14028 W HAMLIN ST 91401
Certificate Information: 14028 W HAMLIN ST 91401
- Application / Permit
- 20010-10000-02267
- Plan Check / Job No.
- B20LA11753
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU WITH ATTACHED GARAGE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 7/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/4/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/10/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 4/23/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/2/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/10/2021 | MAHNAZ NOURHASHEMI |
| Issued | 6/10/2021 | APPLICANT |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| CofO in Progress | 7/11/2022 | RICHARD DOCKUS |
| CofO Issued | 7/11/2022 | MICHAEL SMITH |
| Permit Finaled | 7/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2020 | GABRIEL ROBLES |
| Permit | Cleared | 10/5/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/6/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 10/15/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/21/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/8/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dedmari,, Wajahat Hafiz; Lic. No.: C66819 | 5541 GRAYLOG ST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 7/14/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 7/22/2021 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/29/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/17/2021 | Conditional Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 8/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 8/19/2021 | Corrections Issued | MICHAEL TEMPLE |
| Special/Order Compliance | 8/20/2021 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 9/1/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Sewer | 9/1/2021 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 9/8/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 9/15/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/17/2021 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 9/17/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 9/17/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 11/12/2021 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 11/12/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 11/12/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 11/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 11/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 11/24/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 11/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 11/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 12/2/2021 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/2/2021 | Not Ready for Inspection | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 12/2/2021 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 12/7/2021 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 12/17/2021 | Approved | RICHARD DOCKUS |
| Deputy Wood Construction | 12/29/2021 | No Access for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 12/30/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 12/30/2021 | Approved | RICHARD DOCKUS |
| Insulation | 12/30/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 1/14/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 1/14/2022 | Corrections Issued | ALAN MORELOS |
| Interior/Exterior Lathing | 1/21/2022 | Approved | RYAN SALAZAR |
| Underground Mechanical | 2/25/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Final | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 4/7/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Final | 4/15/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 4/15/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 4/27/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 4/27/2022 | Approved | RICHARD DOCKUS |
| Final | 5/11/2022 | Corrections Issued | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Not Ready | MICHAEL TEMPLE |
| Service/Power Release | 5/11/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Smoke Detectors | 5/11/2022 | Approved | MICHAEL TEMPLE |
| Final | 5/20/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Approved | RICHARD DOCKUS |
| Service/Power Release | 5/20/2022 | Not Required | RICHARD DOCKUS |
| Final | 6/13/2022 | Conditional Approval | MATT KELLERMAN |
| Service/Power Release | 6/13/2022 | Approved | MATT KELLERMAN |
| Final | 7/11/2022 | OK to Issue CofO | RICHARD DOCKUS |