148 W 108TH ST 90061
Certificate Information: 148 W 108TH ST 90061
- Application / Permit
- 20010-10000-02077
- Plan Check / Job No.
- B20LA10810
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/11/2021
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/18/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/25/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 2/18/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/4/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 11/3/2021 | MAHNAZ NOURHASHEMI |
| Issued | 12/11/2021 | APPLICANT |
| Building Plans Picked Up | 12/17/2021 | APPLICANT |
| CofO in Progress | 4/12/2023 | JAMES CHAVEZ |
| Permit Finaled | 4/14/2023 | ANSON MAGLASANG |
| CofO Issued | 4/14/2023 | ANSON MAGLASANG |
| Permit Finaled | 4/14/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/26/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 9/13/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/3/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 10/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Total Property Services; Lic. No.: 732965-B | 712 E MANCHESTER BLVD INGLEWOOD, CA 90301 |
| Engineer | Ayroso,, Ananias Maniquis; Lic. No.: S2413 | 12823 BERKHAMSTED ST CERRITOS, CA 90703 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/30/2022 | Corrections Issued | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 4/4/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/4/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 7/28/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/1/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 8/1/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 8/1/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 8/1/2022 | Corrections Issued | JOHN KLARIN |
| Verify Sprinkler Sign Off | 8/1/2022 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 8/9/2022 | Approved | JOHN KLARIN |
| Insulation | 8/12/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/18/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/18/2022 | Approved | JOHN KLARIN |
| Gas Test | 12/23/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Sewer | 12/23/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Underground Mechanical | 12/23/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Gas Test | 12/29/2022 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 12/29/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Sewer | 12/29/2022 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/9/2023 | Conditional Approval | JAMES CHAVEZ |
| ELECTRICAL-Final | 3/9/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 3/9/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 3/9/2023 | Approved | JAMES CHAVEZ |
| HVAC-Final | 3/9/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 3/9/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 3/9/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 3/9/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 3/9/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 3/24/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 3/28/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 4/12/2023 | Approved | JAMES CHAVEZ |
| Final | 4/12/2023 | OK to Issue CofO | JAMES CHAVEZ |