6211 N KLUMP AVE 91606
Certificate Information: 6211 N KLUMP AVE 91606
- Application / Permit
- 20010-10000-01978
- Plan Check / Job No.
- B20LA10279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADU ATTACHED TO (E) DETACHED GARAGE. WTIH LAUNDRY AND BATHROOM ACCESSIBLE FROM THE OUTSIDE FOR SWIMMING POOL AND ATTACHED LATTICE ROOF PATIO.
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2020 | LUKE GONZALES |
| Corrections Issued | 8/10/2020 | LUKE GONZALES |
| Issued | 8/17/2020 | APPLICANT |
| Building Plans Picked Up | 8/17/2020 | APPLICANT |
| CofO in Progress | 3/18/2021 | DANIEL DREW |
| CofO in Progress | 4/5/2021 | DANIEL DREW |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/23/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 6/23/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/23/2020 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 7/30/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/3/2020 | Partial Approval | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 9/9/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 9/9/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2020 | Partial Approval | DANIEL DREW |
| BUILDING-Rough-Frame | 10/1/2020 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2020 | Approved | DANIEL DREW |
| Green Building Rough | 10/1/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 10/7/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/21/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 10/21/2020 | Approved | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 10/21/2020 | Not Ready for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 11/4/2020 | Approved | DANIEL DREW |
| Green Building Rough | 11/4/2020 | Approved | DANIEL DREW |
| HVAC-Rough | 11/4/2020 | Approved | DANIEL DREW |
| Insulation | 11/4/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 11/25/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/25/2020 | Approved | MICHEL ABAJAN |
| Shower Pan | 11/25/2020 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 11/25/2020 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/3/2020 | Approved | DANIEL DREW |
| Sewer | 12/3/2020 | Approved | DANIEL DREW |
| Final | 2/18/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 2/18/2021 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 2/18/2021 | SGSOV Not Ready | DANIEL DREW |
| Smoke Detectors | 2/18/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 3/4/2021 | Approved | DANIEL DREW |
| Pre-Inspection | 3/4/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | DANIEL DREW |
| Final | 3/18/2021 | OK to Issue CofO | DANIEL DREW |
| Green Building Final | 3/18/2021 | Approved | DANIEL DREW |
| Service/Power Release | 3/24/2021 | Corrections Issued | DANIEL DREW |
| Final | 4/1/2021 | OK to Issue CofO | DANIEL DREW |
| Service/Power Release | 4/1/2021 | Approved | DANIEL DREW |