226-228 E 104TH ST 90003

Certificate Information: 226-228 E 104TH ST 90003

Application / Permit
20010-10000-01872
Plan Check / Job No.
B20LA09683
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 11/23/2020
Issuing Office
Current Status
CofO Issued on 6/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 PRANITA SHAH
Corrections Issued 7/27/2020 PRANITA SHAH
Quality Review Completed 8/7/2020 MINYE PAK
Building Plans Picked Up 8/12/2020 APPLICANT
Applicant returned to address corrections 11/18/2020 PRANITA SHAH
Plan Check Approved 11/19/2020 PRANITA SHAH
Issued 11/23/2020 APPLICANT
CofO in Progress 5/26/2021 EUGENE CASSIDY
Permit Finaled 6/17/2021 DEROLD HAUFF
CofO Issued 6/17/2021 DEROLD HAUFF
Permit Finaled 6/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 8/20/2020 TERRI OSBORNE
Trees in Parkway Cleared 8/20/2020 JOHN KIM
Address approval Cleared 8/24/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/25/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Sewer availability Cleared 8/26/2020 CECILIO NAVARRO
Low Impact Development Cleared 9/25/2020 YVAINNE GALSIM
Permit Cleared 9/28/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 9/28/2020 CELINA MORENO
Green Code Cleared 11/7/2020 PRANITA SHAH

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 1/7/2021 Partial Approval EUGENE CASSIDY
Sewer 1/7/2021 Approved EUGENE CASSIDY
Underground Mechanical 1/7/2021 Approved EUGENE CASSIDY
Wood Frame 1/7/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval JOHN KLARIN
Insulation 1/11/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 2/18/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 2/18/2021 Approved EUGENE CASSIDY
Green Building Rough 2/18/2021 Approved EUGENE CASSIDY
HVAC-Rough 2/18/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 2/18/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 2/18/2021 Approved EUGENE CASSIDY
Insulation 2/23/2021 Approved EUGENE CASSIDY
Drywall Nailing 3/4/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/4/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 5/25/2021 Approved EUGENE CASSIDY
Final 5/25/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 5/25/2021 Approved EUGENE CASSIDY
HVAC-Final 5/25/2021 Approved EUGENE CASSIDY
PLUMBING-Final 5/25/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/25/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 5/25/2021 Approved EUGENE CASSIDY
Smoke Detectors 5/25/2021 Approved EUGENE CASSIDY