16812 W SAN JOSE ST 91344

Certificate Information: 16812 W SAN JOSE ST 91344

Application / Permit
20010-10000-02120
Plan Check / Job No.
B20LA11044
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2020 APPLICANT
Assigned to Plan Check Engineer 6/24/2020 HELEN NGUYEN
Corrections Issued 6/29/2020 HELEN NGUYEN
Applicant returned to address corrections 7/29/2020 AUNG SOE
Plan Check Approved 1/20/2021 SHANGQIN XIE
Issued 4/13/2021 APPLICANT
Building Plans Picked Up 4/19/2021 APPLICANT
CofO in Progress 1/10/2022 MARK JOHNSON
CofO in Progress 1/14/2022 MICHAEL TEMPLE
CofO in Progress 3/22/2022 MICHAEL SMITH
Permit Finaled 3/22/2022 MICHAEL SMITH
CofO Issued 3/22/2022 MICHAEL SMITH
Permit Finaled 3/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/10/2020 ADRIAN CASTRO
Sewer availability Cleared 7/15/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/16/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Construction near power lines Cleared 10/5/2020 WALTER RAMIREZ
Construction within easement Cleared 10/5/2020 WALTER RAMIREZ
Low Impact Development Cleared 12/21/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/5/2021 ADRIAN CASTRO

Contact Information

Contractor H T A Construction & Development; Lic. No.: 1044038-B 1008 E FREELAND ST      LONG BEACH, CA 90807
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/20/2021 Partial Approval MARK JOHNSON
Underground Mechanical 4/20/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 4/26/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 6/14/2021 Approved MARK JOHNSON
HVAC-Rough 6/14/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 6/14/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Corrections Issued MARK JOHNSON
HVAC-Rough 7/1/2021 Approved MARK JOHNSON
Shower Pan 7/1/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 7/15/2021 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 7/22/2021 Approved MARK JOHNSON
Insulation 8/2/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 8/10/2021 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 8/16/2021 Not Ready for Inspection ADAM ESCOTO
Green Building Rough 8/16/2021 Approved ADAM ESCOTO
Insulation 8/16/2021 Not Ready for Inspection ADAM ESCOTO
Verify Sprinkler Sign Off 8/16/2021 Approved ADAM ESCOTO
BUILDING-Rough-Frame 8/18/2021 Approved MARK JOHNSON
Drywall Nailing 8/18/2021 Approved MARK JOHNSON
Insulation 8/18/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 8/30/2021 Partial Approval ADAM ESCOTO
Underground Mechanical 10/25/2021 Not Ready for Inspection MARK JOHNSON
Sewer 10/27/2021 Approved MARK JOHNSON
Underground Mechanical 10/27/2021 Approved MARK JOHNSON
ELECTRICAL-Final 12/7/2021 Approved MARK JOHNSON
Gas Test 12/7/2021 Approved MARK JOHNSON
HVAC-Final 12/7/2021 Approved MARK JOHNSON
PLUMBING-Final 12/7/2021 Approved MARK JOHNSON
Service/Power Release 12/7/2021 Not Required MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Not Ready MICHAEL TEMPLE
Final 12/17/2021 Corrections Issued MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 1/3/2022 SGSOV Not Ready MARK JOHNSON
Final 1/5/2022 Corrections Issued MARK JOHNSON
Final 1/7/2022 Partial Approval MARK JOHNSON
Green Building Final 1/7/2022 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 1/7/2022 SGSOV Approved MARK JOHNSON
Smoke Detectors 1/7/2022 Approved MARK JOHNSON
Final 1/18/2022 Corrections Issued MARK JOHNSON
Final 3/22/2022 OK to Issue CofO MICHAEL SMITH