11015 N SEPULVEDA BLVD 91345
Certificate Information: 11015 N SEPULVEDA BLVD 91345
- Application / Permit
- 20010-10000-02146
- Plan Check / Job No.
- B20LA11175
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CONSTRUCTION OF A (N) RESTAURANT W/ AN INDOOR PLAY-PLACE, EXT BLDG CANOPIES, AND DUAL ORDER POINTE DRIVE-THRU
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 9/18/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/29/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 3/17/2021 | SERGIO GUTIERREZ |
| Green Plans Picked Up | 8/17/2021 | APPLICANT |
| Applicant returned to address corrections | 1/13/2022 | SERGIO GUTIERREZ |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Plan Check Approved | 5/11/2022 | SERGIO GUTIERREZ |
| Issued | 5/23/2022 | APPLICANT |
| TCO Issued (Expire Date: 04-30-2024) | 11/2/2023 | RICKEY JACKSON |
| CofO in Progress | 3/7/2024 | DANNY RODRIGUEZ |
| Permit Finaled | 3/19/2024 | RICKEY JACKSON |
| CofO Issued | 3/19/2024 | RICKEY JACKSON |
| Permit Finaled | 3/19/2024 | RICKEY JACKSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/11/2021 | IDA MEISAMI-FARD |
| Stormwater Pollution Mitigatn | Cleared | 10/11/2021 | IDA MEISAMI-FARD |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/13/2021 | GABRIEL ROBLES |
| Permit | Cleared | 10/20/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 10/20/2021 | GABRIEL ROBLES |
| Highway dedication | Cleared | 11/15/2021 | CARLOS AGUILERA |
| Drive-through fast food | Cleared | 1/20/2022 | ANACANY HURTADO |
| Fire Marshall Fire Life Safety | Cleared | 1/20/2022 | VIDAL GARCIA |
| Frnt yard landscape/Water mgmt | Cleared | 1/20/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/20/2022 | ANACANY HURTADO |
| Prkng lot landscape/Water mgmt | Cleared | 1/20/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/20/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/20/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/20/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/20/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/20/2022 | ANACANY HURTADO |
| Hydrant and Access approval | Cleared | 2/19/2022 | KURT CORRAL |
| Green Code | Cleared | 2/22/2022 | KHEDER ALRAZAA |
| Food Service Establishment | Cleared | 3/1/2022 | KENNETH BROWNE |
| DAS Clearance | Cleared | 3/21/2022 | SERGIO GUTIERREZ |
| Food establishment approval | Cleared | 5/11/2022 | LACDHS APPROVED |
Contact Information
| Architect | Bickel,, James S; Lic. No.: C20925 | 3600 BIRCH STREET SUITE 120 NEWPORT BEACH, CA 92660 |
| Contractor | C C K Builders Inc; Lic. No.: 855822-B | 625 WEST KATELLA AVENUE #2 ORANGE, CA 92867 |
| Engineer | Lee,, Jin Soo; Lic. No.: C49326 | 4249 WILEY LANE GLENDALE, CA 91214 |
| Engineer | Thompson,, Douglas Sevier; Lic. No.: S2578 | 21084 BAKE PARKWAY SUITE 100 LAKE FOREST, CA 92630 |
| Engineer | Yogeswaran,, Pirathapan; Lic. No.: GE2834 | 915 CARTER ST FOLSOM, CA 95630 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2023 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 2/21/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Wood Construction | 3/2/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 3/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 3/6/2023 | Approved | BRIAN KELLY |
| Verify Sprinkler Sign Off | 3/6/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 3/16/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 3/31/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/31/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Insulation | 4/3/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 4/18/2023 | Partial Inspection | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 4/18/2023 | Partial Inspection | CAMERON CHABAN |
| Wood Frame | 4/18/2023 | Partial Inspection | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/12/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Green Building Rough | 5/12/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/12/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 5/12/2023 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 5/18/2023 | Partial Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Corrections Issued | ANDREW DORSO |
| Deputy Wood Construction | 6/6/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Wood Frame | 6/7/2023 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 6/9/2023 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/9/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 6/9/2023 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 6/12/2023 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/14/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 6/14/2023 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 6/16/2023 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/16/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 6/16/2023 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 6/21/2023 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 6/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Piling/Pier/Caisson | 6/23/2023 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 6/26/2023 | Approved | DANNY RODRIGUEZ |
| Special/Order Compliance | 8/2/2023 | Partial Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 8/4/2023 | Approved | DANNY RODRIGUEZ |
| Deputy Drilled-In Anchors | 8/28/2023 | Conditional Approval | JOHN KITCKO |
| Final | 10/20/2023 | OK to Issue CofO | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/20/2023 | Approved | DANNY RODRIGUEZ |
| Green Building Final | 10/20/2023 | Approved | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/20/2023 | SGSOV Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 10/20/2023 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/20/2023 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 10/20/2023 | Approved | DANNY RODRIGUEZ |