5913-5915 S DENVER AVE 90044

Certificate Information: 5913-5915 S DENVER AVE 90044

Application / Permit
20010-10000-02248
Plan Check / Job No.
B20LA11655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 8/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 DANIEL YIP
Corrections Issued 7/31/2020 DANIEL YIP
Quality Review Completed 8/31/2020 HERNAN ARREOLA
Building Plans Picked Up 9/3/2020 APPLICANT
Plan Check Approved 12/10/2020 DANIEL YIP
Issued 12/30/2020 APPLICANT
CofO in Progress 7/9/2021 ALEJANDRO DE ARTOLA
Permit Finaled 8/6/2021 DEROLD HAUFF
CofO Issued 8/6/2021 DEROLD HAUFF
Permit Finaled 8/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/17/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 9/17/2020 ELAINE LEI
Sewer availability Cleared 9/17/2020 ELAINE LEI
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/6/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 11/12/2020 CELINA MORENO
Green Code Cleared 12/8/2020 DANIEL YIP

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/7/2021 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/7/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/17/2021 Partial Approval ROBERT MCDOWELL
Sewer 2/17/2021 Approved ROBERT MCDOWELL
Underground Mechanical 2/17/2021 Approved ROBERT MCDOWELL
Wood Frame 2/17/2021 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Partial Approval ROBERT MCDOWELL
Insulation 2/19/2021 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Partial Approval FREDDIE RIVERA
Pre-Inspection 3/30/2021 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Approved FREDDIE RIVERA
HVAC-Rough 4/1/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 4/1/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/8/2021 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 4/8/2021 Approved FREDDIE RIVERA
Green Building Rough 4/8/2021 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 4/8/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/14/2021 Approved ROBERT MCDOWELL
Green Building Rough 4/14/2021 Approved ROBERT MCDOWELL
MERV13>=Rough 4/14/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 4/14/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 4/14/2021 Approved ROBERT MCDOWELL
Insulation 4/19/2021 Partial Approval FREDDIE RIVERA
Drywall Nailing 4/27/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 4/27/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 6/23/2021 Approved ALEJANDRO DE ARTOLA
Final 6/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/23/2021 Approved ALEJANDRO DE ARTOLA
Gas Test 6/23/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 6/23/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/23/2021 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 6/23/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/23/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/23/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 6/23/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 6/23/2021 Approved ALEJANDRO DE ARTOLA
Final 7/8/2021 OK to Issue CofO ALEJANDRO DE ARTOLA