4308 N MAYCREST AVE 90032
Certificate Information: 4308 N MAYCREST AVE 90032
- Application / Permit
- 20010-10000-02062
- Plan Check / Job No.
- B20LA10696
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER LAMC 12.22A.33 (c).
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/14/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/23/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 7/27/2020 | APPLICANT |
| Applicant returned to address corrections | 5/7/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/10/2021 | MAHNAZ NOURHASHEMI |
| Issued | 6/10/2021 | APPLICANT |
| CofO in Progress | 5/17/2022 | AMY COLIN |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/24/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 11/9/2020 | VASIL MIHALEV |
| Construction near power lines | Cleared | 11/17/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/26/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/26/2021 | JEANIE LAM |
| GPI Written Notices | Cleared | 6/10/2021 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 6/22/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 8/19/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/19/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 8/19/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 8/19/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 8/19/2021 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 8/19/2021 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 8/19/2021 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/27/2021 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 8/27/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/27/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 8/27/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 8/27/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 8/27/2021 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 8/27/2021 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 8/27/2021 | Partial Approval | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/27/2021 | Approved | OSVALDO PARAMO |
| Insulation | 9/2/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 9/16/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/16/2021 | Approved | ALAN MORELOS |
| Shower Pan | 9/16/2021 | Corrections Issued | ALAN MORELOS |
| Shower Pan | 11/5/2021 | Not Ready for Inspection | COREY HUPP |
| Underground Mechanical | 11/5/2021 | Partial Approval | COREY HUPP |
| Shower Pan | 12/15/2021 | Approved | COREY HUPP |
| Underground Mechanical | 12/15/2021 | Approved | COREY HUPP |
| Service/Power Release | 12/20/2021 | Not Ready for Inspection | COREY HUPP |
| Gas Test | 12/30/2021 | Approved | CRAIG VAUGHAN |
| Final | 4/12/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 4/12/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 4/12/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 4/12/2022 | Approved | AMY COLIN |
| Final | 4/21/2022 | Partial Approval | AMY COLIN |
| MERV13>=Final | 4/21/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 4/21/2022 | Approved | AMY COLIN |
| Final | 5/17/2022 | OK to Issue CofO | AMY COLIN |