6021 N ENSIGN AVE 91606

Certificate Information: 6021 N ENSIGN AVE 91606

Application / Permit
20010-10000-02200
Plan Check / Job No.
B20LA11485
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ADU PER ORDINANCE 186481
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 STARR CHEN
Corrections Issued 7/26/2020 STARR CHEN
Quality Review Completed 8/14/2020 HERNAN ARREOLA
Building Plans Picked Up 8/24/2020 APPLICANT
Applicant returned to address corrections 11/16/2020 STARR CHEN
Applicant returned to address corrections 12/10/2020 STARR CHEN
Applicant returned to address corrections 1/12/2021 STARR CHEN
Plan Check Approved 2/10/2021 STARR CHEN
Issued 2/10/2021 APPLICANT
CofO in Progress 11/16/2021 DANIEL DREW
Permit Finaled 2/17/2022 RONALD MYRICK
CofO Issued 2/17/2022 RONALD MYRICK
Permit Finaled 2/17/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 9/22/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/23/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/23/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 10/2/2020 MATTHEW CRAIG
Construction near power lines Cleared 12/14/2020 RIDWAN HARDY
Low Impact Development Cleared 12/18/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/9/2021 ADRIAN CASTRO

Contact Information

Contractor Sarmiento Construction; Lic. No.: 819153-B 13012 WELBY WAY      NORTH HOLLYWOOD, CA 91606
Engineer Chan,, Albert Fong; Lic. No.: C61343 2261 PEPPERWOOD LN      CORONA, CA 92882

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/23/2021 Approved DANIEL DREW
Sewer 3/23/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Order to Comply Issued DANIEL DREW
Underground Mechanical 4/30/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 5/6/2021 Not Ready for Inspection DANIEL DREW
Green Building Rough 5/6/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 5/6/2021 Approved DANIEL DREW
PLUMBING-Rough 5/6/2021 Approved DANIEL DREW
Verify Sprinkler Sign Off 5/6/2021 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 6/16/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 6/16/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 6/16/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 6/16/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/22/2021 Approved DANIEL DREW
ELECTRICAL-Rough 6/22/2021 Approved DANIEL DREW
Green Building Rough 6/22/2021 Approved DANIEL DREW
Interior/Exterior Lathing 6/22/2021 Approved DANIEL DREW
Insulation 6/28/2021 Approved DANIEL DREW
Drywall Nailing 6/30/2021 Approved DANIEL DREW
ELECTRICAL-Final 11/16/2021 Approved DANIEL DREW
Final 11/16/2021 OK to Issue CofO DANIEL DREW
Green Building Final 11/16/2021 Approved DANIEL DREW
HVAC-Final 11/16/2021 Approved DANIEL DREW
PLUMBING-Final 11/16/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV Approved DANIEL DREW
Service/Power Release 11/16/2021 Approved DANIEL DREW
Smoke Detectors 11/16/2021 Approved DANIEL DREW
ELECTRICAL-Final 11/22/2021 No Access for Inspection MATT KELLERMAN
HVAC-Final 11/22/2021 No Access for Inspection MATT KELLERMAN
PLUMBING-Final 11/22/2021 No Access for Inspection MATT KELLERMAN