1664 N BENTON WAY 90026
Certificate Information: 1664 N BENTON WAY 90026
- Application / Permit
- 20010-10000-01887
- Plan Check / Job No.
- B20LA09787
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW STATE-APPROVED FACTORY BUILT HOUSE FOR DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33. 1 OF 2 **See comments for Change of Address**
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Corrected on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | JOHNNY WU |
| Corrections Issued | 7/15/2020 | JOHNNY WU |
| Quality Review Completed | 7/23/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 7/27/2020 | APPLICANT |
| Applicant returned to address corrections | 8/20/2020 | JOHNNY WU |
| Applicant returned to address corrections | 8/10/2021 | JOHNNY WU |
| Applicant returned to address corrections | 8/11/2021 | JOHNNY WU |
| Plan Check Approved | 8/11/2021 | JOHNNY WU |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 1/3/2023 | STUART CHAPMAN |
| CofO Issued-Status Void | 2/7/2023 | DEROLD HAUFF |
| Permit Finaled-Status Void | 2/7/2023 | DEROLD HAUFF |
| Re-Activate Permit | 10/2/2023 | DEROLD HAUFF |
| CofO Corrected | 10/4/2023 | DEROLD HAUFF |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/15/2020 | JOHNNY WU |
| Address approval | Cleared | 8/11/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | ELAINE LEI |
| Sewer availability | Cleared | 8/11/2020 | ELAINE LEI |
| Green Code | Cleared | 8/20/2020 | JOHNNY WU |
| GPI Written Notices | Cleared | 9/18/2020 | JOHNNY WU |
| Hydrant and Access approval | Cleared | 6/7/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 7/14/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/19/2021 | WALLIE JONG |
Contact Information
| Contractor | Cover Building Technologies; Lic. No.: 1039029-B | 1219 W 135TH STREET GARDENA, CA 90247 |
| Engineer | , ; Lic. No.: C89133 | 5900 CANTERBURY DR APT A206 CULVER CITY, CA 90230 |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/7/2022 | Partial Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 4/20/2022 | Partial Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 5/19/2022 | No Access for Inspection | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 6/9/2022 | Conditional Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 6/9/2022 | Partial Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 6/14/2022 | Approved | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 7/6/2022 | Conditional Approval | THOMAS LOGRASSO |
| Underground Mechanical | 7/15/2022 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 7/19/2022 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 8/30/2022 | Partial Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 8/30/2022 | Partial Approval | THOMAS LOGRASSO |
| Final | 12/21/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/21/2022 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Final | 12/21/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 12/21/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 12/21/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 12/21/2022 | Approved | THOMAS LOGRASSO |
| Final | 12/29/2022 | OK for TCO | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/29/2022 | Approved | STUART CHAPMAN |
| Green Building Final | 12/29/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 12/29/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 12/30/2022 | Approved | STUART CHAPMAN |
| Final | 12/30/2022 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 12/30/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 12/30/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 1/24/2023 | Approved | STUART CHAPMAN |