2533 1/2 N IVAN HILL TER 90039

Certificate Information: 2533 1/2 N IVAN HILL TER 90039

Application / Permit
20010-10000-02371
Plan Check / Job No.
B20LA12322
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story over basement ADU with roof deck.
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 RODOLFO ARIAS
Corrections Issued 8/12/2020 RODOLFO ARIAS
Quality Review Completed 8/13/2020 EUGENE BARBEAU
Applicant returned to address corrections 5/25/2021 RODOLFO ARIAS
Applicant returned to address corrections 9/15/2021 RODOLFO ARIAS
Applicant returned to address corrections 9/22/2021 RODOLFO ARIAS
Applicant returned to address corrections 10/1/2021 RODOLFO ARIAS
Applicant returned to address corrections 10/14/2021 RODOLFO ARIAS
Applicant returned to address corrections 10/22/2021 RODOLFO ARIAS
Applicant returned to address corrections 11/1/2021 RODOLFO ARIAS
Applicant returned to address corrections 11/16/2021 RODOLFO ARIAS
Applicant returned to address corrections 11/19/2021 RODOLFO ARIAS
Plan Check Approved 2/7/2022 RODOLFO ARIAS
Issued 2/10/2022 APPLICANT
Building Plans Picked Up 2/16/2022 APPLICANT
CofO in Progress 7/1/2024 ENRIQUE MIRELES
CofO Issued 7/3/2024 DEROLD HAUFF
Permit Finaled 7/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/14/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/14/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/14/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/14/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/14/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 1/21/2021 JEREMY CARTER
Sewer availability Cleared 2/19/2021 CECILIO NAVARRO
Certificate of Compliance Cleared 2/23/2021 MAXFIELD VERMY
Frnt yard landscape/Water mgmt Cleared 2/23/2021 MAXFIELD VERMY
Tract Map conditions Cleared 2/23/2021 MAXFIELD VERMY
ZA Case Cleared 2/23/2021 MAXFIELD VERMY
ZA Case Cleared 2/23/2021 MAXFIELD VERMY
ZA Case Cleared 2/23/2021 MAXFIELD VERMY
ZA Case Cleared 2/23/2021 MAXFIELD VERMY
ZA Case Cleared 2/23/2021 MAXFIELD VERMY
BHO/Hillside ordinance Cleared 3/5/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/10/2021 CECILIO NAVARRO
Low Impact Development Cleared 4/26/2021 ANDRES COVARRUBIAS
Highway dedication Cleared 5/27/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 6/2/2021 CECILIO NAVARRO
Construction near power lines Cleared 8/4/2021 RIDWAN HARDY
GPI Written Notices Cleared 10/14/2021 RODOLFO ARIAS
Grading Pre-Inspection Cleared 10/14/2021 RODOLFO ARIAS
Excavation more than 5-ft deep Cleared 10/22/2021 CALOSHA APPROVED
Permit Cleared 12/9/2021 AMAAN MALIK

Contact Information

Architect Techentin,, Warren A; Lic. No.: C28100 2066 N EDGEMONT STREET      LOS ANGELES, CA 90027
Contractor Giraffe Construction; Lic. No.: 1035286-B 6348 1/2 PRIMROSE AVE      HOLLYWOOD, CA 90068
Engineer Abedian,, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Cugno,, Giuseppe; Lic. No.: EG1804 1461 E CHEVY CHASE DR 200   BYER GEOTECHNICAL, INC.    GLENDALE, CA 91206

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2022 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 3/11/2022 Partial Inspection JOSEPH MCGARRY
Piling/Pier/Caisson 3/11/2022 Partial Approval JOSEPH MCGARRY
Reinforced Concrete Frame 4/13/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/14/2022 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/5/2022 Partial Approval JOSEPH MCGARRY
Piling/Pier/Caisson 5/5/2022 Approved JOSEPH MCGARRY
Deputy Reinf. Concrete 5/9/2022 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 6/23/2022 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/23/2022 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 7/14/2022 Partial Approval JOSEPH MCGARRY
Deputy Steel/Welding 8/1/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 8/22/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Partial Approval JOSEPH MCGARRY
Gas Test 10/24/2022 Partial Approval JOSEPH MCGARRY
HVAC-Rough 10/24/2022 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/24/2022 Approved JOSEPH MCGARRY
Sewer 10/24/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 10/27/2022 Corrections Issued JULIAN AMAYA
ELECTRICAL-Rough 11/1/2022 Approved JOSEPH MCGARRY
Deputy Wood Construction 11/17/2022 Partial Approval JOSEPH MCGARRY
Shower Pan 12/6/2022 Approved JEFFREY MEAD
Green Building Rough 12/16/2022 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 12/16/2022 Conditional Approval RAUL BARAJAS
Verify Sprinkler Sign Off 12/16/2022 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 12/21/2022 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 2/2/2023 Partial Approval JOSEPH MCGARRY
Insulation 4/18/2023 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 4/25/2023 Approved JOSEPH MCGARRY
Drywall Nailing 4/25/2023 Approved JOSEPH MCGARRY
Green Building Rough 4/25/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 4/25/2023 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 4/25/2023 Approved JOSEPH MCGARRY
Gas Test 10/19/2023 Approved JOSEPH MCGARRY
PLUMBING-Final 10/19/2023 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Approved JOSEPH MCGARRY
ELECTRICAL-Rough 11/7/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Final 11/14/2023 Approved JOSEPH MCGARRY
HVAC-Final 11/28/2023 No Access for Inspection JOSEPH MCGARRY
HVAC-Final 12/11/2023 Corrections Issued BRENDAN MORELLI
HVAC-Final 1/11/2024 Approved RICHARD DOCKUS
Final 6/7/2024 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 6/7/2024 Approved ENRIQUE MIRELES
Green Building Final 6/7/2024 Approved ENRIQUE MIRELES
Smoke Detectors 6/7/2024 Approved ENRIQUE MIRELES
Final 6/21/2024 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 6/21/2024 Approved ENRIQUE MIRELES