425 S TOWNE AVE 90013

Certificate Information: 425 S TOWNE AVE 90013

Application / Permit
20010-10000-02169
Plan Check / Job No.
B20LA11342
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 7 STORY, 175-UNIT 100% AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORIES OF TYPE IIIA APARTMENT OVER 1 STORY TYPE IA APARTMENT OVER 1 STORY TYPE IA COMMERCIAL OVER 1 LEVEL TYPE IA SUBTERRENEAN PARKING. PROJECT UTILIZES INCENTIVES PER TOC LAMC 12.22A.31 ***CofO will not be issued until Tract Map Condition is met***
Permit Issued
Issued on 4/27/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 3/29/2023 VU NGUYEN
Issued 4/27/2023 APPLICANT
TCO Issued (Expire Date: 01-25-2026) 7/29/2025 ERNESTO CORRAL
Permit Finaled 1/23/2026 ERNESTO CORRAL
CofO Issued 1/23/2026 ERNESTO CORRAL
Permit Finaled 1/23/2026 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 3/21/2022 MAX LODER
Address approval Cleared 4/4/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 4/19/2022 JEANETTE VONG
Highway dedication Cleared 4/19/2022 JEANETTE VONG
Trees in Parkway Cleared 5/19/2022 ADALBERTO VERA
Construction near power lines Cleared 6/14/2022 RIDWAN HARDY
Bicycle Parking Cleared 6/30/2022 JEREMY CHOK
"D" conditions Cleared 8/22/2022 NELSON RODRIGUEZ
CPC Cleared 8/22/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 8/22/2022 NELSON RODRIGUEZ
Opn space landscape/Water mgmt Cleared 8/22/2022 NELSON RODRIGUEZ
Site Plan review Cleared 8/22/2022 NELSON RODRIGUEZ
Building over 36-ft Cleared 8/25/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 8/25/2022 CALOSHA APPROVED
Low Impact Development Cleared 1/10/2023 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/11/2023 WALLIE JONG
Redevelopment Project Area Cleared 1/23/2023 DAVID URITA
Sewer availability Cleared 1/27/2023 JEANETTE VONG
DCP conditions approval Cleared 2/14/2023 NICHOLAS KAWAZOE
Density Bonus 12.22.A.31 Cleared 2/14/2023 NICHOLAS KAWAZOE
Work Adjacent to Public Way Cleared 2/16/2023 KHOUNG LE
Permit Cleared 2/23/2023 EVERARDO SANTOS
CPC Cleared 2/24/2023 NATHAN ROMINE
Hydrant and Access approval Cleared 2/28/2023 LAVEON RIDER
Public Housing Cleared 3/6/2023 GLEN OLIVER
DAS Clearance Cleared 3/8/2023 EUGENE BARBEAU
Green Code Cleared 3/9/2023 AARON COSTA
Fire Marshall Fire Life Safety Cleared 3/22/2023 ANDREW KO

Contact Information

Architect Sehgal,, Vijay K; Lic. No.: C25142 2902 KNOX AVENUE #200      LOS ANGELES, CA 90039
Contractor Benchmark Contractors Inc; Lic. No.: 462263-B 3330 OCEAN PARK BLVD      SANTA MONICA, CA 90405
Engineer Angelov,, Anton Georgiev; Lic. No.: S6342 18980 VENTURA BLVD STE 350      TARZANA, CA 91356
Engineer Knur,, Reinard Thomas; Lic. No.: GE2755 1435 MONCADO DR      GLENDALE, CA 91207

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/23/2023 Partial Inspection NICK DANERI
Footing/Foundation/Slab 8/22/2023 Partial Inspection NICK DANERI
METHANE-Barrier 8/22/2023 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 8/22/2023 Partial Inspection NICK DANERI
Deputy Shotcrete 8/23/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/28/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/31/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/31/2023 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 9/1/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/1/2023 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 9/5/2023 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 9/6/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/7/2023 Conditional Approval NICK DANERI
Deputy Grading 9/8/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/8/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/8/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/12/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/12/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/13/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/14/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 9/15/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/18/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/19/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/20/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/21/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/22/2023 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/26/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/27/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/29/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/2/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/2/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/3/2023 Conditional Approval NICK DANERI
Deputy Grading 10/5/2023 Conditional Approval GREGORY POMISH
Deputy Grading 10/6/2023 Conditional Approval ADAM BURGESS
Deputy Other (see comments) 10/6/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/6/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/6/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/10/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/10/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/11/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/11/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/12/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/12/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/13/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/16/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/17/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 10/17/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/17/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/18/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 10/20/2023 Partial Approval GREGORY POMISH
Special/Order Compliance 10/20/2023 Partial Approval JACOB MYERS
Deputy Reinf. Concrete 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 10/24/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/24/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 10/24/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/24/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/24/2023 Partial Inspection NICK DANERI
Footing/Foundation/Slab 10/24/2023 Not Ready for Inspection NICK DANERI
Deputy Drilled-In Anchors 10/25/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/25/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 10/25/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/25/2023 Conditional Approval NICK DANERI
Masonry Wall/Backfill 10/25/2023 Not Ready for Inspection NICK DANERI
Deputy Drilled-In Anchors 10/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 10/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 10/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 10/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 10/30/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/30/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 10/30/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/30/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/30/2023 Partial Approval NICK DANERI
Masonry Wall/Backfill 10/30/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/31/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 10/31/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/31/2023 Conditional Approval NICK DANERI
Green Building Rough 10/31/2023 Conditional Approval NICK DANERI
Reinforced Concrete Frame 10/31/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 10/31/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 11/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/3/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/3/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 11/3/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 11/3/2023 Partial Approval NICK DANERI
Footing/Foundation/Slab 11/6/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/7/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/9/2023 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 11/9/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/17/2023 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/17/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 11/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 12/1/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/1/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/1/2023 Partial Approval NICK DANERI
Footing/Foundation/Slab 12/1/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/11/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 12/11/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/12/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 12/13/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 12/18/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/18/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/18/2023 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/19/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/19/2023 Conditional Approval NICK DANERI
Deputy Grading 12/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/21/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 12/22/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/26/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/26/2023 Partial Approval NICK DANERI
Green Building Rough 1/2/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 1/2/2024 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 1/2/2024 Not Ready for Inspection NICK DANERI
Deputy Reinf. Masonry 1/3/2024 Conditional Approval NICK DANERI
Masonry Wall/Backfill 1/3/2024 Partial Approval NICK DANERI
Deputy Reinf. Masonry 1/4/2024 Conditional Approval NICK DANERI
Masonry Wall/Backfill 1/4/2024 Partial Approval NICK DANERI
Deputy Reinf. Masonry 1/5/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/8/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 1/8/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/9/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 1/9/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 1/9/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/10/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 1/10/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/16/2024 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/16/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/16/2024 Partial Approval NICK DANERI
Masonry Wall/Backfill 1/16/2024 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 1/17/2024 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/17/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/17/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/18/2024 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/18/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/19/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/19/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/26/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/26/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/29/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/30/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/31/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/2/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/2/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/6/2024 No Access for Inspection NICK DANERI
Deputy Reinf. Concrete 2/8/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/8/2024 Partial Approval NICK DANERI
Footing/Foundation/Slab 2/9/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/13/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/13/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/14/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/20/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/20/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/21/2024 Conditional Approval NICK DANERI
Masonry Wall/Backfill 2/23/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/29/2024 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 2/29/2024 Conditional Approval NICK DANERI
Masonry Wall/Backfill 2/29/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/11/2024 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 3/11/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/14/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/19/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/20/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/21/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/26/2024 Conditional Approval NICK DANERI
Footing/Foundation/Slab 3/26/2024 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 3/27/2024 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/27/2024 Partial Approval NICK DANERI
Footing/Foundation/Slab 4/3/2024 Partial Approval NICK DANERI
Drywall Nailing 4/9/2024 Partial Inspection NICK DANERI
Wall Anchors 4/9/2024 Partial Approval NICK DANERI
Drywall Nailing 4/10/2024 Partial Approval NICK DANERI
Drywall Nailing 4/12/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 4/15/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/18/2024 Partial Approval NICK DANERI
Deputy Wood Construction 4/25/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval NICK DANERI
Deputy Wood Construction 4/26/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Partial Approval NICK DANERI
Deputy Wood Construction 4/29/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval NICK DANERI
Drywall Nailing 5/6/2024 Partial Approval NICK DANERI
Drywall Nailing 5/7/2024 Partial Approval NICK DANERI
Drywall Nailing 5/8/2024 Partial Approval NICK DANERI
Drywall Nailing 5/9/2024 Partial Inspection NICK DANERI
Drywall Nailing 5/13/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Partial Approval NICK DANERI
Deputy Steel/Welding 5/16/2024 Conditional Approval NICK DANERI
Deputy Wood Construction 5/16/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval NICK DANERI
Deputy Wood Construction 5/17/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Inspection NICK DANERI
Special/Order Compliance 5/17/2024 Not Ready for Inspection LUIS CCAMACHO
Special/Order Compliance 5/17/2024 Partial Inspection JEROME BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval NICK DANERI
Drywall Nailing 5/22/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval NICK DANERI
Drywall Nailing 6/5/2024 Partial Inspection NICK DANERI
Drywall Nailing 6/6/2024 Partial Approval NICK DANERI
Insulation 6/7/2024 Not Ready for Inspection NICK DANERI
Deputy Wood Construction 6/10/2024 Conditional Approval NICK DANERI
Insulation 6/10/2024 Partial Approval NICK DANERI
Drywall Nailing 6/11/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval NICK DANERI
Deputy Wood Construction 6/12/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 6/12/2024 Not Ready for Inspection LUIS CCAMACHO
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Partial Approval LUIS CCAMACHO
Wood Frame 6/12/2024 Partial Approval LUIS CCAMACHO
Deputy Wood Construction 6/13/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 6/13/2024 Partial Approval NICK DANERI
Deputy Wood Construction 6/17/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 6/17/2024 Partial Approval NICK DANERI
Deputy Wood Construction 6/18/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Partial Approval NICK DANERI
Deputy Steel/Welding 6/20/2024 Conditional Approval NICK DANERI
Deputy Wood Construction 6/20/2024 Conditional Approval NICK DANERI
Drywall Nailing 6/20/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval NICK DANERI
Deputy Steel/Welding 6/21/2024 Conditional Approval NICK DANERI
Deputy Wood Construction 6/21/2024 Conditional Approval NICK DANERI
Drywall Nailing 6/21/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Partial Approval NICK DANERI
Deputy Wood Construction 6/24/2024 Conditional Approval NICK DANERI
Drywall Nailing 6/24/2024 Partial Approval NICK DANERI
Deputy Wood Construction 6/25/2024 Conditional Approval NICK DANERI
Drywall Nailing 6/25/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval NICK DANERI
Deputy Wood Construction 6/26/2024 Conditional Approval NICK DANERI
Drywall Nailing 6/26/2024 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Partial Approval NICK DANERI
Drywall Nailing 6/27/2024 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Partial Approval NICK DANERI
Drywall Nailing 7/2/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval NICK DANERI
Insulation 7/2/2024 Partial Approval NICK DANERI
Drywall Nailing 7/9/2024 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Approval LARRY ARNICK
Deputy Wood Construction 7/10/2024 Conditional Approval NICK DANERI
Drywall Nailing 7/10/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval NICK DANERI
Deputy Wood Construction 7/15/2024 Conditional Approval NICK DANERI
Drywall Nailing 7/15/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval NICK DANERI
Deputy Wood Construction 7/16/2024 Conditional Approval NICK DANERI
Drywall Nailing 7/16/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Partial Approval NICK DANERI
Deputy Wood Construction 7/17/2024 Conditional Approval NICK DANERI
Drywall Nailing 7/17/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval NICK DANERI
Drywall Nailing 7/18/2024 Not Ready for Inspection LUIS CCAMACHO
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Partial Approval LUIS CCAMACHO
Deputy Wood Construction 7/25/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval NICK DANERI
Deputy Wood Construction 7/26/2024 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 7/29/2024 Conditional Approval NICK DANERI
Drywall Nailing 7/29/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval NICK DANERI
Insulation 7/30/2024 Partial Approval NICK DANERI
Wood Frame 7/30/2024 Partial Approval NICK DANERI
Deputy Wood Construction 7/31/2024 Conditional Approval NICK DANERI
Drywall Nailing 7/31/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval NICK DANERI
Insulation 7/31/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/1/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/2/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Partial Approval NICK DANERI
Insulation 8/2/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/6/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/6/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval NICK DANERI
Insulation 8/6/2024 Partial Approval NICK DANERI
Drywall Nailing 8/7/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval NICK DANERI
Insulation 8/7/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/9/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/9/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Inspection NICK DANERI
Insulation 8/9/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/12/2024 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 8/12/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Partial Approval NICK DANERI
Insulation 8/12/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/13/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/13/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Partial Approval NICK DANERI
Insulation 8/13/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/14/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/14/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Partial Approval NICK DANERI
Insulation 8/14/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/15/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/15/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Approval NICK DANERI
Insulation 8/15/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/16/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/16/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval NICK DANERI
Insulation 8/16/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/20/2024 Conditional Approval NICK DANERI
Drywall Nailing 8/20/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Partial Approval NICK DANERI
Insulation 8/20/2024 Partial Approval NICK DANERI
Drywall Nailing 8/21/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Partial Approval NICK DANERI
Insulation 8/21/2024 Partial Approval NICK DANERI
Drywall Nailing 8/26/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Conditional Approval NICK DANERI
Insulation 8/26/2024 Partial Approval NICK DANERI
Drywall Nailing 8/27/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Partial Inspection NICK DANERI
Insulation 8/27/2024 Partial Approval NICK DANERI
Drywall Nailing 8/28/2024 Partial Approval NICK DANERI
Insulation 8/28/2024 Partial Approval NICK DANERI
Drywall Nailing 8/29/2024 Partial Approval LUIS CCAMACHO
Insulation 8/29/2024 Partial Approval LUIS CCAMACHO
Wood Frame 8/29/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 9/4/2024 Partial Approval LUIS CCAMACHO
Insulation 9/4/2024 Partial Approval LUIS CCAMACHO
Wood Frame 9/4/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 9/5/2024 Partial Approval NICK DANERI
Wall Anchors 9/5/2024 Partial Approval NICK DANERI
Wood Frame 9/5/2024 Partial Approval NICK DANERI
Drywall Nailing 9/6/2024 Partial Approval NICK DANERI
Insulation 9/6/2024 Partial Approval NICK DANERI
Wood Frame 9/6/2024 Conditional Approval NICK DANERI
Drywall Nailing 9/9/2024 Partial Approval NICK DANERI
Insulation 9/9/2024 Partial Approval NICK DANERI
Drywall Nailing 9/10/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/10/2024 Partial Approval NICK DANERI
Insulation 9/10/2024 Partial Approval NICK DANERI
Drywall Nailing 9/11/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/11/2024 Not Ready for Inspection NICK DANERI
Insulation 9/11/2024 Partial Approval NICK DANERI
Drywall Nailing 9/12/2024 Partial Approval NICK DANERI
Insulation 9/12/2024 Partial Approval NICK DANERI
Drywall Nailing 9/13/2024 Partial Approval NICK DANERI
Insulation 9/13/2024 Partial Approval NICK DANERI
Drywall Nailing 9/17/2024 Partial Approval NICK DANERI
Insulation 9/17/2024 Partial Approval NICK DANERI
Drywall Nailing 9/18/2024 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 9/18/2024 Partial Approval NICK DANERI
Insulation 9/18/2024 Partial Approval NICK DANERI
Drywall Nailing 9/19/2024 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 9/19/2024 Not Ready for Inspection GREGORY POMISH
Insulation 9/19/2024 Partial Inspection GREGORY POMISH
Drywall Nailing 9/20/2024 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Approval RAFAEL CORTES
Insulation 9/20/2024 Not Ready for Inspection RAFAEL CORTES
Deputy Reinf. Concrete 9/23/2024 Conditional Approval NICK DANERI
Drywall Nailing 9/23/2024 Partial Approval NICK DANERI
Insulation 9/23/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 9/23/2024 Conditional Approval NICK DANERI
Drywall Nailing 9/24/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 9/24/2024 Partial Approval NICK DANERI
Drywall Nailing 9/25/2024 Partial Approval NICK DANERI
Insulation 9/25/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 9/25/2024 Partial Approval NICK DANERI
Drywall Nailing 9/26/2024 Conditional Approval NICK DANERI
Insulation 9/26/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 9/26/2024 Partial Approval NICK DANERI
Drywall Nailing 9/27/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 9/27/2024 Partial Approval NICK DANERI
Drywall Nailing 10/1/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/1/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/2/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 10/2/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/3/2024 Partial Inspection NICK DANERI
Insulation 10/3/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/3/2024 Partial Approval NICK DANERI
Drywall Nailing 10/4/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 10/4/2024 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 10/4/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/7/2024 Partial Approval NICK DANERI
Insulation 10/7/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 10/7/2024 Partial Approval NICK DANERI
Wood Frame 10/7/2024 Partial Inspection NICK DANERI
Drywall Nailing 10/8/2024 Partial Approval NICK DANERI
Insulation 10/8/2024 Partial Approval NICK DANERI
Drywall Nailing 10/9/2024 Partial Approval NICK DANERI
Insulation 10/9/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/9/2024 Partial Approval NICK DANERI
Drywall Nailing 10/10/2024 Partial Approval NICK DANERI
Insulation 10/10/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/10/2024 Not Ready for Inspection NICK DANERI
Wood Frame 10/10/2024 Partial Approval NICK DANERI
Drywall Nailing 10/11/2024 Partial Approval NICK DANERI
Insulation 10/11/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/11/2024 Partial Approval NICK DANERI
Drywall Nailing 10/15/2024 Partial Approval NICK DANERI
Insulation 10/15/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/15/2024 Partial Approval NICK DANERI
Drywall Nailing 10/16/2024 Partial Approval NICK DANERI
Insulation 10/16/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 10/16/2024 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 10/16/2024 Partial Inspection NICK DANERI
Deputy Steel/Welding 10/17/2024 Conditional Approval NICK DANERI
Drywall Nailing 10/17/2024 Partial Inspection NICK DANERI
Insulation 10/17/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/17/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 10/17/2024 Partial Inspection NICK DANERI
Drywall Nailing 10/21/2024 Partial Inspection NICK DANERI
Insulation 10/21/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 10/21/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/21/2024 Partial Approval NICK DANERI
Insulation 10/22/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 10/22/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/22/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/23/2024 Conditional Approval NICK DANERI
Drywall Nailing 10/23/2024 Partial Approval NICK DANERI
Insulation 10/23/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 10/23/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/23/2024 Partial Approval NICK DANERI
Drywall Nailing 10/25/2024 Partial Approval NICK DANERI
Insulation 10/25/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/25/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 10/25/2024 Partial Approval NICK DANERI
Drywall Nailing 10/30/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 10/30/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 10/30/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 10/30/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 10/31/2024 Not Ready for Inspection LARRY ARNICK
Insulation 10/31/2024 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 10/31/2024 Partial Approval LARRY ARNICK
Wood Frame 10/31/2024 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 11/1/2024 Partial Inspection NICK DANERI
Insulation 11/1/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 11/1/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 11/1/2024 Partial Approval NICK DANERI
Drywall Nailing 11/4/2024 Partial Approval NICK DANERI
Insulation 11/4/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 11/4/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 11/4/2024 Partial Approval NICK DANERI
Wood Frame 11/5/2024 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/6/2024 Conditional Approval NICK DANERI
Drywall Nailing 11/6/2024 Partial Approval NICK DANERI
Insulation 11/6/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 11/6/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 11/6/2024 Partial Approval NICK DANERI
Drywall Nailing 11/7/2024 Partial Approval NICK DANERI
Insulation 11/7/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 11/7/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 11/7/2024 Partial Approval NICK DANERI
Drywall Nailing 11/8/2024 Partial Approval NICK DANERI
Insulation 11/8/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 11/8/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 11/8/2024 Partial Approval NICK DANERI
Drywall Nailing 11/13/2024 Partial Approval NICK DANERI
Insulation 11/13/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 11/13/2024 Partial Approval NICK DANERI
Drywall Nailing 11/15/2024 Partial Approval RONALD JIMENEZ
Insulation 11/15/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 11/15/2024 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 11/15/2024 Not Ready for Inspection RONALD JIMENEZ
Drywall Nailing 11/18/2024 Not Ready for Inspection RAFAEL CORTES
Insulation 11/18/2024 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 11/18/2024 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 11/18/2024 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 11/19/2024 Partial Approval NICK DANERI
Insulation 11/19/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 11/19/2024 Partial Approval NICK DANERI
Drywall Nailing 11/20/2024 Partial Approval NICK DANERI
Insulation 11/20/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 11/20/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 11/20/2024 Partial Approval NICK DANERI
Drywall Nailing 11/21/2024 Partial Approval NICK DANERI
Insulation 11/21/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 11/21/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 11/21/2024 Partial Approval NICK DANERI
Wood Frame 11/21/2024 Partial Approval NICK DANERI
Drywall Nailing 11/26/2024 Partial Approval NICK DANERI
Insulation 11/26/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 11/26/2024 Partial Approval NICK DANERI
Drywall Nailing 11/27/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 11/27/2024 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/4/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/4/2024 Partial Approval NICK DANERI
Insulation 12/4/2024 Conditional Approval NICK DANERI
Interior/Exterior Lathing 12/4/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 12/4/2024 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/5/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/5/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 12/5/2024 Partial Approval NICK DANERI
Drywall Nailing 12/9/2024 Not Ready for Inspection NICK DANERI
Insulation 12/9/2024 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 12/9/2024 Not Ready for Inspection NICK DANERI
Deputy Fireproofing 12/10/2024 Conditional Approval NICK DANERI
Wood Frame 12/10/2024 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/12/2024 Conditional Approval NICK DANERI
Deputy Fireproofing 12/12/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/12/2024 Partial Inspection NICK DANERI
Insulation 12/12/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/12/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 12/12/2024 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/13/2024 Conditional Approval NICK DANERI
Deputy Fireproofing 12/13/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/13/2024 Partial Approval NICK DANERI
Green Building Rough 12/13/2024 Partial Inspection NICK DANERI
Insulation 12/13/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 12/13/2024 Partial Approval NICK DANERI
Piling/Pier/Caisson 12/13/2024 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 12/13/2024 Partial Inspection NICK DANERI
Wood Frame 12/13/2024 Partial Inspection NICK DANERI
Deputy Fireproofing 12/17/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/17/2024 Partial Approval NICK DANERI
Insulation 12/17/2024 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 12/17/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 12/17/2024 Conditional Approval NICK DANERI
Deputy Fireproofing 12/19/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/19/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/19/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 12/19/2024 Partial Approval NICK DANERI
Deputy Fireproofing 12/24/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/24/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/24/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 12/24/2024 Partial Approval NICK DANERI
Deputy Fireproofing 12/31/2024 Conditional Approval NICK DANERI
Drywall Nailing 12/31/2024 Partial Approval NICK DANERI
Insulation 12/31/2024 Partial Inspection NICK DANERI
Light Gage Steel Frame 12/31/2024 Partial Approval NICK DANERI
Drywall Nailing 1/6/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 1/6/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 1/6/2025 Partial Inspection NICK DANERI
Drywall Nailing 1/10/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 1/10/2025 Partial Inspection NICK DANERI
Light Gage Steel Frame 1/10/2025 Partial Approval NICK DANERI
Drywall Nailing 1/15/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 1/15/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 1/15/2025 Partial Approval NICK DANERI
Drywall Nailing 1/21/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 1/21/2025 Partial Inspection NICK DANERI
Light Gage Steel Frame 1/21/2025 Partial Approval NICK DANERI
Drywall Nailing 1/24/2025 Partial Approval NICK DANERI
Insulation 1/24/2025 Partial Inspection NICK DANERI
Interior/Exterior Lathing 1/24/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 1/24/2025 Conditional Approval NICK DANERI
Drywall Nailing 1/28/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 1/28/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 1/28/2025 Partial Approval NICK DANERI
Drywall Nailing 1/29/2025 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 1/29/2025 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 1/29/2025 Not Ready for Inspection JEFFREY FULTON
Insulation 1/30/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 1/30/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 1/30/2025 Partial Approval NICK DANERI
Insulation 1/31/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 1/31/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 1/31/2025 Partial Approval NICK DANERI
Drywall Nailing 2/3/2025 Partial Approval NICK DANERI
Insulation 2/3/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/3/2025 Partial Approval NICK DANERI
Drywall Nailing 2/4/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/4/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 2/4/2025 Conditional Approval NICK DANERI
Drywall Nailing 2/5/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/5/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 2/5/2025 Partial Approval NICK DANERI
Drywall Nailing 2/7/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/7/2025 Partial Inspection NICK DANERI
Light Gage Steel Frame 2/7/2025 Partial Approval NICK DANERI
Drywall Nailing 2/11/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/11/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 2/11/2025 Conditional Approval NICK DANERI
Drywall Nailing 2/13/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/13/2025 Not Ready for Inspection NICK DANERI
Wood Frame 2/13/2025 Conditional Approval NICK DANERI
Drywall Nailing 2/14/2025 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/14/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/14/2025 Partial Approval NICK DANERI
Drywall Nailing 2/18/2025 Partial Approval NICK DANERI
Insulation 2/18/2025 Partial Inspection NICK DANERI
Drywall Nailing 2/25/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/25/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 2/25/2025 Partial Inspection NICK DANERI
Drywall Nailing 3/17/2025 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 3/17/2025 Partial Approval NICK DANERI
Drywall Nailing 3/25/2025 Corrections Issued NICK DANERI
Masonry Wall/Backfill 3/25/2025 Partial Inspection NICK DANERI
Footing/Foundation/Slab 4/1/2025 Partial Inspection NICK DANERI
Masonry Wall/Backfill 4/3/2025 Partial Approval NICK DANERI
Drywall Nailing 4/10/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 4/10/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/11/2025 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 4/11/2025 Not Ready for Inspection RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 4/14/2025 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 4/14/2025 Partial Approval LARRY ARNICK
Drywall Nailing 4/15/2025 Partial Approval NICK DANERI
Light Gage Steel Frame 4/15/2025 Partial Approval NICK DANERI
Deputy Reinf. Masonry 4/17/2025 Conditional Approval NICK DANERI
Masonry Wall/Backfill 4/17/2025 Partial Approval NICK DANERI
Special/Order Compliance 5/19/2025 Partial Inspection NICK DANERI
Final 5/21/2025 Partial Inspection NICK DANERI
Footing/Foundation/Slab 5/21/2025 Approved NICK DANERI
Green Building Final 5/21/2025 Not Ready for Inspection NICK DANERI
Green Building Rough 5/21/2025 Approved NICK DANERI
Reinforced Concrete Frame 5/21/2025 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 5/21/2025 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Not Ready NICK DANERI
Smoke Detectors 5/21/2025 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 5/21/2025 Not Ready for Inspection NICK DANERI
Pre-Inspection 5/28/2025 Corrections Issued NICK DANERI
Final 6/9/2025 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 6/9/2025 Approved JOEY BUCHANAN
Reinforced Concrete Frame 6/9/2025 Approved JOEY BUCHANAN
Reinforced Masonry Frame 6/9/2025 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 6/9/2025 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 6/9/2025 Approved JOEY BUCHANAN
Final 6/18/2025 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 6/27/2025 Conditional Approval JOEY BUCHANAN
Final 7/17/2025 Conditional Approval JOEY BUCHANAN
Final 7/28/2025 OK for TCO JOEY BUCHANAN
Special/Order Compliance 1/6/2026 Approved JOEY BUCHANAN