1920 N LAUGHLIN PARK DR 90027

Certificate Information: 1920 N LAUGHLIN PARK DR 90027

Application / Permit
20010-10000-02348
Plan Check / Job No.
B20LA12218
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW ACCESSORY LIVING QUARTER W/ATTACHED GARAGE
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
Issued on 6/16/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 CARLOS MONTES
Corrections Issued 8/20/2020 CARLOS MONTES
Quality Review Completed 9/28/2020 WING SUEN
Building Plans Picked Up 10/9/2020 APPLICANT
Applicant returned to address corrections 12/22/2020 CARLOS MONTES
Plan Check Approved 5/26/2022 CARLOS MONTES
Issued 6/16/2022 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/14/2020 RENZ SORIANO
BHO/Hillside ordinance Cleared 12/14/2020 RENZ SORIANO
BHO/Hillside ordinance Cleared 12/14/2020 RENZ SORIANO
BHO/Hillside ordinance Cleared 12/14/2020 RENZ SORIANO
BHO/Hillside ordinance Cleared 12/14/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 12/15/2020 RENZ SORIANO
GPI Written Notices Cleared 12/16/2020 CARLOS MONTES
Grading Pre-Inspection Cleared 12/16/2020 CARLOS MONTES
Permit Cleared 12/16/2020 RENZ SORIANO
Sewer availability Cleared 12/16/2020 RENZ SORIANO
ZA Case Cleared 12/18/2020 MAXFIELD VERMY
Hydrant and Access approval Cleared 1/25/2021 KURT CORRAL
Trees in Parkway Cleared 1/28/2021 JOHN KIM
Private street Cleared 4/1/2021 MAXFIELD VERMY
Low Impact Development Cleared 12/1/2021 TA ANH
Roof/Waste drainage to street Cleared 12/6/2021 CINDY QI
Specific Plan Cleared 5/12/2022 ANACANY HURTADO

Contact Information

Architect Meyer,, James Randolph; Lic. No.: C30803 440 34TH STREET      MANHATTAN BEACH, CA 90266
Contractor Pch Construction; Lic. No.: 1005176-B 26026 REDBLUFF DRIVE      CALABASAS, CA 91302
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/18/2022 Approved BRIAN SULLIVAN
Underground Mechanical 8/18/2022 Partial Approval BRIAN SULLIVAN
Grading Pre-Inspection 9/15/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/14/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/24/2022 Conditional Approval JOAQUIN GREENOUGH
Underground Mechanical 10/24/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Steel/Welding 10/26/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/15/2022 Conditional Approval JOAQUIN GREENOUGH
Deputy Steel/Welding 12/7/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 3/28/2023 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval JOAQUIN GREENOUGH
Special/Order Compliance 4/24/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/15/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 6/15/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 6/15/2023 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 6/15/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/28/2023 Partial Approval JOAQUIN GREENOUGH
HVAC-Rough 7/21/2023 Approved STUART CHAPMAN
PLUMBING-Rough 7/21/2023 Approved STUART CHAPMAN
Sewer 7/21/2023 Corrections Issued STUART CHAPMAN
Wood Frame 8/31/2023 Corrections Issued JOAQUIN GREENOUGH
Wood Frame 9/7/2023 Partial Approval JOAQUIN GREENOUGH
Shower Pan 9/18/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/26/2023 Approved JOAQUIN GREENOUGH
Wood Frame 10/2/2023 Approved JOAQUIN GREENOUGH
Insulation 10/18/2023 Approved ROY SPAULDING
Drywall Nailing 10/24/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 10/24/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/5/2024 Approved ROY SPAULDING
ELECTRICAL-Final 6/5/2024 Approved ROY SPAULDING
Final 6/5/2024 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 6/5/2024 Approved ROY SPAULDING
Green Building Final 6/5/2024 Approved ROY SPAULDING
HVAC-Final 6/5/2024 Approved ROY SPAULDING
PLUMBING-Final 6/5/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Approved ROY SPAULDING
Service/Power Release 6/5/2024 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 6/5/2024 Approved ROY SPAULDING
Verify Sprinkler Sign Off 6/5/2024 Approved ROY SPAULDING