3021 S HALLDALE AVE 90018

Certificate Information: 3021 S HALLDALE AVE 90018

Application / Permit
20010-10000-02259
Plan Check / Job No.
B20LA11706
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER STATE LAW
Permit Issued
Issued on 10/27/2020
Issuing Office
Current Status
CofO Issued on 5/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 DANIEL YIP
Corrections Issued 7/27/2020 DANIEL YIP
Quality Review Completed 8/13/2020 HERNAN ARREOLA
Building Plans Picked Up 8/19/2020 APPLICANT
Plan Check Approved 10/27/2020 DANIEL YIP
Issued 10/27/2020 APPLICANT
CofO in Progress 3/8/2021 KATHRYN BUTTERWORTH
Permit Finaled 5/5/2021 DEROLD HAUFF
CofO Issued 5/5/2021 DEROLD HAUFF
Permit Finaled 5/5/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/4/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/4/2020 RENZ SORIANO
Community Plan Implem. Overlay Cleared 9/8/2020 DALE WILLIAMS
Roof/Waste drainage to street Cleared 9/15/2020 RENZ SORIANO
Sewer availability Cleared 9/15/2020 RENZ SORIANO
Community Plan Implem. Overlay Cleared 9/28/2020 RAFAEL FONTES
Specific Plan Cleared 9/28/2020 WESTON PRINGLE
Green Code Cleared 10/23/2020 DANIEL YIP

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2020 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/23/2020 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 11/23/2020 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 11/23/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/2/2020 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 12/2/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 1/4/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/4/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 1/4/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 1/4/2021 Partial Approval KATHRYN BUTTERWORTH
METHANE-Rough 1/4/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 1/4/2021 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 1/4/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 1/6/2021 Approved KATHRYN BUTTERWORTH
Insulation 1/6/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/6/2021 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 1/8/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 1/11/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/24/2021 Approved KATHRYN BUTTERWORTH
Final 2/24/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 2/24/2021 Approved KATHRYN BUTTERWORTH
HVAC-Final 2/24/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 2/24/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 2/24/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 2/24/2021 Approved KATHRYN BUTTERWORTH
Sewer 2/24/2021 Approved KATHRYN BUTTERWORTH
Smoke Detectors 2/24/2021 Approved KATHRYN BUTTERWORTH
Final 3/5/2021 OK to Issue CofO KATHRYN BUTTERWORTH