201-201 1/2 E 69TH ST 90003

Certificate Information: 201-201 1/2 E 69TH ST 90003

Application / Permit
20010-10000-01873
Plan Check / Job No.
B20LA09684
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 2-story duplex with attached garages for three cars.
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 9/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 RODOLFO ARIAS
Corrections Issued 7/13/2020 RODOLFO ARIAS
Quality Review Completed 7/16/2020 EUGENE BARBEAU
Building Plans Picked Up 8/28/2020 APPLICANT
Applicant returned to address corrections 12/22/2020 RODOLFO ARIAS
Applicant returned to address corrections 1/21/2021 RODOLFO ARIAS
Plan Check Approved 2/10/2021 RODOLFO ARIAS
Issued 3/1/2021 APPLICANT
CofO in Progress 9/10/2021 ALEJANDRO DE ARTOLA
Permit Finaled 9/11/2021 DEROLD HAUFF
CofO Issued 9/11/2021 DEROLD HAUFF
Permit Finaled 9/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
Address approval Cleared 9/25/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/25/2020 THOMAS LANG
Highway dedication Cleared 9/25/2020 THOMAS LANG
Sewer availability Cleared 9/25/2020 THOMAS LANG
Low Impact Development Cleared 10/26/2020 YVAINNE GALSIM
Permit Cleared 10/27/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 10/27/2020 CELINA MORENO
Trees in Parkway Cleared 12/3/2020 JOHN KIM
Green Code Cleared 1/21/2021 RODOLFO ARIAS

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/25/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 4/12/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Partial Approval EUGENE CASSIDY
Insulation 4/13/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/28/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/28/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/28/2021 Approved EUGENE CASSIDY
Green Building Rough 5/28/2021 Approved EUGENE CASSIDY
HVAC-Rough 5/28/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 5/28/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 5/28/2021 Approved EUGENE CASSIDY
Insulation 6/1/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 6/14/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/14/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/11/2021 Approved ALEJANDRO DE ARTOLA
Final 8/11/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/11/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 8/11/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/11/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/11/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/11/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/11/2021 Approved ALEJANDRO DE ARTOLA
Final 9/1/2021 Corrections Issued JOAQUIN GREENOUGH
Final 9/9/2021 OK to Issue CofO ALEJANDRO DE ARTOLA