1315-1317 E 42ND PL 90011

Certificate Information: 1315-1317 E 42ND PL 90011

Application / Permit
20010-10000-02255
Plan Check / Job No.
B20LA11697
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STY DUPLEX W/ ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 10/16/2020
Issuing Office
Current Status
CofO Issued on 4/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 CRYSTEL MAALOUF
Corrections Issued 8/5/2020 CRYSTEL MAALOUF
Quality Review Completed 8/18/2020 TU HUA
Building Plans Picked Up 8/21/2020 APPLICANT
Plan Check Approved 10/16/2020 CRYSTEL MAALOUF
Issued 10/16/2020 APPLICANT
CofO in Progress 3/19/2021 FREDDIE RIVERA
Permit Finaled 4/20/2021 DEROLD HAUFF
CofO Issued 4/20/2021 DEROLD HAUFF
Permit Finaled 4/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2020 CECILIO NAVARRO
Permit Cleared 8/26/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/28/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 9/4/2020 KURT CORRAL
Sewer availability Cleared 9/16/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/5/2020 CELINA MORENO
Low Impact Development Cleared 10/13/2020 ORVAL HERNANDEZ-MARCI
Green Code Cleared 10/16/2020 CRYSTEL MAALOUF

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval ROBERT MCDOWELL
Insulation 12/10/2020 Partial Approval ROBERT MCDOWELL
Underground Mechanical 12/10/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Approval ROBERT MCDOWELL
Insulation 12/11/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/6/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 1/13/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 1/13/2021 Approved STUART CHAPMAN
Green Building Rough 1/13/2021 Approved STUART CHAPMAN
HVAC-Rough 1/13/2021 Approved STUART CHAPMAN
PLUMBING-Rough 1/13/2021 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 1/13/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 1/13/2021 Approved STUART CHAPMAN
Insulation 1/14/2021 Partial Approval DAVID FEILER
Drywall Nailing 1/22/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 1/22/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 3/10/2021 Approved FREDDIE RIVERA
Final 3/10/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 3/10/2021 Approved FREDDIE RIVERA
HVAC-Final 3/10/2021 Approved FREDDIE RIVERA
PLUMBING-Final 3/10/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 3/10/2021 Approved FREDDIE RIVERA
Smoke Detectors 3/10/2021 Approved FREDDIE RIVERA
Final 3/19/2021 OK to Issue CofO FREDDIE RIVERA