1631 W 220TH ST 90501
Certificate Information: 1631 W 220TH ST 90501
- Application / Permit
- 20010-10000-02245
- Plan Check / Job No.
- B20LA11631
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 32.2' X 40' 2 STORY ADU WITH ATTACHED GARAGE
- Permit Issued
- Issued on 8/25/2021
- Issuing Office
- Current Status
- CofO Issued on 1/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 8/19/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 9/28/2020 | WING SUEN |
| Applicant returned to address corrections | 2/26/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 3/3/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 5/14/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/5/2021 | CRYSTEL MAALOUF |
| Issued | 8/25/2021 | APPLICANT |
| Building Plans Picked Up | 8/27/2021 | APPLICANT |
| CofO in Progress | 11/25/2022 | EUGENE CASSIDY |
| Permit Finaled | 1/9/2023 | ANSON MAGLASANG |
| CofO Issued | 1/9/2023 | ANSON MAGLASANG |
| Permit Finaled | 1/9/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | CHINH DINH |
| Sewer availability | Cleared | 10/20/2020 | CHINH DINH |
| Hydrant and Access approval | Cleared | 12/2/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/27/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 10/4/2021 | Corrections Issued | JOHN KLARIN |
| METHANE-Subgrade | 10/8/2021 | Approved | JOHN KLARIN |
| Pre-Inspection | 10/8/2021 | Approved | JOHN KLARIN |
| Deputy Methane Barrier | 10/20/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 10/21/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 10/29/2021 | Approved | JOHN KLARIN |
| Wood Frame | 12/1/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Rough | 2/3/2022 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 2/10/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/11/2022 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 2/11/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 2/11/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 2/11/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 2/11/2022 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 2/11/2022 | Approved | EUGENE CASSIDY |
| Insulation | 3/7/2022 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/10/2022 | Approved | EUGENE CASSIDY |
| Insulation | 3/10/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/17/2022 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 3/17/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/21/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/25/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 3/25/2022 | Approved | EUGENE CASSIDY |
| Final | 7/18/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/18/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 7/18/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 7/18/2022 | Approved | EUGENE CASSIDY |
| Final | 7/25/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/25/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 7/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/29/2022 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 7/29/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/18/2022 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 8/18/2022 | Not Required | EUGENE CASSIDY |
| Final | 10/14/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/2/2022 | Approved | EUGENE CASSIDY |
| Final | 11/2/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 11/2/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 11/2/2022 | Approved | EUGENE CASSIDY |
| Final | 11/23/2022 | OK to Issue CofO | EUGENE CASSIDY |