1258-1260 W 37TH DR 90007

Certificate Information: 1258-1260 W 37TH DR 90007

Application / Permit
20010-10000-02263
Plan Check / Job No.
B20LA11727
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX
Permit Issued
Issued on 6/15/2021
Issuing Office
Current Status
CofO Issued on 7/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 DANIEL YIP
Corrections Issued 7/29/2020 DANIEL YIP
Quality Review Completed 8/14/2020 HERNAN ARREOLA
Building Plans Picked Up 8/27/2020 APPLICANT
Applicant returned to address corrections 10/23/2020 DANIEL YIP
Plan Check Approved 5/26/2021 DANIEL YIP
Issued 6/15/2021 APPLICANT
CofO in Progress 7/26/2022 HORACE FULTZ
Permit Finaled 7/27/2022 DEROLD HAUFF
CofO Issued 7/27/2022 DEROLD HAUFF
Permit Finaled 7/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/15/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 10/15/2020 JUAN ASHTON
Sewer availability Cleared 10/19/2020 JUAN ASHTON
Hydrant and Access approval Cleared 11/13/2020 MATTHEW CRAIG
ZI Cleared 4/26/2021 RAFAEL FONTES
Low Impact Development Cleared 5/11/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/18/2021 JEANIE LAM
Green Code Cleared 5/26/2021 DANIEL YIP

Contact Information

Contractor Tre Development Llc; Lic. No.: 1075573-B 2905 S VERMONT AVE   #204    LOS ANGELES, CA 90007
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2021 Approved JUSTIN CURTIS
Grading Pre-Inspection 6/29/2021 Off-Hour Fees Due
Deputy Reinf. Concrete 9/10/2021 Conditional Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 10/19/2021 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 10/19/2021 Partial Approval SABAS ALONSO
Underground Mechanical 10/19/2021 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 10/29/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 10/29/2021 Approved SABAS ALONSO
Deputy Reinf. Concrete 11/3/2021 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 11/10/2021 Conditional Approval LILIANA PORTILLO
Deputy Wood Construction 11/16/2021 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 11/23/2021 Conditional Approval SABAS ALONSO
Deputy Wood Construction 12/14/2021 Conditional Approval SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/29/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 12/30/2021 Approved SABAS ALONSO
HVAC-Rough 12/30/2021 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 1/5/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 1/5/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 1/5/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 1/5/2022 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 1/5/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 1/10/2022 Not Ready for Inspection HORACE FULTZ
HVAC-Rough 1/18/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 1/18/2022 Corrections Issued SABAS ALONSO
PLUMBING-Rough 1/18/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/20/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 1/20/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 1/20/2022 Partial Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/21/2022 Corrections Issued HORACE FULTZ
BUILDING-Rough-Frame 1/26/2022 Approved SABAS ALONSO
Green Building Rough 1/26/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 1/26/2022 Partial Approval SABAS ALONSO
Insulation 2/1/2022 Corrections Issued SABAS ALONSO
Insulation 2/7/2022 Approved SABAS ALONSO
Drywall Nailing 3/2/2022 Approved SABAS ALONSO
Underground Mechanical 4/19/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Final 5/16/2022 Approved SABAS ALONSO
Service/Power Release 5/16/2022 Approved SABAS ALONSO
Gas Test 5/23/2022 Approved SABAS ALONSO
HVAC-Final 5/23/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 5/23/2022 Approved SABAS ALONSO
HVAC-Final 5/26/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 5/26/2022 Approved SABAS ALONSO
HVAC-Final 5/31/2022 Not Ready for Inspection ANTHONY EGSON
Final 6/24/2022 Corrections Issued SABAS ALONSO
Final 6/30/2022 Corrections Issued HORACE FULTZ
Final 7/7/2022 OK to Issue CofO SABAS ALONSO