15200 W BLEDSOE ST 91342

Certificate Information: 15200 W BLEDSOE ST 91342

Application / Permit
20010-10000-02309
Plan Check / Job No.
B20LA12031
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NEW 3 -STORY CONCRETE TILT-UP BLDG W/ STL FRAME CONSTRUCTION THAT CONSISTS OF 3 CONTINUOUS FIRE WALLS SEPARATE THE BLDG INTO 3 BUILDINGS; 1-STORY PORTION FIRE WALL SEPARATE INTO 2 FIRE AREAS TO BE USED AS SOUND STAGE STUDIOS. 3-STORY FIRE AREA PORTION TO BE USED AS OFFICE BUILDING. TYPE III-B CORE AND SHELL ONLY, T.I. shall be comply to code required for each use. req'd parkings are located in the parking structure under permit # 20010-10k-01637
Permit Issued
Issued on 5/10/2022
Issuing Office
Metro
Current Status
Issued on 5/10/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/4/2020 APPLICANT
Application Withdrawn 8/4/2020 APPLICANT
Re-Activate Applicaton 8/13/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 SAM CHANG
Corrections Issued 9/14/2020 SAM CHANG
Quality Review Completed 9/29/2020 TIEN JEN WANG
Applicant returned to address corrections 10/26/2020 SAM CHANG
Applicant returned to address corrections 10/27/2020 SAM CHANG
Applicant returned to address corrections 11/17/2020 SAM CHANG
Applicant returned to address corrections 12/2/2020 SAM CHANG
Green Plans Picked Up 4/23/2021 APPLICANT
Applicant returned to address corrections 7/7/2021 SAM CHANG
Disabled Access Plans Picked Up 10/7/2021 APPLICANT
Building Plans Picked Up 1/11/2022 APPLICANT
Plan Check Approved 4/21/2022 SAM CHANG
Issued 5/10/2022 APPLICANT

Permit Application Clearance Information

Site Plan review Cleared 10/9/2020 SUSAN ZERMENO
Eng Process Fee Ord 176,300 Cleared 10/13/2020 GUILLERMO PETRA
Metro Rail approval Cleared 10/14/2020 SAM CHANG
Hydrant and Access approval Cleared 11/13/2020 MATTHEW CRAIG
Construction near power lines Cleared 12/16/2020 WALTER RAMIREZ
DAS Clearance Cleared 3/4/2021 SAM CHANG
Green Code Cleared 4/22/2021 AARON COSTA
Driveway location Cleared 5/12/2021 SHEILA AHORAIAN
Internal circulation Cleared 5/12/2021 SHEILA AHORAIAN
Permit Cleared 5/17/2021 GABRIEL ROBLES
Fire Marshall Fire Life Safety Cleared 6/28/2021 OSCAR SALGADO JR
Motion picture studio Cleared 6/30/2021 OSCAR SALGADO JR
Building over 36-ft Cleared 7/1/2021 CALOSHA APPROVED
Sewer availability Cleared 10/26/2021 CARLOS AGUILERA
Prkng lot landscape/Water mgmt Cleared 11/24/2021 DANIEL CORONADO
Trees in Parkway Cleared 12/15/2021 ADALBERTO VERA
Highway dedication Cleared 1/11/2022 LEE GUILBEAUX
Low Impact Development Cleared 2/24/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/24/2022 JOHN LIN

Contact Information

Architect Nouizi,, Ilyes M; Lic. No.: C32135 14252 CULVER DRIVE SUITE A-605      IRVINE, CA 92604
Contractor Xebec Building Company Inc; Lic. No.: 600621-B 3010 OLD RANCH PARKWAY STE 480      SEAL BEACH, CA 90740
Engineer Gerges,, Rafik Refaat; Lic. No.: S5092 1906 W GARVEY AVE STE 200      WEST COVINA, CA 91790
Engineer Govil,, Sanjay; Lic. No.: GE2382 4 TULAROSA COURT      ALISO VIEJO, CA 92656
Engineer Jacoby,, Samuel J; Lic. No.: C74309 8881 RESEARCH DR      IRVINE, CA 92618
Geologist Burrows,, Edward Louis; Lic. No.: EG1750 1303 E PALLARES LN      PLACENTIA, CA 92870
Landscape Architect Nolan,, Colleen M; Lic. No.: LA5439 7 ROBLE #36      RANCHO SANTA MARGARITA, CA 92688

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/3/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 6/3/2022 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/16/2022 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/11/2022 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/12/2022 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/13/2022 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/21/2022 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/24/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/25/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/1/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/1/2022 Partial Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/16/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/16/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/16/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/17/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/22/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/22/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/29/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 12/8/2022 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/12/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/13/2022 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 12/15/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/20/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/27/2022 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 12/28/2022 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 12/29/2022 Conditional Approval BRUCE CAMPBELL
Deputy Steel/Welding 1/9/2023 No Access for Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/9/2023 Conditional Approval STEVEN LEVITT
Deputy Reinf. Concrete 1/19/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/19/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/19/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/23/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/24/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/25/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/26/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/1/2023 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 2/1/2023 Conditional Approval STEVEN LEVITT
Deputy Reinf. Concrete 2/3/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/3/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/3/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 2/3/2023 Not Ready for Inspection STEVEN LEVITT
Deputy Reinf. Concrete 2/7/2023 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/7/2023 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/8/2023 Partial Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 2/22/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 2/22/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/3/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 3/6/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/8/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/9/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/10/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 3/16/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 3/17/2023 Approved JOHN KITCKO
Deputy Steel/Welding 3/20/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/28/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/28/2023 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/30/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 3/31/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/3/2023 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/3/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/4/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 4/11/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 4/12/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/12/2023 Partial Approval JOHN KITCKO
Deputy Steel/Welding 4/13/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/14/2023 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 4/14/2023 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/17/2023 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/17/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/20/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 4/20/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 4/21/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 4/24/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 4/26/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 4/27/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/2/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/3/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/4/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/5/2023 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 5/8/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/9/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/10/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/11/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/12/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/15/2023 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 5/16/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/17/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 5/18/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/18/2023 Partial Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 5/19/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/19/2023 Corrections Issued DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/22/2023 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 5/23/2023 Not Ready for Inspection ANDREW DORSO
Deputy Reinf. Concrete 5/24/2023 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 5/24/2023 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 5/25/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/25/2023 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/26/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/26/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/30/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/30/2023 Partial Approval BRIAN KELLY
Footing/Foundation/Slab 5/30/2023 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 5/31/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/31/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 6/1/2023 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 6/2/2023 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 6/5/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/6/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/7/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/8/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/9/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/12/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/12/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 6/13/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/14/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/14/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/14/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/15/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/16/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/16/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/20/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/20/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/20/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/21/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/21/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/22/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 6/23/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/26/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/27/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/27/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/27/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 6/27/2023 Partial Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 6/28/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/29/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 6/30/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/5/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/6/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/7/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/10/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/11/2023 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 7/12/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 7/13/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/14/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/18/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/19/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/20/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/21/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 7/24/2023 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 7/25/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/26/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/27/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/27/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/28/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 7/31/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/1/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/2/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/3/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/4/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/7/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/8/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/9/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/10/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/11/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/14/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/15/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/16/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/17/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/18/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/22/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/23/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/24/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/25/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/5/2023 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 9/6/2023 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 9/7/2023 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 9/8/2023 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 9/11/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 9/12/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/13/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 9/14/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/15/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/19/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/19/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/20/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/21/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 9/22/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/22/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/22/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 9/26/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 9/26/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 9/27/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/27/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 9/28/2023 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/28/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/29/2023 Approved DANNY RODRIGUEZ
Deputy Wood Construction 9/29/2023 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/2/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/2/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/3/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/4/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/5/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/6/2023 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 10/12/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/16/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/17/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 10/17/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/18/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/18/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/18/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/19/2023 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/20/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/20/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/23/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/23/2023 Approved DANNY RODRIGUEZ
Deputy Wood Construction 10/23/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/24/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/24/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/24/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/25/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/25/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/25/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/26/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/27/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/27/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/30/2023 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/31/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/3/2023 Conditional Approval ANDREW DORSO
Light Gage Steel Frame 11/3/2023 Not Ready for Inspection ANDREW DORSO
Special/Order Compliance 11/3/2023 Not Ready for Inspection ANDREW DORSO
Deputy Steel/Welding 11/6/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/7/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/8/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/8/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/9/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/13/2023 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 11/14/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/15/2023 No Access for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 11/16/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/17/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/20/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/21/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/22/2023 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 11/27/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/28/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 11/28/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/28/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/29/2023 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/30/2023 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 11/30/2023 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 12/1/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/4/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/4/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/5/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/5/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/6/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/6/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/6/2023 Partial Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/7/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/7/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 12/7/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/8/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/8/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/11/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/12/2023 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 12/13/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/14/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/15/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/18/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/19/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/20/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/21/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/22/2023 No Access for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 12/27/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/28/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/2/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 1/3/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/4/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/5/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 1/8/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/9/2024 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/10/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/11/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/12/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/16/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 1/16/2024 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/16/2024 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/17/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/18/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 1/19/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/19/2024 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 1/25/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/29/2024 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/29/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/30/2024 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/30/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/5/2024 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 3/29/2024 Conditional Approval DANNY RODRIGUEZ
Light Gage Steel Frame 4/1/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/23/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/24/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 4/29/2024 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/6/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 5/9/2024 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 5/9/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 5/13/2024 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 5/13/2024 Partial Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 5/15/2024 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/15/2024 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/15/2024 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/16/2024 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 5/17/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/21/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/23/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/30/2024 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 5/30/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 5/30/2024 Partial Inspection ANDREW DORSO
Special/Order Compliance 5/30/2024 Partial Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 5/31/2024 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 6/3/2024 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 6/3/2024 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 6/5/2024 Conditional Approval ANDREW DORSO
Drywall Nailing 6/5/2024 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 6/5/2024 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 6/17/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/17/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 6/17/2024 Partial Approval GREGORY POMISH
Special/Order Compliance 6/17/2024 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/2/2024 Approved DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/6/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/8/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/9/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/12/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/13/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/14/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/15/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/16/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/19/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/19/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/20/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/20/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/21/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/21/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/22/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/22/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 8/23/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/27/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/27/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 8/28/2024 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/28/2024 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 8/29/2024 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 8/29/2024 Conditional Approval JOHN KITCKO
Deputy Drilled-In Anchors 8/30/2024 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 8/30/2024 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 9/3/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 9/4/2024 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 9/5/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/6/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/9/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/10/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 9/11/2024 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 9/11/2024 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/12/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/13/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/18/2024 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 9/25/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/26/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 9/27/2024 Conditional Approval DANNY RODRIGUEZ
Structural Steel Frame 10/7/2024 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/8/2024 Conditional Approval CAMERON CHABAN
Structural Steel Frame 10/9/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 10/11/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/11/2024 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/11/2024 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/15/2024 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 10/16/2024 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 10/18/2024 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 10/21/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 10/21/2024 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 10/29/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/31/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/4/2024 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/4/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/5/2024 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 11/5/2024 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/8/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/14/2024 Conditional Approval DANNY RODRIGUEZ
Insulation 11/18/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/20/2024 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/21/2024 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 11/26/2024 Partial Inspection ANDREW DORSO
Structural Steel Frame 11/26/2024 Not Ready for Inspection ANDREW DORSO
Deputy Reinf. Concrete 12/10/2024 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/10/2024 Partial Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/11/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/11/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/11/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/12/2024 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/16/2024 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/19/2024 Conditional Approval DANNY RODRIGUEZ
Drywall Nailing 12/24/2024 No Access for Inspection DANNY RODRIGUEZ
Drywall Nailing 12/30/2024 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/6/2025 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 1/14/2025 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/15/2025 Conditional Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/16/2025 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 1/22/2025 Partial Approval DANNY RODRIGUEZ
Wall Anchors 1/22/2025 Approved DANNY RODRIGUEZ
Drywall Nailing 1/29/2025 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/29/2025 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/29/2025 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 2/3/2025 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 2/3/2025 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/5/2025 Partial Approval DANNY RODRIGUEZ
Insulation 2/11/2025 Partial Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 2/13/2025 Conditional Approval ANDREW DORSO
Drywall Nailing 2/14/2025 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 2/26/2025 Conditional Approval DANNY RODRIGUEZ
Light Gage Steel Frame 3/27/2025 Partial Inspection BRIAN KELLY
Light Gage Steel Frame 4/3/2025 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/14/2025 Partial Approval GREGORY POMISH
Insulation 4/14/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 4/16/2025 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/21/2025 Conditional Approval GREGORY POMISH
Drywall Nailing 4/21/2025 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 4/21/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 4/21/2025 Partial Approval GREGORY POMISH
Insulation 4/24/2025 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/30/2025 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/2/2025 Conditional Approval DANNY RODRIGUEZ
Drywall Nailing 5/8/2025 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/9/2025 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 6/9/2025 Partial Inspection ANDREW DORSO
Insulation 6/16/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 6/23/2025 Partial Approval GREGORY POMISH
Special/Order Compliance 6/23/2025 Partial Inspection GREGORY POMISH
Drywall Nailing 7/2/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 7/29/2025 Partial Approval JOHN KITCKO
Deputy Drilled-In Anchors 8/13/2025 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 8/18/2025 Partial Inspection ANDREW DORSO
Drywall Nailing 10/21/2025 Partial Approval GREGORY POMISH