136-138 E 101ST ST 90003

Certificate Information: 136-138 E 101ST ST 90003

Application / Permit
20010-10000-02258
Plan Check / Job No.
B20LA11704
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX W/ ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 6/14/2021
Issuing Office
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 ZAW HAN
Corrections Issued 8/4/2020 ZAW HAN
Quality Review Completed 8/12/2020 TU HUA
Building Plans Picked Up 8/18/2020 APPLICANT
Applicant returned to address corrections 10/8/2020 ZAW HAN
Plan Check Approved 11/2/2020 ZAW HAN
Issued 6/14/2021 APPLICANT
CofO in Progress 3/23/2022 JOHN KLARIN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 8/20/2020 TERRI OSBORNE
Address approval Cleared 8/26/2020 ELAINE LEI
Address approval Cleared 8/26/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 8/26/2020 ELAINE LEI
Highway dedication Cleared 8/26/2020 ELAINE LEI
Hydrant and Access approval Cleared 9/4/2020 KURT CORRAL
Sewer availability Cleared 9/4/2020 ELAINE LEI
Low Impact Development Cleared 9/25/2020 YVAINNE GALSIM
Permit Cleared 9/28/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 9/28/2020 CELINA MORENO
Green Code Cleared 10/12/2020 VIVIAN LAO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2021 Approved ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 7/13/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 7/13/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval EUGENE CASSIDY
Insulation 7/15/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/9/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/16/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 9/16/2021 Approved EUGENE CASSIDY
Green Building Rough 9/16/2021 Approved EUGENE CASSIDY
HVAC-Rough 9/16/2021 Approved EUGENE CASSIDY
Insulation 9/16/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 9/16/2021 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 9/16/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 9/16/2021 Approved EUGENE CASSIDY
Insulation 9/17/2021 Approved EUGENE CASSIDY
Drywall Nailing 10/7/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/7/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/22/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 3/17/2022 Approved JOHN KLARIN
Final 3/17/2022 Partial Approval JOHN KLARIN
Green Building Final 3/17/2022 Approved JOHN KLARIN
HVAC-Final 3/17/2022 Approved JOHN KLARIN
PLUMBING-Final 3/17/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 3/17/2022 Approved JOHN KLARIN
Smoke Detectors 3/17/2022 Approved JOHN KLARIN
Verify Sprinkler Sign Off 3/17/2022 Approved JOHN KLARIN
Final 3/22/2022 OK to Issue CofO JOHN KLARIN