5441 W BLACKWELDER ST 90016

Certificate Information: 5441 W BLACKWELDER ST 90016

Application / Permit
20010-10000-01989
Plan Check / Job No.
B20LA10375
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
3 UNITS SMALL LOT SUBDIVISION. PARCEL A. Unit 1 OF 3
Permit Issued
Issued on 1/31/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 JOHNNY WU
Corrections Issued 7/22/2020 JOHNNY WU
Quality Review Completed 7/27/2020 KESETE HAREGOT
Applicant returned to address corrections 8/21/2020 JOHNNY WU
Applicant returned to address corrections 11/19/2020 JOHNNY WU
Applicant returned to address corrections 8/2/2021 JOHNNY WU
Applicant returned to address corrections 8/3/2021 JOHNNY WU
Applicant returned to address corrections 8/19/2021 JOHNNY WU
Applicant returned to address corrections 10/22/2021 JOHNNY WU
Applicant returned to address corrections 11/4/2021 JOHNNY WU
Applicant returned to address corrections 11/5/2021 JOHNNY WU
Building Plans Picked Up 11/5/2021 APPLICANT
Applicant returned to address corrections 11/16/2021 JOHNNY WU
Applicant returned to address corrections 11/17/2021 JOHNNY WU
Applicant returned to address corrections 12/23/2021 JOHNNY WU
Applicant returned to address corrections 6/3/2022 JOHNNY WU
Applicant returned to address corrections 7/1/2022 JOHNNY WU
Plan Check Approved 12/9/2022 JOHNNY WU
Issued 1/31/2023 APPLICANT
CofO in Progress 8/6/2025 NICHOLAS LOPEZ
Permit Finaled 8/9/2025 DEROLD HAUFF
CofO Issued 8/9/2025 DEROLD HAUFF
Permit Finaled 8/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/22/2020 JEANIE LAM
Permit Cleared 9/22/2020 JEANIE LAM
Disturb/Remove Protected Trees Cleared 10/31/2020 JOHNNY WU
Eng Process Fee Ord 176,300 Cleared 11/30/2020 JEANIE LAM
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Highway dedication Cleared 12/17/2020 JEANIE LAM
Low Impact Development Cleared 1/21/2021 MARTIN FRAGOSO
Trees in Parkway Cleared 1/28/2021 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 6/8/2021 ANACANY HURTADO
ZA Case Cleared 6/8/2021 ANACANY HURTADO
ZA Case Cleared 6/8/2021 ANACANY HURTADO
Roof/Waste drainage to street Cleared 8/20/2021 JEANIE LAM
Sewer availability Cleared 8/27/2021 JEANIE LAM
Miscellaneous Cleared 11/18/2022 TERRY PHAN

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Landmark Building & Design Inc; Lic. No.: 982610-B 4717 VAN NUYS BLVD STE 104      SHERMAN OAKS, CA 91403
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/22/2023 Approved JOSE AVILA
Underground Mechanical 5/24/2023 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 6/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 6/6/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 6/9/2023 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 6/28/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval JOSE AVILA
Deputy Wood Construction 7/31/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 8/21/2023 Corrections Issued JOSE AVILA
Deputy Wood Construction 8/30/2023 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 9/5/2023 Partial Approval JOSE AVILA
Deputy Wood Construction 9/28/2023 Conditional Approval JOSE AVILA
HVAC-Rough 12/12/2023 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Rough 1/24/2024 Approved STUART CHAPMAN
HVAC-Rough 1/24/2024 Approved STUART CHAPMAN
PLUMBING-Rough 1/24/2024 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Partial Approval STUART CHAPMAN
Insulation 3/26/2024 Conditional Approval JOSH MEISTER
BUILDING-Rough-Frame 4/2/2024 Approved RICHARD DOCKUS
Green Building Rough 4/2/2024 Not Ready for Inspection RICHARD DOCKUS
Verify Sprinkler Sign Off 4/2/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 4/24/2024 Corrections Issued AMIR NAZARIAN
Insulation 4/30/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 4/30/2024 Approved AMIR NAZARIAN
Drywall Nailing 5/3/2024 Approved ENRIQUE MIRELES
Drywall Nailing 5/8/2024 Approved SCOTT FINNILA
Green Building Rough 5/8/2024 Approved SCOTT FINNILA
Underground Mechanical 10/18/2024 Approved ARTHUR NEGRETE
Service/Power Release 11/18/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 11/20/2024 Approved ENRIQUE MIRELES
Final 11/20/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 11/20/2024 Approved ENRIQUE MIRELES
HVAC-Final 11/20/2024 Approved ENRIQUE MIRELES
PLUMBING-Final 11/20/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 11/20/2024 Approved ENRIQUE MIRELES
Pre-Inspection 12/11/2024 Corrections Issued BRENDAN MORELLI
Service/Power Release 1/15/2025 Corrections Issued NICHOLAS LOPEZ
Special/Order Compliance 1/15/2025 Corrections Issued NICHOLAS LOPEZ
Service/Power Release 1/24/2025 Approved NICHOLAS LOPEZ
Final 4/24/2025 Corrections Issued NICHOLAS LOPEZ
Final 8/5/2025 OK to Issue CofO NICHOLAS LOPEZ