13643-13643 1/2 N FELLOWS AVE 91342
Certificate Information: 13643-13643 1/2 N FELLOWS AVE 91342
- Application / Permit
- 20010-10000-02228
- Plan Check / Job No.
- B20LA11617
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX "BUILDING C2-1" WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 6/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | DANIEL YIP |
| Corrections Issued | 10/7/2020 | DANIEL YIP |
| Quality Review Completed | 10/16/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 10/23/2020 | APPLICANT |
| Applicant returned to address corrections | 4/16/2021 | DANIEL YIP |
| Plan Check Approved | 5/24/2022 | DANIEL YIP |
| Issued | 6/2/2022 | APPLICANT |
| CofO in Progress | 5/8/2026 | JEFFREY PARD |
| Permit Finaled | 5/8/2026 | JOHN JANSON |
| CofO Issued | 5/8/2026 | JOHN JANSON |
| Permit Finaled | 5/8/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2021 | HOWARD COOPER |
| Frnt yard landscape/Water mgmt | Cleared | 3/16/2021 | LAUREN PADICK |
| Opn space landscape/Water mgmt | Cleared | 3/16/2021 | LAUREN PADICK |
| Prkng lot landscape/Water mgmt | Cleared | 3/16/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/8/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 6/28/2021 | KURT CORRAL |
| Trees in Parkway | Cleared | 7/12/2021 | DANIEL YIP |
| Low Impact Development | Cleared | 3/30/2022 | JORGE MEJIA LEMUS |
| Highway dedication | Cleared | 5/13/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/30/2022 | Corrections Issued | JEFFREY PARD |
| Underground Mechanical | 9/6/2022 | Partial Approval | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 9/23/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 9/23/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/6/2023 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 3/6/2023 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 3/6/2023 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Partial Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | JEFFREY PARD |
| Insulation | 6/22/2023 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 6/29/2023 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 8/4/2023 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 8/7/2023 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 8/9/2023 | Approved | JEFFREY PARD |
| HVAC-Rough | 8/15/2023 | Approved | JEFFREY PARD |
| Insulation | 8/15/2023 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 8/15/2023 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | JEFFREY PARD |
| Green Building Rough | 8/16/2023 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 8/16/2023 | Approved | JEFFREY PARD |
| Drywall Nailing | 8/17/2023 | Partial Approval | JEFFREY PARD |
| Interior/Exterior Lathing | 8/29/2023 | Approved | JEFFREY PARD |
| Drywall Nailing | 8/31/2023 | Approved | JEFFREY PARD |
| Gas Test | 3/7/2024 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 4/3/2024 | Not Ready for Inspection | HENRY KIM |
| Final | 4/3/2024 | Not Ready for Inspection | HENRY KIM |
| Green Building Final | 4/3/2024 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 4/3/2024 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Final | 4/3/2024 | Not Ready for Inspection | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Not Ready | HENRY KIM |
| Service/Power Release | 4/3/2024 | Not Ready for Inspection | HENRY KIM |
| Smoke Detectors | 4/3/2024 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Final | 5/22/2024 | Partial Approval | JEFFREY PARD |
| PLUMBING-Final | 5/22/2024 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Final | 5/29/2024 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 5/29/2024 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 6/7/2024 | Approved | JEFFREY PARD |
| PLUMBING-Final | 6/7/2024 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Final | 6/24/2024 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 5/7/2025 | Approved | JEFFREY PARD |
| Service/Power Release | 5/7/2025 | Approved | JEFFREY PARD |
| HVAC-Final | 10/20/2025 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Approved | JEFFREY PARD |
| Final | 10/30/2025 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 10/30/2025 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 10/30/2025 | Approved | JEFFREY PARD |
| Final | 11/21/2025 | Partial Approval | JEFFREY PARD |
| Green Building Final | 11/21/2025 | Approved | JEFFREY PARD |
| Final | 5/5/2026 | OK to Issue CofO | JEFFREY PARD |