140 W 108TH ST 90061

Certificate Information: 140 W 108TH ST 90061

Application / Permit
20010-10000-02075
Plan Check / Job No.
B20LA10795
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ADU PER 12.22 A33 C & D
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 STARR CHEN
Corrections Issued 7/11/2020 STARR CHEN
Quality Review Completed 7/30/2020 HERNAN ARREOLA
Applicant returned to address corrections 7/12/2021 STARR CHEN
Applicant returned to address corrections 7/30/2021 STARR CHEN
Applicant returned to address corrections 11/19/2021 STARR CHEN
Plan Check Approved 1/10/2022 STARR CHEN
Issued 1/18/2022 APPLICANT
Building Plans Picked Up 1/19/2022 APPLICANT
CofO in Progress 4/7/2023 JAMES CHAVEZ
CofO in Progress 4/12/2023 ANSON MAGLASANG
Permit Finaled 4/14/2023 ANSON MAGLASANG
CofO Issued 4/14/2023 ANSON MAGLASANG
Permit Finaled 4/14/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/27/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 7/28/2021 THOMAS LANG
Sewer availability Cleared 7/28/2021 THOMAS LANG
Low Impact Development Cleared 9/13/2021 CHRIS PARK
Roof/Waste drainage to street Cleared 9/15/2021 THOMAS LANG
Hydrant and Access approval Cleared 10/3/2021 GILBERT URREA
Construction near power lines Cleared 10/20/2021 RIDWAN HARDY

Contact Information

Contractor Total Property Services; Lic. No.: 732965-B 712 E MANCHESTER BLVD      INGLEWOOD, CA 90301
Engineer Ayroso,, Ananias Maniquis; Lic. No.: S2413 12823 BERKHAMSTED ST      CERRITOS, CA 90703

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/30/2022 Corrections Issued ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 4/4/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 4/4/2022 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/12/2022 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 4/18/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval ALIZAH MAYAGOITIA
Deputy Wood Construction 7/28/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/1/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 8/1/2022 Approved JOHN KLARIN
Green Building Rough 8/1/2022 Approved JOHN KLARIN
HVAC-Rough 8/1/2022 Approved JOHN KLARIN
PLUMBING-Rough 8/1/2022 Corrections Issued JOHN KLARIN
Verify Sprinkler Sign Off 8/1/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 8/9/2022 Approved JOHN KLARIN
Insulation 8/12/2022 Approved JOHN KLARIN
Drywall Nailing 8/18/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 8/18/2022 Approved JOHN KLARIN
Gas Test 12/23/2022 Approved JAMES CHAVEZ
Sewer 12/23/2022 Approved JAMES CHAVEZ
Underground Mechanical 12/23/2022 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 3/9/2023 Approved JAMES CHAVEZ
Final 3/9/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 3/9/2023 Approved JAMES CHAVEZ
Green Building Final 3/9/2023 Approved JAMES CHAVEZ
Rough-Elec/Plmb/HVAC 3/9/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 3/9/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 3/9/2023 Approved JAMES CHAVEZ
Verify Sprinkler Sign Off 3/9/2023 Approved JAMES CHAVEZ
Service/Power Release 3/24/2023 Approved JAMES CHAVEZ
Service/Power Release 3/28/2023 Approved JAMES CHAVEZ
Final 4/7/2023 OK to Issue CofO JAMES CHAVEZ
Final 4/12/2023 OK to Issue CofO JAMES CHAVEZ