4617 S HOOPER AVE 90011
Certificate Information: 4617 S HOOPER AVE 90011
- Application / Permit
- 20010-10000-01920
- Plan Check / Job No.
- B20LA09919
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD 2 OF 2
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- CofO Issued on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2020 | CARLOS MONTES |
| Corrections Issued | 6/25/2020 | CARLOS MONTES |
| Quality Review Completed | 7/30/2020 | PRANITA SHAH |
| Plan Check Approved | 3/8/2021 | CARLOS MONTES |
| Issued | 4/16/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 3/11/2022 | JOAQUIN GREENOUGH |
| CofO in Progress | 3/11/2022 | JOAQUIN GREENOUGH |
| CofO in Progress | 3/21/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 3/24/2022 | DEROLD HAUFF |
| CofO Issued | 3/24/2022 | DEROLD HAUFF |
| Permit Finaled | 3/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/23/2020 | CECILIO NAVARRO |
| Frnt yard landscape/Water mgmt | Cleared | 10/1/2020 | MAXFIELD VERMY |
| Highway dedication | Cleared | 10/7/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/19/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 2/25/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/8/2021 | ROSA SILVA |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/29/2021 | Partial Approval | ROBERT MCDOWELL |
| Underground Mechanical | 4/29/2021 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 5/6/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/14/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 7/14/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/14/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/14/2021 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 7/14/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/25/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/25/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/25/2021 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/30/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 9/3/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 9/3/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 9/3/2021 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 9/28/2021 | Approved | JOAQUIN GREENOUGH |
| Sewer | 9/28/2021 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| Verify Rec and Parks Fee Memo | 11/5/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 1/4/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 1/4/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 1/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 1/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 1/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 1/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 1/20/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 1/20/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 1/20/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 1/20/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 3/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Service/Power Release | 3/4/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 3/10/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 3/11/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 3/21/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Service/Power Release | 3/21/2022 | Approved | JOAQUIN GREENOUGH |