5003 S 2ND AVE 90043
Certificate Information: 5003 S 2ND AVE 90043
- Application / Permit
- 20010-10000-02089
- Plan Check / Job No.
- B20LA10889
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU AT REAR OF PROPERTY (see comments). FRAMING PER THE WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 1/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | ALBERT SERVIN |
| Corrections Issued | 7/15/2020 | ALBERT SERVIN |
| Quality Review Completed | 7/21/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 7/27/2020 | APPLICANT |
| Applicant returned to address corrections | 9/9/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 9/14/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 12/21/2020 | ALBERT SERVIN |
| Plan Check Approved | 1/8/2021 | ALBERT SERVIN |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 5/13/2022 | ANTHONY EGSON |
| Permit Finaled | 1/5/2023 | DEROLD HAUFF |
| CofO Issued | 1/5/2023 | DEROLD HAUFF |
| Permit Finaled | 1/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2020 | ELENA LOPEZ |
| Hydrant and Access approval | Cleared | 8/31/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 9/29/2020 | ELENA LOPEZ |
| Green Code | Cleared | 10/16/2020 | ALBERT SERVIN |
| Low Impact Development | Cleared | 12/4/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/10/2020 | ELENA LOPEZ |
| Public Works-Sewers | Cleared | 1/20/2022 | KHOUNG LE |
| Public Works-Open Permits | Cleared | 1/20/2022 | KHOUNG LE |
Contact Information
| Contractor | Tolbert Construction; Lic. No.: 498836-B | PO BOX 44349 LOS ANGELES, CA 90044 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2021 | Corrections Issued | ROBERT MCDOWELL |
| PLUMBING-Rough | 1/27/2021 | Partial Approval | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 2/1/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 2/4/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 2/24/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 3/3/2021 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 5/13/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 6/7/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 6/7/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 6/7/2021 | Partial Approval | DAVID FEILER |
| Sewer | 6/11/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 6/14/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 6/14/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 6/14/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 6/21/2021 | No Access for Inspection | DAVID FEILER |
| HVAC-Rough | 6/25/2021 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 6/25/2021 | Approved | FREDDIE RIVERA |
| Insulation | 6/30/2021 | Corrections Issued | ALFREDO BALANDRA |
| Insulation | 7/2/2021 | Approved | ALFREDO BALANDRA |
| Drywall Nailing | 7/9/2021 | Approved | BENEVA JACKSON |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | ADAM ESCOTO |
| Final | 10/12/2021 | Corrections Issued | ADAM ESCOTO |
| Green Building Final | 10/12/2021 | Approved | ADAM ESCOTO |
| Green Building Rough | 10/12/2021 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | ADAM ESCOTO |
| Service/Power Release | 10/12/2021 | Corrections Issued | ADAM ESCOTO |
| Smoke Detectors | 10/12/2021 | Corrections Issued | ADAM ESCOTO |
| Verify Sprinkler Sign Off | 10/12/2021 | Approved | ADAM ESCOTO |
| Final | 11/30/2021 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV No Gas | ANTHONY EGSON |
| Service/Power Release | 11/30/2021 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 11/30/2021 | Partial Inspection | ANTHONY EGSON |
| Final | 12/6/2021 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 12/6/2021 | Corrections Issued | ANTHONY EGSON |
| Final | 12/15/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Service/Power Release | 12/15/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Smoke Detectors | 12/15/2021 | Conditional Approval | ADAM ESCOTO |
| Final | 12/23/2021 | Not Ready for Inspection | HORACE FULTZ |
| Service/Power Release | 12/23/2021 | Not Ready for Inspection | HORACE FULTZ |
| Smoke Detectors | 12/23/2021 | Partial Approval | HORACE FULTZ |
| Final | 5/3/2022 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 5/3/2022 | Approved | ANTHONY EGSON |
| Smoke Detectors | 5/3/2022 | Approved | ANTHONY EGSON |