2518-2518 1/2 E MALABAR ST 90033
Certificate Information: 2518-2518 1/2 E MALABAR ST 90033
- Application / Permit
- 20010-10000-02318
- Plan Check / Job No.
- B20LA12058
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 35' X 40' 2-STORY DUPLEX (REAR DUPLEX) 2 OF 2
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 6/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 8/5/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 9/17/2020 | WING SUEN |
| Building Plans Picked Up | 10/7/2020 | APPLICANT |
| Applicant returned to address corrections | 3/18/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/24/2021 | CRYSTEL MAALOUF |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 5/17/2022 | OSVALDO PARAMO |
| CofO in Progress | 5/17/2022 | OSVALDO PARAMO |
| Permit Finaled | 6/3/2022 | DEROLD HAUFF |
| CofO Issued | 6/3/2022 | DEROLD HAUFF |
| Permit Finaled | 6/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 10/15/2020 | TERRI OSBORNE |
| Address approval | Cleared | 10/20/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | JEANIE LAM |
| Permit | Cleared | 10/20/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/20/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 2/9/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/4/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/5/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 3/24/2021 | CRYSTEL MAALOUF |
| Green Code | Cleared | 3/24/2021 | CRYSTEL MAALOUF |
Contact Information
| Contractor | R One Development Group Inc; Lic. No.: 1039213-B | 15030 VENTURA BLVD SUITE 621 SHERMAN OAKS, CA 91403 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2021 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/26/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 5/11/2021 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 5/11/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2021 | Partial Approval | OSVALDO PARAMO |
| Insulation | 5/17/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 6/28/2021 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2021 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 7/13/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 7/14/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/19/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/20/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 7/20/2021 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 7/20/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/28/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 7/29/2021 | No Access for Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 7/29/2021 | No Access for Inspection | SCOTT FINNILA |
| Drywall Nailing | 8/20/2021 | Corrections Issued | RUBEN SALAS |
| Drywall Nailing | 8/24/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 10/5/2021 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 10/7/2021 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 11/2/2021 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 11/5/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/29/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 3/30/2022 | Approved | OSVALDO PARAMO |
| HVAC-Final | 3/31/2022 | Approved | OSVALDO PARAMO |
| Final | 5/4/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/4/2022 | Approved | OSVALDO PARAMO |
| Gas Test | 5/4/2022 | Approved | OSVALDO PARAMO |
| Green Building Final | 5/4/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 5/4/2022 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/4/2022 | Approved | OSVALDO PARAMO |
| Final | 5/9/2022 | OK to Issue CofO | OSVALDO PARAMO |