4529 W 8TH ST 90005
Certificate Information: 4529 W 8TH ST 90005
- Application / Permit
- 20010-10000-02108
- Plan Check / Job No.
- B20LA10988
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SINGLE FAMILY RESIDENCE WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | STARR CHEN |
| Corrections Issued | 8/19/2020 | STARR CHEN |
| Building Plans Picked Up | 9/25/2020 | APPLICANT |
| Quality Review Completed | 9/30/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/13/2020 | STARR CHEN |
| Applicant returned to address corrections | 12/24/2020 | STARR CHEN |
| Applicant returned to address corrections | 1/29/2021 | STARR CHEN |
| Plan Check Approved | 2/17/2021 | STARR CHEN |
| Issued | 2/23/2021 | APPLICANT |
| CofO in Progress | 9/28/2022 | JEFFREY MEAD |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
| CofO Issued | 12/10/2022 | DEROLD HAUFF |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2020 | CELINA MORENO |
| Permit | Cleared | 10/8/2020 | CELINA MORENO |
| Sewer availability | Cleared | 10/8/2020 | CELINA MORENO |
| ZI | Cleared | 10/14/2020 | CHI DANG |
| Trees in Parkway | Cleared | 10/20/2020 | JOHN KIM |
| Low Impact Development | Cleared | 11/5/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 11/12/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 11/17/2020 | CELINA MORENO |
Contact Information
| Contractor | Philmont Management Inc; Lic. No.: 808686-B | 3450 WILSHIRE BLVD #850 LOS ANGELES, CA 90010 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/7/2021 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 4/7/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 4/22/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 4/22/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 4/22/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Structural Steel Frame | 4/22/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/7/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 5/7/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 5/24/2021 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 5/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/24/2021 | Partial Inspection | CHARLES BOGHOSKHAN |
| Deputy Wood Construction | 6/24/2021 | Approved | CHARLES BOGHOSKHAN |
| Deputy Wood Construction | 8/24/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/25/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 8/25/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 8/25/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 8/25/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/31/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 8/31/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/31/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/16/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 9/16/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/16/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 10/1/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 10/12/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 10/12/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 11/1/2021 | Approved | MASHEL JONGERT |
| Shower Pan | 12/1/2021 | Approved | MASHEL JONGERT |
| Footing/Foundation/Slab | 12/13/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Rough | 12/13/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 12/13/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/14/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 12/14/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 1/12/2022 | Approved | ARTHUR SARGSYAN |
| Grading Pre-Inspection | 3/15/2022 | Partial Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 3/31/2022 | Approved | CRAIG DAVIS |
| Service/Power Release | 3/31/2022 | Approved | CRAIG DAVIS |
| Gas Test | 4/1/2022 | Approved | ADAM ESCOTO |
| HVAC-Final | 4/7/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 4/7/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 4/11/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 4/20/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Final | 5/3/2022 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 5/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 5/6/2022 | Approved | SHAVONNE ESPINOZA |
| Green Building Final | 5/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Smoke Detectors | 5/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Verify Sprinkler Sign Off | 5/6/2022 | Approved | SHAVONNE ESPINOZA |
| Green Building Final | 6/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 7/19/2022 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 7/19/2022 | Partial Approval | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 7/19/2022 | Approved | JEFFREY MEAD |
| Final | 9/13/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 9/13/2022 | Partial Approval | JEFFREY MEAD |
| Final | 9/27/2022 | OK to Issue CofO | JEFFREY MEAD |
| Green Building Final | 9/27/2022 | Approved | JEFFREY MEAD |