3424 W 36TH ST 90018

Certificate Information: 3424 W 36TH ST 90018

Application / Permit
20010-10000-02293
Plan Check / Job No.
B20LA11883
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
NEW 4 STORY TYPE IIA ANNEX BUILDING TO EXISTING CHURCH PER ZA 94-0478 AND ZA 96-0770 AND DIR-2020-3490-SPP
Permit Issued
Issued on 10/14/2021
Issuing Office
Metro
Current Status
CofO Issued on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 LARRY LEE
Corrections Issued 8/13/2020 LARRY LEE
Quality Review Completed 8/19/2020 CHARLES CHANG
Applicant returned to address corrections 8/28/2020 LARRY LEE
Applicant returned to address corrections 10/9/2020 LARRY LEE
Applicant returned to address corrections 10/27/2020 LARRY LEE
Applicant returned to address corrections 12/11/2020 LARRY LEE
Applicant returned to address corrections 1/15/2021 LARRY LEE
Applicant returned to address corrections 1/27/2021 LARRY LEE
Applicant returned to address corrections 2/23/2021 LARRY LEE
Applicant returned to address corrections 2/26/2021 LARRY LEE
Applicant returned to address corrections 5/14/2021 LARRY LEE
Applicant returned to address corrections 8/6/2021 LARRY LEE
Plan Check Approved 8/26/2021 LARRY LEE
Plan Check Approved 10/12/2021 LARRY LEE
Issued 10/14/2021 APPLICANT
Building Plans Picked Up 7/22/2022 APPLICANT
CofO in Progress 4/10/2024 JAMES POWERS
CofO Issued 4/10/2024 ERNESTO CORRAL
Permit Finaled 4/10/2024 ERNESTO CORRAL

Permit Application Clearance Information

CPC Cleared 10/16/2020 ANACANY HURTADO
"D" conditions Cleared 12/8/2020 KYLE WINSTON
Specific Plan Cleared 12/8/2020 KYLE WINSTON
Eng Process Fee Ord 176,300 Cleared 2/8/2021 CECILIO NAVARRO
Specific Plan Cleared 2/17/2021 WESTON PRINGLE
Address approval Cleared 2/25/2021 CECILIO NAVARRO
Miscellaneous Cleared 2/26/2021 ANACANY HURTADO
ZA Case Cleared 2/26/2021 ANACANY HURTADO
ZA Case Cleared 2/26/2021 ANACANY HURTADO
Redevelopment Project Area Cleared 3/2/2021 GRACIELA ACOSTA
Sewer availability Cleared 3/11/2021 WALLIE JONG
Building over 36-ft Cleared 3/17/2021 CALOSHA APPROVED
Hydrant and Access approval Cleared 4/2/2021 JOHN CONNEALLY
Highway dedication Cleared 4/13/2021 CECILIO NAVARRO
DAS Clearance Cleared 4/29/2021 LARRY LEE
Work Adjacent to Public Way Cleared 4/29/2021 JOSE RODRIGUEZ
Low Impact Development Cleared 5/6/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/11/2021 CECILIO NAVARRO
Construction near power lines Cleared 5/13/2021 RIDWAN HARDY
Construction within easement Cleared 5/13/2021 RIDWAN HARDY
Fire Marshall Fire Life Safety Cleared 6/7/2021 WILLIAM JOHNS
Flood clearance Cleared 7/8/2021 BRYAN GATHUKA
Green Code Cleared 7/26/2021 AARON COSTA

Contact Information

Architect Williamson,, Craig Robert; Lic. No.: C23466 8811 RESEARCH DRIVE SUITE 200      IRVINE, CA 92618
Contractor Klorman W M Construction Corporation; Lic. No.: 684991-B 23047 VENTURA BLVD 2ND FLOOR      WOODLAND HILLS, CA 91364
Engineer Bittar,, Simon Yousef; Lic. No.: C68166 11443 FOX HOLLOW LN      LOS ANGELES, CA 91331
Engineer Maingot,, Martin Rex; Lic. No.: S5623 4722 CASTLEWOOD STREET      SUGAR LAND, TX 77479

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/19/2021 Conditional Approval RUSSELL BONVOULOIR
Pre-Inspection 10/19/2021 Partial Inspection RUSSELL BONVOULOIR
Deputy Reinf. Concrete 10/20/2021 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 10/21/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 10/22/2021 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/1/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 11/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/10/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/15/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 11/16/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 11/16/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 11/22/2021 Approved TED RIES
Deputy Reinf. Concrete 11/23/2021 Conditional Approval TED RIES
Reinforced Concrete Frame 11/23/2021 Partial Approval TED RIES
Deputy Reinf. Concrete 11/24/2021 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/7/2022 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 1/7/2022 Partial Approval RAFAEL ESPINOZA
Deputy Other (see comments) 1/12/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/9/2022 Partial Approval JAMES POWERS
Deputy Other (see comments) 2/18/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/18/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/1/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/1/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/14/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/6/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/7/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/18/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/20/2022 Conditional Approval NICK DANERI
Deputy Pre-Stress Concrete 5/2/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/3/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/4/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/5/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/6/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/9/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/9/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/10/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/11/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/13/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/13/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/16/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/17/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/18/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/7/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/7/2022 Partial Approval JAMES POWERS
Pre-Inspection 6/7/2022 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 6/8/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/9/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/9/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/10/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/10/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/13/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/14/2022 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/17/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 6/21/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/5/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/6/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/15/2022 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 7/20/2022 Partial Approval JAMES POWERS
Insulation 7/27/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/4/2022 Partial Approval JAMES POWERS
Structural Steel Frame 8/4/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/15/2022 Not Ready for Inspection JAMES POWERS
Deputy Other (see comments) 8/25/2022 Partial Approval JAMES POWERS
Structural Steel Frame 8/30/2022 Partial Approval JAMES POWERS
Drywall Nailing 9/21/2022 Partial Approval JAMES POWERS
Insulation 9/22/2022 Partial Approval JAMES POWERS
Insulation 9/23/2022 Partial Approval JAMES POWERS
Drywall Nailing 10/17/2022 Partial Approval JAMES POWERS
Insulation 10/17/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/17/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/28/2022 Not Ready for Inspection JAMES POWERS
Insulation 10/28/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/28/2022 Partial Approval JAMES POWERS
Structural Steel Frame 10/28/2022 Not Ready for Inspection JAMES POWERS
Deputy Other (see comments) 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 11/2/2022 Partial Approval GREGORY POMISH
Deputy Other (see comments) 11/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 11/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/10/2022 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 11/10/2022 Partial Approval JAMES POWERS
Drywall Nailing 11/16/2022 Partial Approval JAMES POWERS
Insulation 11/28/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 12/1/2022 Partial Approval JAMES POWERS
Insulation 12/6/2022 Partial Approval JAMES POWERS
Insulation 12/19/2022 Partial Approval JAMES POWERS
Drywall Nailing 12/21/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/21/2022 Partial Approval JAMES POWERS
Drywall Nailing 12/29/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/29/2022 Partial Approval JAMES POWERS
Insulation 1/3/2023 Partial Approval JAMES POWERS
Insulation 1/6/2023 Partial Inspection EDWIN GREGORYONA
Insulation 1/9/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/9/2023 Partial Approval JAMES POWERS
Drywall Nailing 1/11/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/11/2023 Partial Approval JAMES POWERS
Drywall Nailing 1/17/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/17/2023 Partial Approval JAMES POWERS
Insulation 1/18/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/6/2023 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 2/7/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/21/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/28/2023 Approved JAMES POWERS
Drywall Nailing 3/6/2023 Partial Approval GREGORY POMISH
T-Bar Ceiling 3/13/2023 Approved JAMES POWERS
Drywall Nailing 3/14/2023 Partial Approval JAMES POWERS
T-Bar Ceiling 5/22/2023 Partial Approval LARRY ARNICK
T-Bar Ceiling 5/24/2023 Not Ready for Inspection LARRY ARNICK
Insulation 7/17/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/10/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/14/2023 Partial Approval JAMES POWERS
Green Building Rough 8/24/2023 Approved JAMES POWERS
Reinforced Concrete Frame 8/24/2023 Approved JAMES POWERS
Masonry Wall/Backfill 8/28/2023 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 8/28/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 8/28/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 8/29/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 8/29/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/29/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 8/29/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/29/2023 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/7/2023 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 9/7/2023 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/8/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/8/2023 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 9/18/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/21/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/22/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/22/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/25/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/26/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/2/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/3/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/3/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/4/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/12/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/19/2023 Approved JAMES POWERS
Special/Order Compliance 10/26/2023 Partial Approval LARRY ARNICK
Final 11/2/2023 Not Ready for Inspection JAMES POWERS
Green Building Final 11/2/2023 Approved JAMES POWERS
Reinforced Masonry Frame 11/2/2023 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Not Ready JAMES POWERS
Smoke Detectors 11/2/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/2/2023 Not Ready for Inspection JAMES POWERS
Final 2/29/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 2/29/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Approved JAMES POWERS
Verify Sprinkler Sign Off 2/29/2024 Approved JAMES POWERS
Final 3/11/2024 OK for TCO JAMES POWERS
Final 4/10/2024 OK to Issue CofO JAMES POWERS