1161 E ADAMS BLVD 90011
Certificate Information: 1161 E ADAMS BLVD 90011
- Application / Permit
- 20010-10000-01966
- Plan Check / Job No.
- B20LA10217
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY ADU PER ORDINANCE
- Permit Issued
- Issued on 9/1/2021
- Issuing Office
- Current Status
- CofO Issued on 9/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | CARLOS MONTES |
| Corrections Issued | 7/9/2020 | CARLOS MONTES |
| Quality Review Completed | 7/28/2020 | PRANITA SHAH |
| Building Plans Picked Up | 8/10/2020 | APPLICANT |
| Plan Check Approved | 7/28/2021 | CARLOS MONTES |
| Issued | 9/1/2021 | APPLICANT |
| CofO in Progress | 8/31/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/2/2022 | DEROLD HAUFF |
| CofO Issued | 9/2/2022 | DEROLD HAUFF |
| Permit Finaled | 9/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 8/31/2020 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/7/2021 | CARLOS MONTES |
| Roof/Waste drainage to street | Cleared | 7/19/2021 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 1/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 1/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 1/11/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 2/2/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 2/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 2/4/2022 | Conditional Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 4/28/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 5/3/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/3/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/3/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 5/3/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 6/7/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Gas Test | 6/13/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Final | 8/10/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/10/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 8/10/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 8/10/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/10/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/10/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/16/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Green Building Final | 8/16/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/16/2022 | Approved | JOAQUIN GREENOUGH |