10584 W PUTNEY ROAD 90064
Certificate Information: 10584 W PUTNEY ROAD 90064
- Application / Permit
- 20010-10000-02300
- Plan Check / Job No.
- B20LA11927
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE
- Permit Issued
- Issued on 11/24/2020
- Issuing Office
- Current Status
- CofO Issued on 5/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | DANIEL YIP |
| Corrections Issued | 8/6/2020 | DANIEL YIP |
| Quality Review Completed | 9/4/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 9/8/2020 | APPLICANT |
| Applicant returned to address corrections | 10/29/2020 | DANIEL YIP |
| Plan Check Approved | 11/20/2020 | DANIEL YIP |
| Issued | 11/24/2020 | APPLICANT |
| CofO in Progress | 5/6/2022 | KEVIN SARGSYAN |
| CofO in Progress | 5/9/2022 | KEVIN SARGSYAN |
| Permit Finaled | 5/20/2022 | DANIEL ORRANTE |
| CofO Issued | 5/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 9/11/2020 | KURT CORRAL |
| Sewer availability | Cleared | 9/11/2020 | DINAH GARIN |
| Specific Plan | Cleared | 9/15/2020 | JOE LUCKEY |
| Disturb/Remove Protected Trees | Cleared | 10/14/2020 | DANIEL YIP |
| Low Impact Development | Cleared | 10/21/2020 | MARTIN FRAGOSO |
| Specific Plan | Cleared | 10/29/2020 | VALERIA CEJA |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | DINAH GARIN |
| GPI Written Notices | Cleared | 11/18/2020 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 11/18/2020 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grabarek,, Jaroslaw; Lic. No.: L9258 | 668 TWIN PEAKS AVE SIMI VALLEY, CA 93065 |
| Engineer | Jung,, Jason Stanley; Lic. No.: C80569 | 1032 S PALM AVE SAN GABRIEL, CA 91776 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2020 | Partial Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/15/2021 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/22/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/22/2021 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/5/2021 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/5/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Grounding or Bonding | 2/5/2021 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/10/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/10/2021 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/10/2021 | Approved | KEVIN SARGSYAN |
| Grounding or Bonding | 2/10/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/10/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/2/2021 | Partial Approval | KEVIN SARGSYAN |
| Gas Test | 3/2/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/2/2021 | Partial Approval | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 3/2/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 3/3/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 3/5/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/14/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/29/2021 | Approved | KEVIN SARGSYAN |
| Sewer | 4/29/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 5/10/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 5/14/2021 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/18/2021 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/19/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 6/3/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/4/2021 | Partial Approval | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 6/4/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/14/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 6/14/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/14/2021 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 6/18/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 6/22/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 6/30/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/20/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/3/2022 | Approved | KEVIN SARGSYAN |
| Gas Test | 3/3/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 3/3/2022 | Approved | KEVIN SARGSYAN |
| Verify Rec and Parks Fee Memo | 3/22/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 3/23/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 4/25/2022 | No Access for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Not Ready | KEVIN SARGSYAN |
| Service/Power Release | 4/25/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Smoke Detectors | 4/25/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Final | 5/4/2022 | OK to Issue CofO | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 5/4/2022 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 5/4/2022 | Approved | KEVIN SARGSYAN |
| Final | 5/9/2022 | OK to Issue CofO | KEVIN SARGSYAN |