1315-1317 E 42ND PL 90011
Certificate Information: 1315-1317 E 42ND PL 90011
- Application / Permit
- 20010-10000-02255
- Plan Check / Job No.
- B20LA11697
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STY DUPLEX W/ ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 10/16/2020
- Issuing Office
- Current Status
- CofO Issued on 4/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 8/5/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 8/18/2020 | TU HUA |
| Building Plans Picked Up | 8/21/2020 | APPLICANT |
| Plan Check Approved | 10/16/2020 | CRYSTEL MAALOUF |
| Issued | 10/16/2020 | APPLICANT |
| CofO in Progress | 3/19/2021 | FREDDIE RIVERA |
| Permit Finaled | 4/20/2021 | DEROLD HAUFF |
| CofO Issued | 4/20/2021 | DEROLD HAUFF |
| Permit Finaled | 4/20/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2020 | CECILIO NAVARRO |
| Permit | Cleared | 8/26/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 9/4/2020 | KURT CORRAL |
| Sewer availability | Cleared | 9/16/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 10/5/2020 | CELINA MORENO |
| Low Impact Development | Cleared | 10/13/2020 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 10/16/2020 | CRYSTEL MAALOUF |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Partial Approval | ROBERT MCDOWELL |
| Insulation | 12/10/2020 | Partial Approval | ROBERT MCDOWELL |
| Underground Mechanical | 12/10/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | Partial Approval | ROBERT MCDOWELL |
| Insulation | 12/11/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 1/13/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/13/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 1/13/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 1/13/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 1/13/2021 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 1/13/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 1/13/2021 | Approved | STUART CHAPMAN |
| Insulation | 1/14/2021 | Partial Approval | DAVID FEILER |
| Drywall Nailing | 1/22/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/22/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/10/2021 | Approved | FREDDIE RIVERA |
| Final | 3/10/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 3/10/2021 | Approved | FREDDIE RIVERA |
| HVAC-Final | 3/10/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 3/10/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 3/10/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 3/10/2021 | Approved | FREDDIE RIVERA |
| Final | 3/19/2021 | OK to Issue CofO | FREDDIE RIVERA |