1056 N OBAN DR 90065

Certificate Information: 1056 N OBAN DR 90065

Application / Permit
20010-10000-01943
Plan Check / Job No.
B20LA10073
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO-CAR GARAGE 1 OF 3
Permit Issued
Issued on 8/16/2022
Issuing Office
Metro
Current Status
Issued on 8/16/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/9/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 DANIEL YIP
Corrections Issued 7/2/2020 DANIEL YIP
Quality Review Completed 7/22/2020 HERNAN ARREOLA
Building Plans Picked Up 8/3/2020 APPLICANT
Applicant returned to address corrections 10/19/2020 DANIEL YIP
Applicant returned to address corrections 6/7/2022 DANIEL YIP
Plan Check Approved 6/24/2022 DANIEL YIP
Issued 8/16/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/31/2020 ELENA LOPEZ
BHO/Hillside ordinance Cleared 8/31/2020 ELENA LOPEZ
BHO/Hillside ordinance Cleared 8/31/2020 ELENA LOPEZ
BHO/Hillside ordinance Cleared 8/31/2020 ELENA LOPEZ
BHO/Hillside ordinance Cleared 8/31/2020 ELENA LOPEZ
Permit Cleared 8/31/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/9/2020 ELENA LOPEZ
Sewer availability Cleared 9/9/2020 ELENA LOPEZ
Hydrant and Access approval Cleared 9/24/2020 KURT CORRAL
Low Impact Development Cleared 10/7/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/6/2021 CELINA MORENO
Specific Plan Cleared 1/7/2021 ANNA VIDAL
BHO/Hillside ordinance Cleared 1/8/2021 CELINA MORENO
Excavation more than 5-ft deep Cleared 4/13/2021 CALOSHA APPROVED
GPI Written Notices Cleared 4/13/2021 DANIEL YIP
Grading Pre-Inspection Cleared 4/13/2021 DANIEL YIP
Green Code Cleared 4/13/2021 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2024 Corrections Issued THOMAS LOGRASSO
Piling/Pier/Caisson 10/3/2024 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 10/9/2024 Not Ready for Inspection THOMAS LOGRASSO
Piling/Pier/Caisson 10/9/2024 Not Ready for Inspection THOMAS LOGRASSO
Piling/Pier/Caisson 10/11/2024 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/11/2025 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 2/11/2025 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/25/2025 Partial Approval WILLIAM SIERRA
Deputy Shotcrete 6/11/2025 Conditional Approval NICHOLAS LOPEZ
Sewer 7/2/2025 Approved NICHOLAS LOPEZ
Special/Order Compliance 7/2/2025 Corrections Issued NICHOLAS LOPEZ
Special/Order Compliance 8/20/2025 Corrections Issued NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 10/17/2025 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 10/17/2025 Approved NICHOLAS LOPEZ