2001 S CRESCENT AVE 90731

Certificate Information: 2001 S CRESCENT AVE 90731

Application / Permit
20010-10000-02174
Plan Check / Job No.
B20LA11370
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
PROPOSED 2 STORY OFFICE BUILDING WITH ATTACHED 1-CAR GARAGE PER DIR-2018-4279-CDP
Permit Issued
Issued on 9/26/2022
Issuing Office
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 ARMEN JIVALAGIAN
Corrections Issued 7/28/2020 ARMEN JIVALAGIAN
Quality Review Completed 7/30/2020 CHAD DOI
Building Plans Picked Up 8/6/2020 APPLICANT
Disabled Access Plans Picked Up 8/18/2020 APPLICANT
Applicant returned to address corrections 10/16/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 6/25/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/19/2022 ARMEN JIVALAGIAN
Green Plans Picked Up 3/29/2022 APPLICANT
Applicant returned to address corrections 4/12/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 5/3/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 5/11/2022 ARMEN JIVALAGIAN
Plan Check Approved 6/2/2022 ARMEN JIVALAGIAN
Issued 9/26/2022 APPLICANT
Permit Finaled 9/16/2025 ERNESTO CORRAL
CofO Issued 9/16/2025 ERNESTO CORRAL
Permit Finaled 9/16/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 10/5/2020 ERIK BEASLEY
Community Plan Implem. Overlay Cleared 10/5/2020 ERIK BEASLEY
Community Plan Implem. Overlay Cleared 10/5/2020 WESTON PRINGLE
Permit Cleared 10/5/2020 ERIK BEASLEY
Hydrant and Access approval Cleared 12/10/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 12/14/2020 ERIK BEASLEY
Highway dedication Cleared 12/14/2020 ERIK BEASLEY
Sewer availability Cleared 12/14/2020 ERIK BEASLEY
Community Plan Implem. Overlay Cleared 1/20/2021 RIDWAN HARDY
Green Code Cleared 1/26/2021 ARMEN JIVALAGIAN
Low Impact Development Cleared 2/1/2021 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 2/4/2021 ERIK BEASLEY
Historic Resource Verification Cleared 2/17/2021 GRACIELA ACOSTA
Redevelopment Project Area Cleared 2/17/2021 GRACIELA ACOSTA
Coastal Zone Cleared 12/14/2021 ANNA VIDAL
Miscellaneous Cleared 12/14/2021 ANNA VIDAL
Specific Plan Cleared 12/14/2021 ANNA VIDAL
Community Plan Implem. Overlay Cleared 1/7/2022 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 3/17/2022 NORALI MARTINEZ
Comm Cor/Mini-Mall Cleared 3/31/2022 ANNA VIDAL
Comm Cor/Mini-Mall Cleared 3/31/2022 ANNA VIDAL
DAS Clearance Cleared 4/24/2022 ARMEN JIVALAGIAN
Comm Cor/Mini-Mall Cleared 5/5/2022 ANNA VIDAL

Contact Information

Contractor Bay Properties Development Corp; Lic. No.: 946206-B 21111 VICTOR ST      TORRANCE, CA 90503
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/12/2022 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 11/30/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 12/6/2022 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 12/9/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 2/1/2023 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 2/2/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Conditional Approval JOEY BUCHANAN
Interior/Exterior Lathing 7/5/2023 Approved AMANUEL BERHE
Green Building Rough 7/11/2023 Approved DAVID TSAU
Verify Sprinkler Sign Off 7/11/2023 Partial Approval DAVID TSAU
Wood Frame 7/11/2023 Partial Approval DAVID TSAU
Verify Sprinkler Sign Off 7/20/2023 Approved JOEY BUCHANAN
Wood Frame 7/20/2023 Approved JOEY BUCHANAN
Insulation 7/27/2023 Approved DAVID TSAU
Drywall Nailing 8/8/2023 Approved JOEY BUCHANAN
Piling/Pier/Caisson 11/14/2023 Approved JOEY BUCHANAN
Reinforced Masonry Frame 11/14/2023 Approved JOEY BUCHANAN
Final 4/11/2024 Corrections Issued JOEY BUCHANAN
Footing/Foundation/Slab 4/11/2024 Approved JOEY BUCHANAN
Green Building Final 4/11/2024 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 4/11/2024 Approved JOEY BUCHANAN
Final 5/16/2024 Conditional Approval JOEY BUCHANAN
Special/Order Compliance 1/29/2025 Corrections Issued JOEY BUCHANAN