3492 1/2 E 4TH ST 90063

Certificate Information: 3492 1/2 E 4TH ST 90063

Application / Permit
20010-10000-01811
Plan Check / Job No.
B20LA09480
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1-STORY 26'6"X26'9" DETACHED ADU PER WFPP
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 CRYSTEL MAALOUF
Corrections Issued 6/24/2020 CRYSTEL MAALOUF
Quality Review Completed 8/13/2020 TU HUA
Applicant returned to address corrections 1/21/2022 CRYSTEL MAALOUF
Plan Check Approved 2/23/2022 CRYSTEL MAALOUF
Issued 4/5/2022 APPLICANT
Building Plans Picked Up 4/11/2022 APPLICANT
CofO in Progress 2/14/2023 FREDDIE RIVERA
Permit Finaled 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/20/2020 WALLIE JONG
Clean Up Green Up Cleared 11/20/2020 RUBEN VASQUEZ
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 12/8/2020 WALLIE JONG
Sewer availability Cleared 9/7/2021 WALLIE JONG
Low Impact Development Cleared 12/27/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 2/3/2022 KHOUNG LE
Green Code Cleared 2/23/2022 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/21/2022 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/17/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 8/3/2022 Not Ready for Inspection RUBEN SALAS
HVAC-Rough 8/3/2022 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 8/3/2022 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 8/8/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 8/8/2022 Approved FREDDIE RIVERA
Green Building Rough 8/8/2022 Approved FREDDIE RIVERA
MERV13>=Rough 8/8/2022 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 8/8/2022 Approved FREDDIE RIVERA
Insulation 8/10/2022 Approved FREDDIE RIVERA
Drywall Nailing 8/25/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 8/25/2022 Approved FREDDIE RIVERA
Service/Power Release 10/17/2022 Partial Inspection FREDDIE RIVERA
Underground Mechanical 10/17/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/10/2022 Approved FREDDIE RIVERA
Final 11/10/2022 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 11/10/2022 Approved FREDDIE RIVERA
Green Building Final 11/10/2022 Approved FREDDIE RIVERA
MERV13>=Final 11/10/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 11/10/2022 Approved FREDDIE RIVERA
Smoke Detectors 11/10/2022 Approved FREDDIE RIVERA
Final 12/23/2022 Conditional Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Approved FREDDIE RIVERA
Final 2/14/2023 OK to Issue CofO FREDDIE RIVERA