3492 1/2 E 4TH ST 90063
Certificate Information: 3492 1/2 E 4TH ST 90063
- Application / Permit
- 20010-10000-01811
- Plan Check / Job No.
- B20LA09480
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1-STORY 26'6"X26'9" DETACHED ADU PER WFPP
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 2/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 6/24/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 8/13/2020 | TU HUA |
| Applicant returned to address corrections | 1/21/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 2/23/2022 | CRYSTEL MAALOUF |
| Issued | 4/5/2022 | APPLICANT |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| CofO in Progress | 2/14/2023 | FREDDIE RIVERA |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
| CofO Issued | 2/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2020 | WALLIE JONG |
| Clean Up Green Up | Cleared | 11/20/2020 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/7/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 12/27/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 2/3/2022 | KHOUNG LE |
| Green Code | Cleared | 2/23/2022 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/21/2022 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/17/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/3/2022 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 8/3/2022 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 8/3/2022 | Partial Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 8/8/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/8/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 8/8/2022 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 8/8/2022 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 8/8/2022 | Approved | FREDDIE RIVERA |
| Insulation | 8/10/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 8/25/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/25/2022 | Approved | FREDDIE RIVERA |
| Service/Power Release | 10/17/2022 | Partial Inspection | FREDDIE RIVERA |
| Underground Mechanical | 10/17/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/10/2022 | Approved | FREDDIE RIVERA |
| Final | 11/10/2022 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 11/10/2022 | Approved | FREDDIE RIVERA |
| Green Building Final | 11/10/2022 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 11/10/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 11/10/2022 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 11/10/2022 | Approved | FREDDIE RIVERA |
| Final | 12/23/2022 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | FREDDIE RIVERA |
| Final | 2/14/2023 | OK to Issue CofO | FREDDIE RIVERA |