 1/28/2026 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 1/28/2026 Not Ready for Inspection DAVID BURKHEAD
Final 4/7/2026 OK to Issue CofO DAVID BURKHEAD
Green Building Final 4/7/2026 Approved DAVID BURKHEAD