Pre-Inspection
|
1/26/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
2/7/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
2/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
2/9/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
2/9/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
3/2/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
4/6/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
4/8/2022
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
5/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
5/14/2022
|
Off-Hour Fees Due
|
|
|
Wood Frame
|
6/6/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/16/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/16/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/22/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/22/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/19/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/26/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/29/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/5/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/9/2022
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
9/12/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/16/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/19/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
10/13/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/13/2022
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/29/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
10/29/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
11/2/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
11/16/2022
|
Partial Approval
|
JAMES POWERS
|
|
Wall Anchors
|
11/16/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
11/17/2022
|
Partial Approval
|
JAMES POWERS
|
|
Wall Anchors
|
11/18/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/1/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Rough
|
12/1/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
12/1/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
12/1/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
12/1/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Rough
|
12/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
12/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
12/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/6/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
1/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
1/18/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
1/19/2023
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/23/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/25/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
2/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Insulation
|
3/7/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
4/3/2023
|
Approved
|
GREGORY POMISH
|
|
Green Building Rough
|
6/14/2023
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
6/14/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
6/14/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
8/29/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/20/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/28/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
10/11/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
10/11/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
10/23/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
10/23/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
12/11/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
12/19/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
12/27/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
1/19/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/25/2024
|
Approved
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
1/25/2024
|
Approved
|
JAMES POWERS
|
|
Final
|
5/30/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
5/30/2024
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
5/30/2024
|
Approved
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
5/30/2024
|
SGSOV Approved
|
JAMES POWERS
|
|
Smoke Detectors
|
5/30/2024
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/30/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
5/30/2024
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
10/3/2024
|
OK for TCO
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
10/3/2024
|
Approved
|
JAMES POWERS
|
|
Wood Frame
|
10/3/2024
|
Approved
|
JAMES POWERS
|
|
Final
|
10/16/2024
|
OK for TCO
|
JAMES POWERS
|
|
Final
|
10/22/2024
|
OK to Issue CofO
|
JAMES POWERS
|