1161 E ADAMS BLVD 90011

Certificate Information: 1161 E ADAMS BLVD 90011

Application / Permit
20010-10000-01966
Plan Check / Job No.
B20LA10217
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ADU PER ORDINANCE
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 9/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 CARLOS MONTES
Corrections Issued 7/9/2020 CARLOS MONTES
Quality Review Completed 7/28/2020 PRANITA SHAH
Building Plans Picked Up 8/10/2020 APPLICANT
Plan Check Approved 7/28/2021 CARLOS MONTES
Issued 9/1/2021 APPLICANT
CofO in Progress 8/31/2022 JOAQUIN GREENOUGH
Permit Finaled 9/2/2022 DEROLD HAUFF
CofO Issued 9/2/2022 DEROLD HAUFF
Permit Finaled 9/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 8/31/2020 ERIK BEASLEY
Sewer availability Cleared 8/31/2020 ERIK BEASLEY
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 6/7/2021 CARLOS MONTES
Roof/Waste drainage to street Cleared 7/19/2021 CHINH DINH

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/6/2022 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 1/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 1/6/2022 Partial Approval JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 1/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/11/2022 Partial Approval JOAQUIN GREENOUGH
Insulation 1/11/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 2/2/2022 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 2/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Wood Construction 2/4/2022 Conditional Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 3/21/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 3/21/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/28/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 4/28/2022 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/3/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 5/3/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 5/3/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/3/2022 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 5/3/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/9/2022 Approved JOAQUIN GREENOUGH
Insulation 5/9/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 5/16/2022 Approved JOAQUIN GREENOUGH
Gas Test 6/7/2022 Corrections Issued JOAQUIN GREENOUGH
Gas Test 6/13/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Final 8/10/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/10/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 8/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 8/10/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 8/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 8/10/2022 Approved ALIZAH MAYAGOITIA
Final 8/16/2022 OK to Issue CofO JOAQUIN GREENOUGH
Green Building Final 8/16/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 8/16/2022 Approved JOAQUIN GREENOUGH